Anomaly in Adding a Third-Party Claimant to a Liability Insurance Coverage Dispute
May 05, 2026 —
David Adelstein - Florida Construction Legal UpdatesIn an insurance coverage lawsuit seeking declaratory relief, an insurer sued the third-party claimant. The insurer was seeking a declaration that there was no coverage, which naturally would impact the third-party claimant. The insured did not respond to the lawsuit and the insurer moved for a default judgment which was objected to by the third-party claimant. The trial court granted a final judgment in favor of the insurer, which prompted an appeal from the third-party claimant because the final judgment impacts its rights to coverage if it obtains a judgment against the insured.
The appellate court reversed but please take a look at this Court’s discussion on the issue of an insurer adding a third-party claimant to a coverage lawsuit when then the third-party cannot pursue a direct claim against the insurer until it obtains a settlement or judgment against the insured. It presents an interesting argument and counter-point for a third-party claimant that is added to the coverage lawsuit which has implications if it obtains a judgment against the insured:
This case involves an apparent anomaly in Florida law. It is well-established that third-party claimants injured by an insured’s negligence have a right as third-party beneficiaries to payment from the insured’s insurance proceeds. It is equally well-established that the third-party claimants’ rights in this regard do not accrue unless and until they obtain a verdict or settlement against the insured. A quick review of this law is helpful at this point.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
At Lake Powell, Engineering Is Outpacing Colorado River Policy
February 10, 2026 —
Bryan Gottlieb - Engineering News-RecordArizona’s Lake Powell is in trouble. U.S. Bureau of Reclamation modeling shows the reservoir dropped roughly 36 ft between December 2024 and December 2025, a decline that is no longer a warning but an operating condition engineers are designing around.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com
Southwest Super Lawyers Recognizes 50 Snell & Wilmer Attorneys in 2026 Rankings
June 15, 2026 —
Snell & WilmerPHOENIX (April 22, 2026) – Snell & Wilmer is pleased to announce that 50 attorneys in the Phoenix and Tucson offices have been selected for inclusion in the 2026 Southwest Super Lawyers publication. Of those 50, four were recognized for the first time and 24 were recognized as Southwest Rising Stars. Super Lawyers is a listing of lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The selection process is multi-phased and includes independent research, peer nominations, and peer evaluations. Super Lawyers was first published in 1991 by Law & Politics and was acquired by Thomson Reuters, Legal in February 2010. Thomson Reuters is a leading source of information for businesses and professionals. The below Snell & Wilmer attorneys have been selected for inclusion in the 2026 Southwest Super Lawyers rankings.
Read the full story...Reprinted courtesy of
Snell & Wilmer
White and Williams LLP Recognized on the List of Largest Law Firms in Greater Philadelphia
March 03, 2026 —
White and Williams LLPWhite and Williams LLP was recently recognized on the list of Largest Law Firms in Greater Philadelphia by the Philadelphia Business Journal. The Firm is ranked #10 among the largest law firms in the Greater Philadelphia area.
This listing ranks over 500 law firms in the counties of Bucks, Chester, Delaware, Montgomery, or Philadelphia in Pennsylvania; Atlantic, Burlington, Camden, or Gloucester in New Jersey, and Kent or New Castle in Delaware. White and Williams has been named on the list since 2023.
Read the full story...Reprinted courtesy of
White and Williams LLP
Soot Constitutes Property Damage
March 17, 2026 —
Tred R. Eyerly - Insurance Law HawaiiApplying Missouri law, the Eighth Circuit affirmed the jury verdict awarding damages for the presence of soot after a fire. Maxus Metropolitan, LLC v. Travelers Property Cas. Co. of Am., 2025 U.S. App. LEXIS 29921 (8th Cir. Nov, 17, 2025).
A fire destroyed Phase 6 of a multi-building apartment complex known as the Metropolitan. At the time of the fire, all six phases of the Metropolitan were at various stages of completion, including some of which were occupied by tenants. Phase 6 was still under construction. The fire caused severe damage to Phase 5. The interiors of Phases 1-4 were unaffected by the fire.
Maxus Metropolitan, the owner of the complex, had a policy with Travelers which covered up to $35 million in “direct physical loss, . . or damage.” The policy also provided coverage for up to $5 million in lost business income.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
GRSM Trial Team Holds Alameda County Asbestos Verdict to $900,000 Against $50 Million Demand
July 27, 2026 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani Partners John Katerndahl and Vincent Gunter recently obtained an outstanding trial result for a manufacturer of asbestos-containing electrical cable, holding a jury verdict to $900,000 against a $50 million demand following an eight-week trial in Alameda County Superior Court, which is among the most challenging asbestos venues in the country. The GRSM team also included Associate Brandon Sanchez, on-site trial Paralegal Laura Vitanova, and Paralegal Kerrie Lease.
The plaintiffs, the surviving spouse and four children of a former painter who died of mesothelioma, alleged that the decedent was exposed to asbestos from the company’s electrical cable during construction of a California nuclear power facility. GRSM’s client was the sole remaining defendant at trial. The plaintiffs asked the jury for $50 million and called 15 witnesses across their case-in-chief and rebuttal.
Read the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
Los Angeles Times Ranks Lewis Brisbois Third Largest Firm in LA County, Largest for Litigation
June 08, 2026 —
Lewis BrisboisThe Los Angeles Times has ranked Lewis Brisbois the third largest firm in LA County by attorney headcount, and first for number of litigation attorneys.
Lewis Brisbois, whose Los Angeles office is led by Co-Managing Partners Jana I. Lubert and Kathleen Walker, has 273 attorneys working in LA County, including 167 partners.
The firm ranked No. 1 for Litigation in the county, with 206 attorneys under the leadership of Partner Craig Holden.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.