What Massachusetts Contractors and Developers Can Learn from Cannistraro v. Columbia Construction
July 13, 2026 —
Anthony LaPlaca & Luke Marston - The Construction SeytIntroduction
On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.—a holding that sits at the intersection of Prompt Pay Act compliance and the Massachusetts Arbitration Act.
[1]
Most already know that the Massachusetts Prompt Pay Act (PPA) imposes strict timing and certification requirements for rejecting payment applications and proposed change orders on projects valued at $3 million or more. Most notably, the PPA requires the paying party to give the payee written notice of its approval or rejection of progress applications and proposed changes within 15 days of receipt, which notice must include a “factual and contractual basis for the rejection” and must be “certified as made in good faith.”
[2] In the absence of a timely certified notice, payment is “deemed to be approved” unless the payor properly rejects payment before it comes due.
[3]
Reprinted courtesy of
Anthony LaPlaca, Seyfarth Shaw LLP and
Luke Marston, Seyfarth Shaw LLP
Mr. LaPlaca may be contacted at alaplaca@seyfarth.com
Mr. Marston may be contacted at lmarston@seyfarth.com
Read the full story...
Insufficient Notice of Commencement and Construction Lien Rights
August 03, 2026 —
David Adelstein - Florida Construction Legal UpdatesWhen a party is preserving their construction lien rights, the party will look to the recorded Notice of Commencement. This is the recorded document that provides the lienor with the information for purposes of preserving construction lien rights. A Notice to Owner company will typically rely on the Notice of Commencement to serve Notices to Owners from lower tiers not in contract with the owner. However, when it comes to preparing the lien, a lienor should look beyond just the Notice of Commencement and also look to the property appraiser’s website as a backstop.
In a recent case, a window company had the homeowner sign the Notice of Commencement and then filled in the information. The company naturally did this for the convenience of the homeowner that probably was unfamiliar with the Notice of Commencement process. Regardless, information in the Notice of Commencement was inaccurate. It failed to include all the real property owners. Thus, when a payment dispute arose and a construction lien was prepared, it did not identify all of the real property owners. All of the real property owners were added later during the pendency of a lien foreclosure lawsuit. The trial court denied the lien because of the defective / insufficient Notice of Commencement — the lienor assumed the risk of error by filling out the information in the Notice of Commencement. The trial court further denied the lien holding that because the work did not commence within 90 days of the Notice of Commencement, the Notice of Commencement is void.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Beyond the Storm: How Non-Hurricane Catastrophes Expose Florida’s Construction Defect Blind Spot
August 11, 2026 —
Franchesco “Frank” Soto & Amanda L. Gonzalez - Ball JanikOn June 8, 2026, a magnitude 6.1 earthquake struck the Gulf near the coast of Cuba, the largest instrumentally recorded earthquake in the Gulf since seismic monitoring began in 1950. Buildings swayed, offices were evacuated, and many residents along the east coast of Florida, from Miami-Dade to Jacksonville, felt the ground shake. Although no tsunami followed and reported structural damage was limited, this event exposed a blind spot that Florida property owners, developers, and their counsel cannot afford to ignore: catastrophic stress on Florida buildings does not always come in the form of a named storm.
Florida property owners have grown accustomed to preparing for wind, storm surge, floods, and torrential rain. Far less attention is paid to earthquakes, sinkholes, tornadoes, hail, and non-tropical flooding, each of which can place unexpected stress on buildings not designed with those forces top of mind and can trigger deficiencies in buildings that were not otherwise known, expose design failures, and create an urgency for both insurance claims and subsequent litigation.
Non-Hurricane Triggers of Latent Defects
Seismic activity is the clearest example. Florida’s building code accounts for wind loads, not seismic forces, meaning even a moderate earthquake can reveal weaknesses in curtain wall systems, structural connections, or foundations that were already marginal. Sinkholes, driven by Florida’s karst limestone geology, remain a persistent threat, particularly in Central Florida, where subsurface voids can undermine foundations without warning. Non-tropical flooding, like the record rainfall that flooded South Florida in June 2024, can intrude through building envelopes and waterproofing systems that were never stress-tested for such volumes of water. Tornadoes and hail, while more localized, can cause roofing and envelope failures that mimic, mask, or trigger latent construction defects.
The Litigation and Coverage Disputes That Follow
When one of these events strikes a building already carrying undisclosed or unresolved construction defects, the resulting disputes become considerably more complex. Property owners and associations must move quickly to document existing conditions and distinguish damage caused by the event from pre-existing defective construction, the same causation issue that arises in the hurricane context under Chapter 558, but often without the benefit of established precedent or adjuster experience with these less common events.
Insurance coverage disputes frequently follow close behind. Carriers may dispute whether an earthquake, flood, or other peril is covered at all, particularly where policies contain earthquake or flood exclusions requiring separate endorsements, or anti-concurrent causation language that can bar coverage entirely when a covered peril combines with an uncovered one, such as pre-existing defective construction, to cause a loss. Sinkhole claims carry their own statutory framework under Florida law, requiring specific testing protocols and reporting before a claim is compensable. Developers and contractors, in turn, may find themselves defending Chapter 558 claims while simultaneously litigating with their own carriers over defense and indemnity obligations.
Practical Risk Mitigation Strategies
Property owners, associations, and developers can take several concrete steps to reduce their exposure. First, maintain thorough documentation, including engineering reports, maintenance logs, and photographs, well before any event occurs. This documentation is often the deciding factor in causation disputes. Second, engage structural engineers and consultants immediately following any seismic event, unusual flooding, or storm damage, regardless of whether a hurricane is involved. Prompt inspection preserves evidence and can help prevent inadvertent waiver of construction defect claims. Third, review insurance policies regularly with counsel or a broker to confirm earthquake, flood, and sinkhole coverage matches the property’s actual risk profile, rather than assuming a standard property policy responds to every peril. Fourth, avoid rushing to remediate before conditions are documented and/or before consulting counsel. Well-intentioned repairs can inadvertently compromise evidence needed to prove a defect claim.
The June earthquake was a reminder that Florida’s catastrophic risk profile extends beyond hurricane season. Property owners, associations, and developers who build readiness plans around all forms of catastrophic stress, not just named storms, will be far better positioned when the next unexpected event occurs.
Franchesco “Frank” Soto is a partner in
Ball Janik’s Construction Defect Practice Group in Miami. He may be reached at fsoto@balljanik.com.
Amanda L. Gonzalez is a litigation attorney in
Ball Janik’s Construction Defect Practice Group in Miami. She may be reached at agonzalez@balljanik.com.
Colorado’s New Mechanics’ Lien Protections: What S.B. 26-074 Means for Your Next Project
October 27, 2026 —
Maria Conversa - Snell & WilmerStarting August 12, 2026, Colorado’s mechanics’ lien statute underwent its most significant update in years. Colorado’s General Assembly enacted Senate Bill 26-074 on April 6, 2026, and the new law directly addressed a problem that has plagued contractors and subcontractors for decades. For years, a contractor and subcontractor who filed a lien for the full amount it believed was due — particularly when that amount included disputed costs, delay damages, or lost productivity — risked triggering the “excessive lien” penalty. That penalty could force the claimant to forfeit its lien rights entirely and pay the other side’s attorney fees. The new law expands the categories of costs to be claimed by good-faith lien claimants, while still protecting against truly abusive filings. General contractors, subcontractors, suppliers, owners, and lenders all need to understand these changes.
What the Bill Changed
1. Lien Value May Include Disputed Amounts
The bill amends the core lien statute to insert the phrase “whether disputed or undisputed” into the description of lienable value. Prior law referenced only “the value” of labor, services, or materials furnished. The new text confirms that a lien can attach for amounts the parties still dispute. A claimant no longer needs the owner or general contractor to agree on the amount before filing.
Read the full story...Reprinted courtesy of
Maria Conversa, Snell & WilmerMs. Conversa may be contacted at
mconversa@swlaw.com
Landlord Determined to Not Qualify as Additional Insured
September 08, 2026 —
Tred R. Eyerly - Insurance Law HawaiiIn a dispute between two insurers, the Second Circuit affirmed the district court’s determination that the landlord was not an additional insured under the tenant’s policy. Peleus Ins. Co. v. Am. European Ins. Co., 2026 U.S. App. LEXIS 17981 June 22, 2026).
Blossom Miller sued 57th Avenue and 21st Century in state court alleging that she was injured when she tripped on the sidewalk in front of the leased premises (the “Miller Action”). The premises was leased by 57th Avenue to 21st Century.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Flatiron Said Disputed Concrete Mix Cost Millions on Large Caltrans Project
June 22, 2026 —
Elaine Silver & Richard Korman - Engineering News-RecordFor awhile in 2023, part of the California Dept. of Transportation's (Caltrans) Fix 50 HOV lane and resurfacing project in Sacramento itself needed to be fixed.
Reprinted courtesy of
Elaine Silver, Engineering News-Record and
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story...
Voluntary Dismissal of an Indemnity Claim Does Not Make the Subcontractor a “Prevailing Party,” Washington Court of Appeals Holds
September 21, 2026 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIn
King County v. Walsh Construction Company II, LLC, No. 86503-0-I (Wash. Ct. App. Aug. 4, 2025), an unpublished decision from Division I of the Washington Court of Appeals, the Court affirmed the denial of a subcontractor’s request for prevailing-party attorney fees under an indemnity clause after the general contractor voluntarily dismissed its indemnity claims. Because the indemnity claim was no longer live and no determination of fault had occurred, the Court held that the trial court did not err in denying the request. ACS represented Walsh, the general contractor, in securing the denial of the fee request at the trial court that the Court of Appeals affirmed.
A Pass-Through Indemnity Claim That Ended Before Fault Was Decided
The dispute arose out of a public works contract under which King County hired Walsh Construction Company II, LLC (“Walsh”) to construct and install a conveyance pipeline. After the pipeline broke, King County sued Walsh for breach of contract and warranty, expressly identifying both Walsh and its subcontractor, Mears Group Inc., (“Mears”) as responsible. Walsh tendered defense and indemnity to Mears under the subcontract.
Read the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
New Survey Reveals Overwhelmingly Optimistic Results on the Use of AI in Construction
May 14, 2026 —
Construction ExecutiveOn December 5, 2025,
CMiC and
Dodge released a
survey asking over 6,000 companies across various sectors of the construction industry their stance on artificial intelligence—whether they use it or not; whether they like it or not; whether they have or are planning to implement it or not; and so on. Considering its reputation for skepticism and reluctance when it comes to adopting new forms of technology, the construction industry pleasantly surprised CMiC and Dodge with its answers to these questions, with 87% of contractors believing AI will have a meaningful impact on construction.
“The research indicates the construction industry is nearing a tipping point for AI adoption,” says Steve Jones, senior director of industry insights at Dodge Construction Network, who sat down with Construction Executive to delve further into the survey questions and answers and what the industry’s current position on them means for AI’s future role in construction.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...