Beyond the Storm: How Non-Hurricane Catastrophes Expose Florida’s Construction Defect Blind Spot
August 11, 2026 —
Franchesco “Frank” Soto & Amanda L. Gonzalez - Ball JanikOn June 8, 2026, a magnitude 6.1 earthquake struck the Gulf near the coast of Cuba, the largest instrumentally recorded earthquake in the Gulf since seismic monitoring began in 1950. Buildings swayed, offices were evacuated, and many residents along the east coast of Florida, from Miami-Dade to Jacksonville, felt the ground shake. Although no tsunami followed and reported structural damage was limited, this event exposed a blind spot that Florida property owners, developers, and their counsel cannot afford to ignore: catastrophic stress on Florida buildings does not always come in the form of a named storm.
Florida property owners have grown accustomed to preparing for wind, storm surge, floods, and torrential rain. Far less attention is paid to earthquakes, sinkholes, tornadoes, hail, and non-tropical flooding, each of which can place unexpected stress on buildings not designed with those forces top of mind and can trigger deficiencies in buildings that were not otherwise known, expose design failures, and create an urgency for both insurance claims and subsequent litigation.
Non-Hurricane Triggers of Latent Defects
Seismic activity is the clearest example. Florida’s building code accounts for wind loads, not seismic forces, meaning even a moderate earthquake can reveal weaknesses in curtain wall systems, structural connections, or foundations that were already marginal. Sinkholes, driven by Florida’s karst limestone geology, remain a persistent threat, particularly in Central Florida, where subsurface voids can undermine foundations without warning. Non-tropical flooding, like the record rainfall that flooded South Florida in June 2024, can intrude through building envelopes and waterproofing systems that were never stress-tested for such volumes of water. Tornadoes and hail, while more localized, can cause roofing and envelope failures that mimic, mask, or trigger latent construction defects.
The Litigation and Coverage Disputes That Follow
When one of these events strikes a building already carrying undisclosed or unresolved construction defects, the resulting disputes become considerably more complex. Property owners and associations must move quickly to document existing conditions and distinguish damage caused by the event from pre-existing defective construction, the same causation issue that arises in the hurricane context under Chapter 558, but often without the benefit of established precedent or adjuster experience with these less common events.
Insurance coverage disputes frequently follow close behind. Carriers may dispute whether an earthquake, flood, or other peril is covered at all, particularly where policies contain earthquake or flood exclusions requiring separate endorsements, or anti-concurrent causation language that can bar coverage entirely when a covered peril combines with an uncovered one, such as pre-existing defective construction, to cause a loss. Sinkhole claims carry their own statutory framework under Florida law, requiring specific testing protocols and reporting before a claim is compensable. Developers and contractors, in turn, may find themselves defending Chapter 558 claims while simultaneously litigating with their own carriers over defense and indemnity obligations.
Practical Risk Mitigation Strategies
Property owners, associations, and developers can take several concrete steps to reduce their exposure. First, maintain thorough documentation, including engineering reports, maintenance logs, and photographs, well before any event occurs. This documentation is often the deciding factor in causation disputes. Second, engage structural engineers and consultants immediately following any seismic event, unusual flooding, or storm damage, regardless of whether a hurricane is involved. Prompt inspection preserves evidence and can help prevent inadvertent waiver of construction defect claims. Third, review insurance policies regularly with counsel or a broker to confirm earthquake, flood, and sinkhole coverage matches the property’s actual risk profile, rather than assuming a standard property policy responds to every peril. Fourth, avoid rushing to remediate before conditions are documented and/or before consulting counsel. Well-intentioned repairs can inadvertently compromise evidence needed to prove a defect claim.
The June earthquake was a reminder that Florida’s catastrophic risk profile extends beyond hurricane season. Property owners, associations, and developers who build readiness plans around all forms of catastrophic stress, not just named storms, will be far better positioned when the next unexpected event occurs.
Franchesco “Frank” Soto is a partner in
Ball Janik’s Construction Defect Practice Group in Miami. He may be reached at fsoto@balljanik.com.
Amanda L. Gonzalez is a litigation attorney in
Ball Janik’s Construction Defect Practice Group in Miami. She may be reached at agonzalez@balljanik.com.
Chambers USA 2026 Recognizes Multiple Snell & Wilmer Attorneys and Practices
August 11, 2026 —
Snell & WilmerPHOENIX – Snell & Wilmer is pleased to announce that its attorneys have received 57 individual recognitions in their respective fields, by Chambers USA: America’s Leading Lawyers for Business 2026. These prestigious rankings are driven by independent interviews with clients of the firm and members of the legal community.
Read the full story...Reprinted courtesy of
Snell & Wilmer
Lienor Dealing With “Show Cause” Summons by Condominium Unit Owner
September 01, 2026 —
David Adelstein - Florida Construction Legal UpdatesOne of the statutory vehicles to shorten a construction lienor’s statute of limitations to foreclose on a construction lien is through a “show cause” summons that essentially requires the lienor to foreclose on the lien within 20 days from receipt of the “show cause” summons. This is a statutory procedure under Florida’s Lien Law in
Fla. Stat. s. 713.21(4). If a lienor receives a “show cause” summons and lawsuit, the lienor should, without delay, counterclaim or file a separate lien foreclosure lawsuit within the 20-day period without exception. This is provided the lienor wants to move forward with its lien. If a lienor does not, the lien will be discharged of record. If you are a lienor and receive a “show cause” summons, please immediately consult with construction counsel that can best advise you and perfect your lien rights.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Congratulations to Reno Partner Karen Baytosh for Securing a Complete Dismissal via a Motion for Summary Judgment
July 13, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBWB&O is proud to announce that Reno Partner Karen Baytosh received a significant victory on behalf of the firm’s Developer Client in a high-exposure personal injury matter.
Plaintiff, a teenager, was struck by an intoxicated driver while walking her dog at night, sustaining catastrophic injuries requiring 24-hour critical care for the remainder of her life. Plaintiff’s Guardian brought suit against the drunk driver and her husband, the City, and BWB&O’s Developer Clients, alleging that the City and Developers failed to improve street lighting and install a sidewalk that would have prevented the accident.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
U.S. Supreme Court Decision Alters Course of $745M Louisiana Coastal Damage Judgment
June 15, 2026 —
Jennifer Kretschmann & Jennifer E. Michel - Lewis BrisboisThe U.S. Supreme Court has issued a unanimous decision allowing oil and gas companies to move Louisiana coastal erosion lawsuits from state court to federal court under the federal officer removal statute. While the ruling is procedural, it carries significant implications for environmental- and energy-related risks. The case,
Chevron U.S.A. Inc. v. Plaquemines Parish, Louisiana, Slip Op. 24-813 (April 17, 2026), addressed a threshold jurisdictional question but has broader significance for environmental and climate related litigation. State courts are often viewed as more favorable forums for plaintiffs asserting environmental damage claims, particularly those brought by governmental entities.
The opinion issued on April 17, 2026 is the latest development in long-running Louisiana coastal litigation that began more than a decade ago. Starting in 2013, Louisiana parishes filed 42 lawsuits against oil and gas companies alleging environmental damage related to historic oil field operations. The parishes alleged that oil and gas companies violated state coastal management laws by failing to properly restore impacted areas. Chevron sought to remove the cases from state court under 28 U.S.C. § 1442(a)(1), known as federal officer removal, which provides federal jurisdiction over “any person acting under [an] officer” of the United States "for or relating to any act under color of such office." The Fifth Circuit rejected the argument and remanded the case, and others like it, to state court. Trial began in March 2025 in Point à la Hache, Louisiana. On April 4, 2025, the jury awarded a total of $745 million to compensate for land loss, contamination and abandoned equipment. On June 16, 2025, the U.S. Supreme Court agreed to review the question of whether a federal contractor can remove to federal court when sued for oil-production activities undertaken to fulfill a federal oil-refinement contract.
Reprinted courtesy of
Jennifer Kretschmann, Lewis Brisbois and
Jennifer E. Michel, Lewis Brisbois
Ms. Kretschmann may be contacted at Jennifer.Kretschmann@lewisbrisbois.com
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Read the full story...
New Law Prompts ABC Minnesota/North Dakota to Design New Telecommunications Safety Training Program
June 29, 2026 —
Grace Calengor - Construction ExecutiveOn the first day of the year, a
Minnesota law requiring installers of underground telecommunication infrastructure broadband, fiber or phone lines (when projects utilize directional drilling, and/or work is being conducted within 10 feet of existing utilities) to undergo a 40-hour certification went into effect.
Originally passed in mid-2024 and proposed to go into effect in July 2025, the law’s requirements were postponed until January 2026, giving
ABC Minnesota/North Dakota—in partnership with
NCCER and the
Minnesota Cable Communications Association—time to roll out their
Safety Qualified Underground Telecommunications Installer training program, which would ensure the workforce of their contractor members were certified.
Reprinted courtesy of
Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Construction Liens: Liening for Amounts Not Yet Technically Due Does Not Mean Lien Is Fraudulent
August 11, 2026 —
David Adelstein - Florida Construction Legal UpdatesA 2024 bankruptcy ruling, In re Edgewater Construction Group, Inc., 657 B.R. 668 (S.D.Fla. 2024), touched upon an interesting issue when it comes to construction liens. Is a construction lien fraudulent simply because the lien includes amounts not yet due? Not necessarily.
In this bankruptcy dispute, the subcontractor debtor (that filed for bankruptcy) recorded two construction liens on projects. The general contractor argued in the bankruptcy court that the subcontractor debtor’s liens were fraudulent.
As to the first lien, the general contractor argued that the lien was fraudulent because it included amounts that the debtor knew the general contractor had already paid to the debtor’s subcontractors/suppliers. The bankruptcy court disagreed: “The Court finds that, although the Debtor had been told that [the general contractor] had paid these subcontractors, in light of the ongoing dispute between Debtor and [the general contractor], it was reasonable for the Debtor to demand proof. Debtor’s subsequent filing of a partial satisfaction of lien once the Debtor received the requested proof of payment from [the general contractor] counters any claim of willful exaggeration.” In re Edgewater Construction Group, supra, at 672-673.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Kahana Feld Obtains Favorable Result in High-Exposure NY Premises Liability Case
June 15, 2026 —
Leigh Katz - Kahana FeldKahana Feld partner Leigh Katz obtained a significant victory in a recent matter involving a videotaped alleged trip and fall on the sidewalk in front of the client’s commercial residence. The plaintiff claimed he suffered a knee injury that necessitated surgery, along with other assorted injuries that prevented him from continuing high-level athletic activities. Leigh was able to demonstrate that the fall was staged and received a voluntary discontinuance with prejudice.
At mediation, Leigh emphasized that KF’s expert witness challenged the plaintiff’s claim that the fall was caused by a sidewalk height differential after reviewing the videotape footage and determining the plaintiff’s fall began before his feet made contact with the alleged defect. Based on this analysis, the expert concluded the reported height differential did not initiate the fall, which supported KF’s position that the incident depicted in the video was unrealistic and appeared staged.
Read the full story...Reprinted courtesy of
Leigh Katz, Kahana FeldMs. Katz may be contacted at
lkatz@kahanafeld.com