Beyond the Storm: How Non-Hurricane Catastrophes Expose Florida’s Construction Defect Blind Spot
August 11, 2026 —
Franchesco “Frank” Soto & Amanda L. Gonzalez - Ball JanikOn June 8, 2026, a magnitude 6.1 earthquake struck the Gulf near the coast of Cuba, the largest instrumentally recorded earthquake in the Gulf since seismic monitoring began in 1950. Buildings swayed, offices were evacuated, and many residents along the east coast of Florida, from Miami-Dade to Jacksonville, felt the ground shake. Although no tsunami followed and reported structural damage was limited, this event exposed a blind spot that Florida property owners, developers, and their counsel cannot afford to ignore: catastrophic stress on Florida buildings does not always come in the form of a named storm.
Florida property owners have grown accustomed to preparing for wind, storm surge, floods, and torrential rain. Far less attention is paid to earthquakes, sinkholes, tornadoes, hail, and non-tropical flooding, each of which can place unexpected stress on buildings not designed with those forces top of mind and can trigger deficiencies in buildings that were not otherwise known, expose design failures, and create an urgency for both insurance claims and subsequent litigation.
Non-Hurricane Triggers of Latent Defects
Seismic activity is the clearest example. Florida’s building code accounts for wind loads, not seismic forces, meaning even a moderate earthquake can reveal weaknesses in curtain wall systems, structural connections, or foundations that were already marginal. Sinkholes, driven by Florida’s karst limestone geology, remain a persistent threat, particularly in Central Florida, where subsurface voids can undermine foundations without warning. Non-tropical flooding, like the record rainfall that flooded South Florida in June 2024, can intrude through building envelopes and waterproofing systems that were never stress-tested for such volumes of water. Tornadoes and hail, while more localized, can cause roofing and envelope failures that mimic, mask, or trigger latent construction defects.
The Litigation and Coverage Disputes That Follow
When one of these events strikes a building already carrying undisclosed or unresolved construction defects, the resulting disputes become considerably more complex. Property owners and associations must move quickly to document existing conditions and distinguish damage caused by the event from pre-existing defective construction, the same causation issue that arises in the hurricane context under Chapter 558, but often without the benefit of established precedent or adjuster experience with these less common events.
Insurance coverage disputes frequently follow close behind. Carriers may dispute whether an earthquake, flood, or other peril is covered at all, particularly where policies contain earthquake or flood exclusions requiring separate endorsements, or anti-concurrent causation language that can bar coverage entirely when a covered peril combines with an uncovered one, such as pre-existing defective construction, to cause a loss. Sinkhole claims carry their own statutory framework under Florida law, requiring specific testing protocols and reporting before a claim is compensable. Developers and contractors, in turn, may find themselves defending Chapter 558 claims while simultaneously litigating with their own carriers over defense and indemnity obligations.
Practical Risk Mitigation Strategies
Property owners, associations, and developers can take several concrete steps to reduce their exposure. First, maintain thorough documentation, including engineering reports, maintenance logs, and photographs, well before any event occurs. This documentation is often the deciding factor in causation disputes. Second, engage structural engineers and consultants immediately following any seismic event, unusual flooding, or storm damage, regardless of whether a hurricane is involved. Prompt inspection preserves evidence and can help prevent inadvertent waiver of construction defect claims. Third, review insurance policies regularly with counsel or a broker to confirm earthquake, flood, and sinkhole coverage matches the property’s actual risk profile, rather than assuming a standard property policy responds to every peril. Fourth, avoid rushing to remediate before conditions are documented and/or before consulting counsel. Well-intentioned repairs can inadvertently compromise evidence needed to prove a defect claim.
The June earthquake was a reminder that Florida’s catastrophic risk profile extends beyond hurricane season. Property owners, associations, and developers who build readiness plans around all forms of catastrophic stress, not just named storms, will be far better positioned when the next unexpected event occurs.
Franchesco “Frank” Soto is a partner in
Ball Janik’s Construction Defect Practice Group in Miami. He may be reached at fsoto@balljanik.com.
Amanda L. Gonzalez is a litigation attorney in
Ball Janik’s Construction Defect Practice Group in Miami. She may be reached at agonzalez@balljanik.com.
DOI Finalizes Long-Awaited Modernization of Type A Natural Resource Damage Assessment Regulations
August 03, 2026 —
Amanda G. Halter, Ashleigh K. Myers & Jillian Marullo - Gravel2Gavel Construction & Real Estate Law BlogFor nearly three decades, the U.S. Department of the Interior’s (DOI) simplified “Type A” Natural Resource Damage Assessment (NRDA) regulations were available more in theory than in practice, constrained by dated models, narrow geographic applicability and a $100,000 cap that rarely matched the economics of modern environmental claims. DOI has now finalized revisions to the Type A natural resource damages assessment procedures under 43 C.F.R. Part 11 for hazardous substance releases under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and the Clean Water Act (CWA), with the final rule published in the
Federal Register on July 13, 2026 and scheduled to become effective August 12, 2026.
As discussed
previously, DOI has sought to modernize what it views as an “inefficient and inflexible” process and restore the Type A procedure to its intended role as a more streamlined pathway for smaller, less contentious NRD claims. The final rule adopts a $5 million default damages threshold, allows use above that amount if all parties agree, clarifies that Type A may be used in all environments and for all natural resource types, and removes legacy model appendices that had tethered the process to outdated formulas.
Reprinted courtesy of
Amanda G. Halter, Pillsbury,
Ashleigh K. Myers, Pillsbury and
Jillian Marullo, Pillsbury
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Marullo may be contacted at jillian.marullo@pillsburylaw.com
Read the full story...
Before Snowbirds Pay That Florida Condo Bill, Ask This
November 18, 2026 —
Jocelyn R. Rocha - Ball Janik LLPFor many seasonal Florida condominium owners, the first unwelcome surprise of snowbird season may not be a hurricane warning or a higher insurance renewal. It may be a special assessment notice.
Before assuming the entire bill reflects the ordinary cost of condominium ownership, owners should ask: What caused the condition the assessment is meant to address?
What the Assessment is Funding
A special assessment is a charge imposed in addition to regular condominium fees. It can help pay for major repairs or address a reserve shortfall. Reserves are funds set aside for future major repairs and replacements.
Florida’s structural integrity reserve requirements generally prevent covered associations from waiving reserve funding for critical components, including roofs, structural systems, waterproofing and plumbing. A structural integrity reserve study estimates those components’ remaining useful lives, repair or replacement costs, and needed reserve contributions.
A limited extension permits qualifying associations to complete a reserve study with a required milestone inspection, but no later than December 31, 2026. Milestone inspections assess a building’s structural condition. As studies reveal funding shortfalls, owners may face special assessments.
When Repairs May Point to Defects
A reserve study is primarily a funding tool. Its visual inspection does not necessarily determine why repairs are needed. An aging roof may simply need replacement. In a newer building, substantial repairs well before the end of a component’s expected service life may point to defective design, materials or installation.
Patterns across a building deserve attention. Recurring leaks around the same window detail in multiple units may indicate improper flashing or sealant installation. Repeated balcony leaks may reveal waterproofing or drainage failures. Widespread premature concrete cracking or corrosion may warrant investigation into construction quality. A qualified professional should assess the cause, considering maintenance and environmental exposure as well.
A newer building may still have time to pursue claims against the developer, contractors and/or design professionals, making early investigation particularly valuable. Older buildings may also have claims involving more recent renovation or replacement work. Insurance should be evaluated separately: coverage for resulting property damage can differ from coverage for correcting defective work, depending on the policy and facts.
When the Right to Bring a Claim Expires
The timing is critical. Florida Statutes section 95.11 generally imposes a seven-year statute of repose, an outside cutoff for filing construction defect lawsuits. The period generally runs from the earliest applicable issuance of a temporary certificate of occupancy, certificate of occupancy or certificate of completion, or abandonment if construction was not completed. Buying a unit, developer turnover or discovering a hidden defect does not restart that seven-year period.
A separate four-year limitations period may expire sooner. For latent defects, that period generally turns on when the defect was discovered or should have been discovered through due diligence. Counsel should calculate the applicable deadlines promptly. Serving a Chapter 558 presuit notice does not pause the seven-year repose period.
What Owners Should Ask Now
Owners should consider when problems first appeared, whether they recur after repairs, and whether neighbors report similar conditions. Ask the board:
- Does the assessment fund repairs, reserves or both, and what reports support the proposed work?
- Has a qualified professional investigated the cause, and has the association identified potentially responsible parties?
- Have applicable insurance, notice requirements and claim deadlines been evaluated?
- How will evidence and potential claims be preserved while repairs proceed?
Prompt investigation can protect the opportunity to recover appropriate costs from responsible parties or available insurance. Necessary safety repairs should proceed, and potential recovery does not suspend the obligation to pay a lawfully imposed assessment.
Reprinted courtesy of
Jocelyn R. Rocha, Ball Janik LLPMs. Rocha may be contacted at
jrocha@balljanik.com
What Construction Attorneys Do and When Contractors Need Them
August 11, 2026 —
Construction ExecutiveDirect Answer
A construction attorney advises contractors on contracts, payment rights, mechanic's liens, payment bond claims, change orders, delay claims, OSHA matters, defect claims, terminations and dispute resolution. The work covers far more than lawsuits—much of its value comes before a dispute ever becomes formal.
Construction attorneys help contractors protect payment rights, manage project risk, resolve disputes and avoid contract terms that can turn a profitable job into a financial loss. Their work covers more than lawsuits. A construction attorney may review a contract before bid day, help preserve lien rights, respond to a defective work claim, prepare for mediation or defend a contractor after a safety citation.
For contractors, legal counsel is often most valuable before a dispute becomes formal. A missed notice deadline, vague scope clause, unsigned change order or broad indemnity provision can create problems long before a claim is filed. Construction attorneys help identify those risks while there is still time to negotiate, document the issue or preserve leverage.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
2026 Top Business Risks for Construction and Engineering Companies
May 26, 2026 —
Darren Tasker - Construction ExecutiveThe 2026 Allianz Risk Barometer revealed some surprising findings for construction and engineering businesses. Now in its fifteenth year, this
annual business risk ranking by corporate insurer
Allianz Commercial incorporates the views of 3,338 global risk management professionals on the main perils on their radar for the year.
Survey respondents included construction and engineering risk experts who identified the threats keeping them up at night. Here is how they ranked the top industry risks for 2026:
Natural Catastrophes
Natural catastrophe risk retains the top spot, with 38% of construction and engineering respondents citing this risk as their leading concern for 2026. From the insurance perspective, economic and insured losses remained high, albeit lower than the 10-year average. The evolving nature of natural catastrophes continues to pose significant challenges to businesses and the (re)insurance industry. Insured losses from natural catastrophes are set to reach $107 billion for 2025, according to Swiss Re—the sixth year in a row they have exceeded $100 billion, while economic losses are well in excess of $200 billion.
Reprinted courtesy of
Darren Tasker, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
The Grenfell & Champlain Towers: Risk Management Considerations in the Wake of Catastrophic Loss — A UK/US Comparison
June 02, 2026 —
Eric M. Clarkson - Saxe Doernberger & Vita, P.C.1. Introduction
As part of the multinational collaborative relationship between Saxe Doernberger & Vita, P.C. and Fenchurch Law, we continually find ourselves in conversations about the sometimes subtle but sometimes drastic differences between risk management and coverage considerations from one country to the next. These differences are often highlighted by the fallout from large catastrophic losses that are widely publicized and illuminate sometimes widespread risks and perils that many others may be facing in the coming years.
The response of governments and their subdivisions to the needs of victims and/or commercial parties, and insurance markets’ evaluation of and reactions to catastrophic losses vary widely from country to country and jurisdiction. In this article, we discuss these responses and reactions in the cases of the Grenfell Tower Fire in London, England, and the Champlain Tower collapse in Surfside, Florida, within the United States. These two widely publicized losses involved different risk management and insurance considerations based on where they occurred. They also saw substantially different government responses and raised varied questions about what the next steps are for their respective commercial and insurance markets.
Read the full story...Reprinted courtesy of
Eric M. Clarkson, Saxe Doernberger & Vita, P.C.Mr. Clarkson may be contacted at
EClarkson@sdvlaw.com
Don’t Forget to Include Termination Language in Your Contract
November 02, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent case explains why termination language or a basis to withhold contract sums is important in your contract. Don’t neglect this language or the negotiation that goes into having this language.
In a recent dispute, GSD Contracting, LLC v. All American Builders & Debris Removal, Inc., 2026 WL 3068422 (Fla. 4th CA 2026), a subcontract included language that said that 10% retainage would be paid 90 days after final completion of the project. The subcontract did NOT include termination for cause language; it only included termination for convenience language. Towards the end of the project, mold was discovered warranting mold remediation. The subcontractor refused to perform until the mold was remediated. The general contractor claimed it was remediated but the subcontractor argued the remediation was insufficient because the contractor did not engage an industrial hygienist. After the subcontractor refused to complete its work, the general contractor terminated the subcontractor for cause. The subcontractor then sued the general contractor for its 10% retainage claiming the general contractor breached the subcontract. The trial court, as affirmed by the appellate court, agreed. The appellate court found that the contract required the general contractor to pay the subcontractor’s retainage 90 days after final completion and the project had long been completed. “Significantly, the subcontract does not contain a termination for cause provision or any pertinent provision permitting [the general contractor] to withhold or retain [the subcontractor’s] retainage following a termination…Nothing in the subcontract provides that [the general contractor] may thereafter withhold the retainage based on an alleged default by [the subcontractor].” GSD Contracting, supra, at *2.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Two Important Points Regarding the Miller Act
September 15, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller Act case, U.S. f/u/b/o Boundless Management Outsourcing Group, LLC v. Endurance Assurance Corp, 2026 WL 2241491 (D. Puerto Rico 2026), confirms two important points when it comes to the Miller Act. In this case, a subcontractor pursued a Miller Act payment bond lawsuit more than one year after its work was finished. The subcontractor also asserted a claim against the federal government. The lawsuit was dismissed. Below are two takeaway points to consider if you are dealing with a Miller Act payment bond lawsuit.
First, as it relates the claim against the federal government, the federal district court followed authority that held that the Miller Act does NOT include a waiver of sovereign immunity against the federal government. “[T]he Court does not identify any clear language in the Miller Act expressly waiving the United States or its agencies’ sovereign immunity.” Endurance Assurance Corp., supra at *3.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com