The Construction Defect Litigation Podcast: Navigating Multi-Party Construction Defect Litigation
September 08, 2026 —
Ivette Kincaid & Thomas McCarrick - Kahana FeldKahana Feld Construction Defect Practice Group Chair Ivette Kincaid and attorney Thomas McCarrick recently joined the Construction Defect Litigation podcast to discuss the challenges—and strategies—behind complex construction defect matters involving multiple stakeholders.
Drawing on their experience, Ivette and Thomas explore practical approaches to:
- Identifying key parties and understanding how claims and crossclaims develop
- Working with experts to evaluate defects, causation and damages
- Managing procedural challenges, including scheduling, document management and depositions
- Applying thoughtful case management strategies to position complex matters for successful resolution
Reprinted courtesy of
Ivette Kincaid, Kahana Feld and
Thomas McCarrick, Kahana Feld
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Mr. McCarrick may be contacted at tmccarrick@kahanafeld.com
Read the full story...
Predict Risk, Not Incidents: A New Analytics Framework for Your Construction Safety Data
August 03, 2026 —
Tabrez Zahoor - Construction ExecutiveBehind every “zero-incidents” company report, hidden hazards may already be accumulating—
risks that could become serious injuries tomorrow. The question every executive should be asking is not, “Did anything go wrong last month?” It is: “Where is risk building on my projects right now?”
Most construction organizations cannot answer that question. Not because the data does not exist—it does. Every active project generates daily inspection findings, labor records, near-miss reports and audit results. The problem is that standard safety systems collect this data and then report it in ways that make it operationally useless for prevention. They describe the past. They predict nothing.
The predictive safety analytics framework (PSAF) is a practical, deployable system developed from years of applying data science to large-scale construction portfolio operations that takes the safety data construction organizations already collect and transforms it into a forward-looking risk signal. The result? A single weekly score that tells executives where risk is concentrating across their portfolio before anyone gets hurt.
Reprinted courtesy of
Tabrez Zahoor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLP’s Fort Lauderdale office. He may be reached at shauptman@balljanik.com.
The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Trend Continues Where Unlicensed Contractors Have No Recourse
July 13, 2026 —
David Adelstein - Florida Construction Legal UpdatesThere’s been a recent trend in Florida case law that has figuratively “killed” unlicensed contractors. Here’s another one. The moral to this trend and case is simple: make sure you have the proper licenses prior to serving as a contractor under Florida law. Trying to be cute, as seemed to be the situation in this case with a creative argument, is not an argument that will carry the day and your resources will be devoted to being creative versus the ultimate merits of the dispute.
In Ramindesign, LLC v. Skarzynski, 2026 WL 1649571 (S.D.Fla. 2026) an owner of real property hired a company to design and construct a spec home on the property. The company and its owner were NOT licensed contractors. The contract stated the company was serving as a “spec developer” and referred to it as the contractor throughout the contract. Other than this, the contract was set up as a cost plus a fee.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Sometimes a General Damages Assessment is Enough. . .
July 06, 2026 —
Christopher G. Hill - Construction Law MusingsIt has been a while since I last posted here at
Construction Law Musings. Life, law practice, and “blogger’s block” have taken their toll on the posting schedule. Hopefully this will be one of several upcoming posts now that the litigation schedule has lightened a bit over the summer.
Today’s post is about damages. Specifically damage to a homeowner’s roof and her legal damages therefor. That last is of course a sentence that only a
construction attorney (or other litigator) could possibly craft and have it make sense. Now, on with the case. . .In
Hardesty Construction, Inc. v. Weedon, the facts are as follows:
Ms. Weedon had hail damage to the roof of her home. She hired Hardesty Construction to repair and replace the roof. After the first roof was installed and failed inspection, a second roof was installed. The issue was that the first roof had a warranty and the second roof, installed similarly to the first (and allegedly with the same construction issues according to Ms. Weedon’s expert), was not provided with the promised warranty. As one may expect, Weedon sued Hardesty and Hardesty Construction for fraudulent inducement and breach of contract. At trial, Weedon testified, without objection, that her home was worth $40,000 less because of Hardesty Construction’s work, which was based partially on quotes Weedon received to fix the roof. The Circuit Court granted Hardesty Construction’s motion to strike Weedon’s fraudulent inducement claim, but not her other claims. A jury awarded Weedon $30,253.30 on her breach of contract claim. Hardesty Construction appealed, arguing the Circuit Court erred in (a) allowing the jury to consider Weedon’s valuation testimony because it was not based on her personal knowledge and (b) denying its motion to strike based on insufficient evidence as to damages. Weedon assigned cross-error in the Circuit Court’s decision to grant the motion to strike her fraudulent inducement claim against Samual Hardesty.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Traub Lieberman Wins Affirmation of Judgment on Pleadings Before the Seventh Circuit
August 16, 2026 —
Dana A. Rice & Adam P. Joffe - Traub LiebermanTraub Lieberman Partners Dana Rice and Adam Joffe obtained affirmation of judgment from the Seventh Circuit Court of Appeals in favor of an Insurance Company. The Insurance Company filed suit seeking a declaration that it had no duty to defend or indemnify its Insured, a Roofing Contractor, in an underlying lawsuit. The Insurance Company issued a commercial general liability policy with a one-year policy term. The policy included an exclusion that barred coverage for any losses arising out of work the insured completed before the date the policy incepted.
Reprinted courtesy of
Dana A. Rice, Traub Lieberman and
Adam P. Joffe, Traub Lieberman
Mr. Rice may be contacted at drice@tlsslaw.com
Mr. Joffe may be contacted at ajoffe@tlsslaw.com
Read the full story...
Humanoid Robots in Construction: The Reality Right Now
October 12, 2026 —
Aarni Heiskanen - AEC BusinessHumanoid robots are getting a lot of media attention. Videos of robots doing backflips and kung fu moves suggest that a general-purpose machine worker is just around the corner. A recent visit by the Finnish technology magazine
Tekniikka&Talous to crane manufacturer
Konecranes offers a more sober picture. I think it is a useful reality check for anyone in the AEC industry wondering what humanoids can actually do today.
What a Humanoid Can Do in a Controlled Environment
Konecranes bought a
Unitree G1 EDU humanoid in autumn 2025, likely as the first Finnish industrial company to do so. With separately purchased five-finger hands and other extras, the price came close to €100,000.
Read the full story...Reprinted courtesy of