Wadsworth v. Regional Rail Partners — Verified Statements of Claim Under the Colorado Public Works Act
August 25, 2026 —
Olivia Barden - Colorado Construction Litigation BlogEditor’s Note: Wadsworth Revisited
In August 2024, following the Colorado Court of Appeals’ decision in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, we published
Colorado Court of Appeals’ Ruling Highlights Dangers of Excessive Public Works Claims.
At the time, the decision warranted a significant warning to contractors and subcontractors performing public work in Colorado. The Court of Appeals concluded that Wadsworth’s verified statement of claim improperly included unliquidated delay damages and that, because the claim was excessive, Wadsworth forfeited its right to recover the amounts included in the claim. We cautioned contractors to carefully scrutinize verified statements of claim and to avoid including unliquidated damages or amounts that were not yet due and payable.
The Colorado Supreme Court has now reversed that decision.
Read the full story...Reprinted courtesy of
Olivia Barden, Higgins, Hopkins, McLain & Roswell, LLC
Four Families Now Live in the Season Six Rock the Block Homes in Grantsville, Utah
April 20, 2026 —
Hamlet HomesSALT LAKE CITY, April 20, 2026 /PRNewswire/ -- The premier of Rock the Block season seven aired last Monday and is set in Las Vegas, Nevada. Rock The Block is HGTV's highest rated show. Last year, season six was set in Utah and had HGTV's highest rating yet, with over 14 million viewers. All episodes of season six were filmed in the Worthington Ranch community in Grantsville, Utah. The four homes on the show were built by Utah builder Hamlet Homes. During the show, the location of the four Rock The Block homes had to be kept secret and were surrounded by a locked gate. After over a year of being inaccessible, the Utah public was invited in May 2025 to tour the homes and help raise money together for charity. On May 30-31, 2025, Hamlet hosted a 'Rock The Block Party' where the public was able to walk through the homes made famous by the show.
Hamlet Owner, VP of Marketing & Design Tami Ostmark shares stories from the show and her perspective of what it's like to be the builder on a national show like this. Ostmark was on set almost the entire time. "As expected, there were times when there was tension on the set. All four designers were super competitive with each other. It's amazing that the production team was able to produce the show as well as they did. I'm very impressed," said Ostmark.
Another interesting point related to the show is how much work the local builder is responsible for. Some nights as many as 30 Hamlet team members worked through the night to keep up with the pace of production. "Each designer provided their own trusted carpenters to do finishing work. In two of the cases, designers' flew their favorite carpenters in to carry out their visions. Given the quick turnaround, it's not always practical for finishing work to be permanent. Sometimes, it just needs to look appealing on camera," said Ostmark. This is frequently referred to as 'TV Magic'. "When the show was over, Hamlet re-did any areas that required extra attention". The show really does shoot in only 7 weeks as depicted. This creates a fast pace that was very exciting to be a part of", continued Ostmark. All four of the homes featured on the show have since been purchased; four Utah families currently call them home.
ABOUT HAMLET HOMES
Hamlet Homes (www.hamlethomes.com) crafts quality customer-oriented townhomes and single-family homes located in attractively designed communities in Utah and Idaho. Since the company's founding in 1995, Hamlet has built over 5,000 homes in 80 communities. The company is a proud recipient of many awards on Sustainable Business & Design, Quality Builder Awards; recognized both locally and nationally. Named by the Salt Lake Chamber of Commerce as the 'Veteran Owned Small Business of the Year, in 2019'. Hamlet has since been named several times to the Professional Builder's Housing Giants List and annual HOME AWARDS Best Customer Experience. Most recently in 2026, Hamlet was named Utah's 'Best of State for Real Estate Development and Utah Businesses 'Best Companies to Work For' for the 6th consecutive year.
Los Angeles Times Ranks Lewis Brisbois Third Largest Firm in LA County, Largest for Litigation
June 08, 2026 —
Lewis BrisboisThe Los Angeles Times has ranked Lewis Brisbois the third largest firm in LA County by attorney headcount, and first for number of litigation attorneys.
Lewis Brisbois, whose Los Angeles office is led by Co-Managing Partners Jana I. Lubert and Kathleen Walker, has 273 attorneys working in LA County, including 167 partners.
The firm ranked No. 1 for Litigation in the county, with 206 attorneys under the leadership of Partner Craig Holden.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Powering Data Centers in a Moving Regulatory Landscape: Positioning Deals Before FERC’s Next Move
April 27, 2026 —
Stephen J. Humes, Alicia M. McKnight & Andrew H. Jacobs - Gravel2Gavel Construction & Real Estate Law BlogThe explosive growth of data‑center load—driven by artificial intelligence, cloud computing and the expansion of digital infrastructure across industries—has forced U.S. energy regulators into unfamiliar territory. Nowhere is this more evident than at the Federal Energy Regulatory Commission (FERC), which is actively considering how large, concentrated loads can be powered without compromising grid reliability or shifting costs to other customers.
FERC has not yet issued a standalone rulemaking on data centers. But make no mistake, the regulatory framework is quietly and deliberately being built. For developers, hyperscalers, utilities and investors, the period before FERC finalizes its next round of decisions represents the critical window to crystallize advocacy and structure transactions in ways that anticipate regulatory change.
Reprinted courtesy of
Stephen J. Humes, Pillsbury,
Alicia M. McKnight, Pillsbury and
Andrew H. Jacobs, Pillsbury
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Jacobs may be contacted at andrew.jacobs@pillsburylaw.com
Read the full story...
The Seventh Circuit Rejects Navigators Insurance Company’s Attempt to Escape Additional Insured Coverage For a Gas Explosion
March 24, 2026 —
Kyle A. Rudolph & Anna M. Perry - Saxe Doernberger & Vita, P.C.In a recent Seventh Circuit decision, Atlanta Gas Light Company v. Navigators Insurance Company, the court addressed a theme that policyholders are often confronted with by insurers
[1] – insurers disputing additional insured coverage where the named insured is not named in the underlying action. The court aptly rejected this position since it was undisputed that the bodily injuries alleged in the underlying lawsuits were due to a gas explosion that was “caused, in whole or in part, by” the named insured’s acts or omissions.
I. Background
The additional insureds, Atlanta Gas Light Company and Southern Company Gas (collectively, “AGL”), retained the named insured, United States Infrastructure Corporation (“USIC”), to locate and mark gas lines that AGL owned in Georgia. USIC failed to mark a certain gas line, which was later struck by a boring company, leading to an explosion that injured three people.
Reprinted courtesy of
Kyle A. Rudolph, Saxe Doernberger & Vita, P.C. and
Anna M. Perry, Saxe Doernberger & Vita, P.C.
Mr. Rudolph may be contacted at KRudolph@sdvlaw.com
Ms. Perry may be contacted at APerry@sdvlaw.com
Read the full story...
California Poised for the Most Significant Residential Construction Defect Reforms in Decades
September 01, 2026 —
Thomas D. Fama & Andrew J. Mallon - Wood Smith Henning BermanThe California Legislature is considering legislation that would dramatically alter the landscape of residential construction defect litigation. Assembly Bill 1903, currently pending before the Senate Judiciary Committee, proposes extensive amendments to California's Right to Repair Act (Civil Code sections 895-945.5) that would substantially strengthen procedural protections for builders while narrowing the scope of recoverable construction defect claims.
If enacted, the legislation would affect virtually every stage of a construction defect dispute- from the initial notice of claim through litigation and settlement- and would introduce an entirely new certification process for newly constructed condominium projects. This article details some of the most significant proposed changes.
Higher Burden for Construction Defect Plaintiffs
Perhaps the most consequential change is the bill's modification of the proof required to establish liability. current law generally requires a claimant to demonstrate the residence fails to satisfy one of the statutory performance standards established under the Right to Repair Act. AB1903 would instead require claimants to establish three separate elements:
- A violation of an applicable statutory performance standard;
- The violation caused appreciable, present, non-speculative physical damage to another building component; and
- The violation resulted from the original construction.
Reprinted courtesy of
Thomas D. Fama, Wood Smith Henning Berman and
Andrew J. Mallon, Wood Smith Henning Berman
Mr. Fama may be contacted at tfama@wshblaw.com
Mr. Mallon may be contacted at amallon@wshblaw.com
Read the full story...
Did You Get the Message? (And does it count?) The Legal Consequences of Text Messages, Group Chats, and Informal Digital Communication on Construction Projects
March 17, 2026 —
Kellie Ros & Curtis Martin - ConsensusDocsIntroduction: The New Reality of Construction Communication
Construction projects have always depended on a constant stream of communication. Today’s project managers, superintendents, and foremen have broadened the method of communication to include convenient forms of digital communication. Superintendents text photos of field conditions, owners send quick approvals through WhatsApp, architects clarify design intent in a Teams chat, and subcontractors coordinate sequencing through group texts. These channels are fast, convenient, and deeply embedded in modern project culture. Yet the legal framework governing construction contracts has not evolved at the same pace. Many contracts still assume – or require – that notice, directives, and approvals occur through formal written channels—letters, emails to designated recipients, or structured project‑management platforms. This disconnect creates significant legal risk, particularly for contractors who rely on informal messages as authorization for extra work or schedule changes. Courts are increasingly asked to interpret text messages, chat threads, and screenshots as evidence of notice, direction, or waiver. The outcomes vary, but the trend is unmistakable: informal digital communication is now part of the project record, and it can bind parties in ways they did not expect.
Reprinted courtesy of
Kellie Ros, Peckar & Abramson, P.C. and
Curtis Martin, Peckar & Abramson, P.C.
Ms. Ros may be contacted at kros@pecklaw.com
Mr. Martin may be contacted at cmartin@pecklaw.com
Read the full story...
Colorado Legislature Considers Series of Bills Aimed at Boosting Affordable Housing Construction in Colorado — What Homebuilders Need to Know
April 08, 2026 —
Amanda E. McKinlay - Snell & WilmerOn January 21, 2026, lawmakers introduced a series of bills with the goals of addressing affordable housing issues and incentivizing construction in Colorado.
House Bill 26-1001 (known as the “Housing Opportunities Made Easier ‘HOME’ Act”) concerns the promotion for residential developments on “qualifying properties” that do not contain exempt parcels through the bypassing of often time-consuming local planning processes. Under HB26-1001, a “qualifying property is any real property that contains no more than five acres of land and is owned by: (i) a nonprofit organization with a demonstrated history of providing affordable housing; (ii) a nonprofit organization that provides public transit; (iii) a nonprofit organization that has entered into an agreement with another nonprofit organization with a demonstrated history of providing affordable housing, provided that the agreement requires the nonprofit organization with a demonstrated history of providing affordable housing to develop a residential development on the property; (iv) a school district; (v) a state college or university; (vi) a housing authority; or (vii) a local or regional transit district or a regional transportation authority serving one or more counties.
Read the full story...Reprinted courtesy of
Amanda E. McKinlay, Snell & WilmerMs. McKinlay may be contacted at
amckinlay@swlaw.com