D.C. Circuit Upholds EPA’s CERCLA Hazardous-Substance Designations for PFAS as State-Law Settlements Highlight Expanding Liability Landscape
September 15, 2026 —
Ashleigh K. Myers, Amanda G. Halter, Jillian Marullo & Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law BlogOn August 18, 2026, a unanimous panel of the U.S. Court of Appeals for the D.C. Circuit upheld the 2024 designation by the U.S. Environmental Protection Agency (EPA) of perfluorooctanoic acid (PFOA) and perfluorooctanesulfonic acid (PFOS) as hazardous substances under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA or Superfund). (See Chamber of Commerce of the United States of America, et al. v. EPA, No. 24-1193 (D.C. Cir. Aug. 18, 2026).)
The decision leaves EPA’s PFOA and PFOS hazardous substance designations in place and provides guidance on the scope of EPA’s authority to make future hazardous substances designations under CERCLA Section 102(a). The decision also likely resolves a challenge to the rule that has spanned two presidential administrations. After taking office, the Trump administration had obtained an abeyance of the litigation challenging the Biden-era rule while EPA reconsidered its position. In September 2025, EPA informed the court that it had decided to retain the designations, while signaling that it would work with Congress and industry to address CERCLA liability concerns for “passive receivers.” The litigation then resumed, with the current Administration defending the rule.
Reprinted courtesy of
Ashleigh K. Myers, Pillsbury,
Amanda G. Halter, Pillsbury,
Jillian Marullo, Pillsbury and
Anthony B. Cavender, Pillsbury
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Mr. Cavender may be contacted at anthony.cavender@pillsburylaw.com
Read the full story...
A Permitting Base Checklist for Data Centers and Power Plants
June 02, 2026 —
Michael S. McDonough, Stephen J. Humes & Stacey C. Wright - Gravel2Gavel Construction & Real Estate Law BlogThere is a lot of talk these days about “license to operate” for data centers, meaning management of the relationships with stakeholders and broader communities concerning both the benefits and adverse consequences of locating a facility in a particular locale. Here, we are speaking of “license to operate” more literally—namely, the legal and regulatory permitting and approval requirements for a privately owned data center whether by itself or colocated with a power generating plant.
Our Base Checklist includes generally and potentially applicable permitting requirements for development and operation, using California as an example. (Taking legal authority Frank Sinatra out of context, “If you can make it there, you can make it anywhere.”) The actual requirements for a given facility would depend, in part, on local law, including planning and zoning laws and plans, and the environment of the site. Just as examples, additional permitting and mitigation requirements might apply if sensitive receptors are located nearby (e.g., noise mitigation for residential dwellings), if sensitive and protected biological resources (e.g., jurisdictional waters and/or protected species) would be impacted, or if the present or former land uses require additional measures (e.g., hazardous materials remediation, mitigation for conversion of prime farmland, or protection of cultural resources). The scope of permit requirements would ultimately be determined by the applicable regulatory agencies and by the lead and responsible agencies under the applicable state environmental land use regime—in our reference case here, the California Environmental Quality Act (CEQA).
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Stephen J. Humes, Pillsbury and
Stacey C. Wright, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. Humes may be contacted at stephen.humes@pillsburylaw.com
Ms. Wright may be contacted at stephen.humes@pillsburylaw.com
Read the full story...
EPA Expands PFAS Reporting Requirements with Addition of New Chemical to Toxics Release Inventory, Published by Law360
June 08, 2026 —
Gordon Rees Scully MansukhaniThe U.S. Environmental Protection Agency’s (EPA) addition of sodium perfluorohexanesulfonate (PFHxS-Na) to the Toxics Release Inventory (TRI) introduces new federal reporting requirements for businesses that manufacture, process, or use the chemical. Because reporting obligations apply retroactively to the start of the year, affected facilities must quickly evaluate their compliance and recordkeeping practices.
In a recent Law360 article, Gordon Rees Scully Mansukhani Senior Counsel, Ayodeji Ayolola, explains why PFHxS-Na was automatically added to the TRI, how the EPA’s public reporting system works, and which businesses may be affected by the new rule. The article also touches upon key compliance considerations, including supply chain reviews, reporting thresholds for chemicals of special concern, and preparation for public disclosure requirements.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Federal Court Strikes Down New York’s Climate Superfund Act: What It Means for the “Polluter Pays” Movement
September 28, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogA federal judge in the Northern District of New York has struck down New York’s
Climate Change Superfund Act, ruling that the “polluter pays” climate law is preempted by federal law and “simply beyond the limits of state law.” The court concluded that the Clean Air Act (CAA) does not authorize New York’s compensation scheme, which calculates liability based on greenhouse gas (GHG) emissions attributable to worldwide fossil fuel extraction and refining. It separately held that any cost-recovery demand against a foreign producer would be preempted under the constitutional foreign affairs doctrine, which limits state intrusion into matters committed predominantly to the federal government. The court directed the parties to file a status report by September 14, leaving the form of further relief unresolved. In practical terms, the court has decided that the Act is preempted and cannot be enforced but has not yet determined the precise terms of its final order, including whether to formally enjoin its enforcement.
The
decision in West Virginia v. James, Case No. 1:25-cv-00168 (N.D.N.Y. Aug. 31, 2026), issued by Chief U.S. District Judge Brenda K. Sannes, who was appointed by President Obama, marks the first judicial invalidation of a state climate superfund statute and carries significant implications for the
climate superfund landscape and the three remaining
lawsuits challenging these laws.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...
Pay-If-Paid: What You Need to Know Before Signing on the Dotted Line
August 03, 2026 —
Christian Fernandez & Matthew Racioppo - Snell & WilmerBuried deep in the fine print of a subcontract, a pay-if-paid clause may be looming. If you are a subcontractor or supplier, misreading these clauses can put your cash flow at risk. If you are an owner or general contractor, drafting them incorrectly can leave you with obligations you never intended — or unenforceable protections you were counting on.
It is more important than ever to understand when pay-if-paid clauses hold up and when they do not, as well as recent litigation and drafting trends. Whether you are negotiating a new agreement, reviewing your standard form contracts, or staring down a payment dispute, understanding how Arizona law treats pay-if-paid clauses is essential. In this article, we break down key considerations, walk through the legal standards Arizona courts apply, and offer practical tips to consider to help you protect your payment rights on the next project.
Reprinted courtesy of
Christian Fernandez, Snell & Wilmer and
Matthew Racioppo, Snell & Wilmer
Mr. Fernandez may be contacted at cfernandez@swlaw.com
Mr. Racioppo may be contacted at mracioppo@swlaw.com
Read the full story...
Lewis Brisbois Welcomes Clients and Community Leaders to New Garden City Office Opening
July 27, 2026 —
Lewis BrisboisOn July 15, Lewis Brisbois hosted a ribbon-cutting event for its new Garden City office, which opened in April to serve the Long Island community and beyond.
The event was attended by more than 100 people, including Lewis Brisbois attorneys and staff as well as clients, local business and government leaders, Nassau County Supreme Court judges, and members of the press. Nassau County Executive Bruce Blakeman delivered remarks and cut the ribbon for the office.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Doctrine of Substantial Performance When It Comes to Payment
July 27, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent non-construction case touches upon the doctrine of substantial performance when it comes to payment. In this case, a club was to make two payments to secure a rapper’s attendance. The first payment was made. The second payment was made but was a few hundred dollars short of the agreed amount. The rapper did not show up. The club claimed it substantially performed its obligations. At first glance, the argument makes sense because the second payment fell only a few hundred dollars short. But that wasn’t the case when it comes to pre-commencement payment obligations:
Substantial performance applies only when the variance from the contract terms “is inadvertent or unintentional and unimportant so that the work actually performed is substantially what was called for in the contract.” However, when one party agrees to pay the other on or before a specific date, time is of the essence, and the payor is required to pay the payee on or before that date. “There is almost always no such thing as ‘substantial performance’ of payment between commercial parties when the duty is simply the general one to pay. Payment is either made in the amount and on the date due, or it is not.”
Big Gate Records, LLC v. Washington, 51 Fla.L.Weekly D1281a (Fla. 2nd DCA 2026) (internal citations omitted).
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Course of Construction Exclusions and the CGL Policy
July 20, 2026 —
Anna M. Perry, Rachel S. Kindseth & Nina Catanzaro - Saxe Doernberger & Vita, P.C.I. Course of Construction Exclusions
Course of Construction (“COC”) exclusions are found on General Liability and excess liability policies, typically a wrap-up or project specific policy, and generally exclude “all property damage occurring during the course of construction.” Insurers claim COC exclusions are not problematic because they are intended to prevent an overlap in coverage between the general liability policy and first-party property Builder’s Risk policy. However, because General Liability policies and Builder’s Risk policies provide coverage for different risks, COC exclusions can create a gap in coverage for owners and contractors. Therefore, any exclusion on a wrap-up or project specific policy that limits coverage for property damage liability should be scrutinized, and amendments sought when warranted and commercially achievable, for owners, developers and contractors because General Liability policies do not cover the same risk as that of a Builder’s Risk policy.
General liability policies provide defense and indemnity to the insured(s) for claims made by a third-party against the insured. Broad COC exclusions serve to preclude coverage for all property damage, not just property damage to the insured project. This includes property damage to property other than the insured project, e.g. an adjacent property. On the other hand, Builder’s Risk policies provide first-party property coverage for direct physical loss to the project during the course of construction. The Builder’s Risk policy will not provide coverage for property other than the project itself (e.g., adjacent property) and it will not provide a defense or indemnity in the event the owner of the damaged property brings a claim against a potentially at-fault party.
Reprinted courtesy of
Anna M. Perry, Saxe Doernberger & Vita, P.C.,
Rachel S. Kindseth, Saxe Doernberger & Vita, P.C. and
Nina Catanzaro, Saxe Doernberger & Vita, P.C.
Ms. Perry may be contacted at APerry@sdvlaw.com
Ms. Kindseth may be contacted at rkindseth@sdvlaw.com
Ms. Catanzaro may be contacted at NCatanzaro@sdvlaw.com
Read the full story...