Additional Insureds Owed a Defense in Underlying Personal Injury Suit
March 03, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted partial summary judgment on the duty to defend to two additional insureds who were named as defendants in the underlying personal injury suit. In re Third St. Equity, LLC, 2025 U.S. Dist. LEXIS 234909 (E.D. N. Y. Dec. 2, 2025).
Third Street Equity LLD hired Developing NY State, LLC as the contractor for a construction project. Developing NY entered a subcontract agreement with Capital Source Concrete NY LLC for concrete work as well as labor and services for a construction project. The subcontract required that Capital Concrete keep the construction site free of debris, waste material or rubbish. Further, Capital Concrete was responsible for compliance with OSHA safety regulations. It was also agreed that Capital Concrete would obtain liability and workers compensation insurance naming Third Street and Developing NY as additional insureds.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Appraisal Award Upheld Despite Insurer’s Contention that Causation was Considered
February 23, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court in Tennessee granted the insured’s motion for summary judgment finding the appraisal award was properly determined despite the insurer’s argument that the appraisal panel considered causation of the loss. Nashville Communications, Inc. v. Auto-Owners (Mutual) Ins. Co., 2025 U.S. Dist. LEXIS 223455 (M.D. Tenn. Nov. 13, 2025)
A windstorm struck and damaged the building owned and insured by Nashville Communications (NashComm). A claim was submitted to the insurer, Auto-Owners, for damage to the roof and interior water leakage. Auto-Owners acknowledged that there was some amount of wind damage to the building from the wind event.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Substantial Evidence of Flood Loss is Not a Substitute for Required Proof of Loss
April 20, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe court found that the insurer properly denied the insured’s claim for loss due to flood because a proof of loss was never submitted. Bay Haven at Coco Bay Condominium Association, Inc. v. Hartford Ins. Co. of the Midwest, 2026 U.S. Dist. LEXIS 6847 (M.D. Fla. Jan. 14, 2026).
Bay Haven managed several condo buildings. When Hurricane Ian hit, it caused significant flood damage to these properties. Bay Haven held federal flood insurance policies through Hartford under “Write-Your-Own” policies. This meant Hartford was essentially a fiscal agent that managed policies and handled claims but paid them using federal funds.
Following the storm, FEMA extended the usual 60-day deadline for filing a proof of loss to one year, or until September 28, 2023. Bay Haven did not submit its proofs of loss until November 2023. FEMA granted an extension but only for the specific amounts in the November requests. Hartford did not waive the 60-day proof of loss requirement for any other proof of loss. Hartford paid the amounts reflected in the November submissions.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Surety Liability Is Coextensive with Its Bond Principal
April 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller act payment bond case, U.S. f/u/b/o Whitetail General Constructors v. Northcon, Inc., 2026 WL 46671 (D.Mont. 2026), contains a short noteworthy discussion as to a surety’s liability being coextensive with that of its bond principal. If you are bonded, or you are pursuing a bond, you need to appreciate this, which is why this is a noteworthy discussion:
A “surety’s liability on a Miller Act bond must be at least coextensive with the obligations imposed by the Act if the bond is to have its intended effect.” “Therefore, ‘the liability of a surety and its principal on a Miller Act payment bond is coextensive with the contractual liability of the principal only to the extent that it is consistent with the rights and obligations created under the Miller Act.’” In other words, “[w]here a subcontract’s terms are consistent with the Miller Act’s provisions, the surety’s liability on the Miller Act bond is coextensive with the contractual liability of its princip[al].”
“The liability of a surety under the Miller Act is controlled by federal law, rather than state contract law[.]” The court may, however, “look to state law when interpreting contractual provisions” in a Miller Act case.
“[T]he measure of recovery under the Miller Act is generally determined by the terms of the subcontract [or underlying contract].”
Northcon, supra, at *4-5 (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Turnover Traps for Community Associations: Investigate First, Release Claims Later
April 14, 2026 —
Nicholas B. Vargo - Ball Janik LLPTurnover of a community association from developer control to owner control is a uniquely vulnerable moment. Developers are increasingly presenting Florida condominium and homeowners’ associations with “standard” settlement or release agreements at turnover, often being framed as routine steps to finalize the transition of control. In reality, these agreements can have sweeping consequences, including the release of construction-defect claims before the association has conducted any meaningful independent evaluation.
The developer has years of project knowledge and access to plans, subcontractors, and internal records. The newly elected board is just beginning to organize, obtain documents, and understand the property’s condition. Many defects, especially those involving roofing, waterproofing, windows, or structural components, are latent and not yet visible. Signing a release at this stage means the association is making a binding decision under conditions of uncertainty, without full information, to release all future potential claims.
Over the last few years, there has been a rise in reports of developers offering a packaged deal: they agree to complete certain repairs, often minor punch-list or cosmetic items, and to “forgive” an alleged financial deficit (often around $50,000) supposedly owed by the association from the developer-control period. In exchange, the association is asked to sign a broad release covering all claims, including known and unknown construction defects. To a new HOA board that received their community with limited operating and reserve funds, they are left with a difficult decision to either accept the developer’s offer or assess their owners to pay this alleged debt.
These agreements are occasionally presented through community management companies, which may describe them as “standard” or "routine.” Whether due to misunderstanding or influence from the developer, management companies can unintentionally reinforce the idea that signing is expected. Any recommendation provided to HOAs about whether to sign these releases could open community management to liability down the road. The best practice for both associations and community managers is to refer any agreements to be reviewed by general counsel for the association.
The following two case studies illustrate the real-world consequences:
Case Study One: A newly transitioned board relies on its management company to negotiate with the developer-builder to resolve irrigation issues, pond concerns, and signage deficiencies, along with forgiving an asserted financial shortfall. In exchange, the board signs a broad release covering all claims, including latent defects.
Within a year, several punch-list items remain incomplete, and more serious issues arise. When the association demands completion, the developer delays, prompting the association to seek advice on how to enforce the settlement agreement. The association hires counsel to hold the developer responsible for both the previously agreed-upon items and newly identified construction defects. However, when the association brings claims against the developer, the developer points to the release of all potential construction defects in the community. Thus, the only remaining remedy is limited to enforcement of the specific punch-list terms. The community, still relatively new, has no viable claims against the developer-builder for the construction defects. With warranties expired and the release, the association must fund repairs through special assessments, despite defects that would otherwise have been actionable.
Case Study Two: A community is presented with a similar agreement as above. The management company encourages execution, suggesting it is standard and even telling the board to “name your price.” The developer also pressures the newly elected board to sign.
Instead of signing, the board consults with their attorney. Counsel advises the board not to sign the release and recommends further investigation. Engineers are retained and identify early indicators of broader issues, including stucco cracking, water intrusion, and irrigation deficiencies. Based on this information, the association declines to sign the release. Subsequent evaluation reveals potentially significant construction-defect claims, allowing the community to pursue recovery that would have been lost under the proposed agreement.
These scenarios underscore a fundamental point: signing a release at turnover is not an administrative formality—it is a major legal decision. Board members act in a fiduciary capacity on behalf of their community, and their decisions can bind all current and future owners. At turnover, an association’s right is to investigate and pursue claims. Preserving that right until a full and independent evaluation is completed is not adversarial—it is responsible governance.
Accordingly, associations should retain independent evaluations of the property and consult qualified legal counsel before signing any “standard” agreements, especially ones involving a release of future claims.
Nicholas B. Vargo is a partner in Ball Janik LLP’s Construction Practice Group. He may be reached at nvargo@balljanik.com.
Construction Liens and the “Substantial Performance” Doctrine
April 08, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn a recent case dealing with a construction lien, the driving issue was whether the air conditioning contractor “substantially performed” before recording its construction lien against residential property. The importance here pertains to the substantial performance doctrine with respect to construction liens. The Third District Court of Appeal explained, with relevant citations, this doctrine as follows:
Under Florida law, a contractor is entitled to a mechanic’s lien if he complies with all provisions of Chapter 713, governing construction liens, and “has substantially performed the contract.” Grant v. Wester, 679 So. 2d 1301, 1307 (Fla. 1st DCA 1996) (quotation omitted); Langley v. Knowles, 958 So. 2d 1149, 1151 (Fla. 5th DCA 2007) (“The substantial performance doctrine recognizes that a contactor who complies with all of the provisions of the contactor’s lien statute is entitled to enforce a lien if he has substantially, but not completely, performed his contractual obligations.”). Substantial performance is performance “so nearly equivalent to what was bargained for that it would be unreasonable to deny the promisee the full contract price subject to the promisor’s right to recover whatever damages may have been occasioned him by the promisee’s failure to render full performance.” Ocean Ridge Dev. Corp. v. Quality Plastering, Inc., 247 So. 2d 72, 75 (Fla. 4th DCA 1971).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Bona Fide Dispute Defeats Violation of Prompt Payment Act
June 15, 2026 —
David Adelstein - Florida Construction Legal UpdatesMost, if not all, jurisdictions, including the federal government, have what is known as a “Prompt Payment Act.” The objective is to ensure prompt payment. If prompt payment is not made, the Prompt Payment Act provides for interest penalties, as well as potentially other costs such as attorney’s fees.
But the thing is, it’s not as simple as untimely payment to support the recourse and interest penalties the applicable Prompt Payment Act affords. And the teeth associated with the applicable Prompt Payment Act are not as sharp as perhaps the party claiming untimely payment prefers.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
A Permitting Base Checklist for Data Centers and Power Plants
June 02, 2026 —
Michael S. McDonough, Stephen J. Humes & Stacey C. Wright - Gravel2Gavel Construction & Real Estate Law BlogThere is a lot of talk these days about “license to operate” for data centers, meaning management of the relationships with stakeholders and broader communities concerning both the benefits and adverse consequences of locating a facility in a particular locale. Here, we are speaking of “license to operate” more literally—namely, the legal and regulatory permitting and approval requirements for a privately owned data center whether by itself or colocated with a power generating plant.
Our Base Checklist includes generally and potentially applicable permitting requirements for development and operation, using California as an example. (Taking legal authority Frank Sinatra out of context, “If you can make it there, you can make it anywhere.”) The actual requirements for a given facility would depend, in part, on local law, including planning and zoning laws and plans, and the environment of the site. Just as examples, additional permitting and mitigation requirements might apply if sensitive receptors are located nearby (e.g., noise mitigation for residential dwellings), if sensitive and protected biological resources (e.g., jurisdictional waters and/or protected species) would be impacted, or if the present or former land uses require additional measures (e.g., hazardous materials remediation, mitigation for conversion of prime farmland, or protection of cultural resources). The scope of permit requirements would ultimately be determined by the applicable regulatory agencies and by the lead and responsible agencies under the applicable state environmental land use regime—in our reference case here, the California Environmental Quality Act (CEQA).
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Stephen J. Humes, Pillsbury and
Stacey C. Wright, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. Wright may be contacted at stephen.humes@pillsburylaw.com
Read the full story...