At the Intersection of Indemnity and Prevailing Wages
March 17, 2026 —
Garret Murai - California Construction Law BlogIn a case that I’m frankly surprised I don’t see more of, the 2nd District Court of Appeal of California examined an indemnity claim by a subcontractor against a general contractor and public entity who mistakenly believed that a construction project did not require the payment of prevailing wages.
The Nabors Case
In
Nabors Corporate Services, Inc. v. City of Long Beach, 108 Cal.App 540 (2025), subcontractor Nabors Corporate Services, Inc. sued general contractor Tidelands Oil Production Company and the City of Long Beach after it was found liable in a class action lawsuit for failing to pay prevailing wages to its employees. Nabors’ contract with Tidelands did not require the payment of prevailing wages and neither Tidelands nor the City believed that the project, which involved “oil well plug and abandonment” work, required the payment of prevailing wages.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
New York Enacts First-in-the-Nation Statewide Data Center Moratorium
August 03, 2026 —
Joshua L. Sturtevant - SheppardAs of May 2026, nearly 12 gigawatts of data center load requests were in the New York Independent System Operator interconnection queue, with more than two-thirds of capacity requests entering the queue in 2025 alone. On July 14, 2026, in response to concerns over this rapid growth, Governor Kathy Hochul issued Executive Order No. 62 (the “Order”) imposing a temporary moratorium on data centers in New York State. Among the concerns cited in the Order are the cost burden on ratepayers associated with transmission upgrades required to accommodate large loads, potential environmental impacts, and large-scale water use.
The moratorium is intended to halt activities while the state government develops a comprehensive legal framework for data center development. While dozens of municipal and county-level moratoriums are in place throughout the U.S., and while the legislatures of several states, including Maine, have proposed moratoriums, the Order is the first statewide moratorium to be enacted nationally.
Read the full story...Reprinted courtesy of
Joshua L. Sturtevant, SheppardMr. Sturtevant may be contacted at
jsturtevant@sheppard.com
Real Estate & Construction News Roundup (7/8/26) – Data Centers Negotiate Flexibility for Speed, Hotel Deal Activities Focus on Luxury, and DC Sues Apartment Owners
July 20, 2026 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, rail projects gain steam across the U.S., AI optimizes building operations, a modular approach speeds data center construction, and more!
- Hyperscalers want their data centers online, and utilities want to provide interconnections, but both are still looking for common operating guidelines. (Herman K. Trabish, Construction Dive)
- Contractors are taking advantage of multibillion-dollar train and transit contracts, even as funding challenges create hurdles for project execution. (Matthew Thibault, Construction Dive)
- Although hospitality and leisure M&A deal volume was down 2.5% in the first half of 2026 compared to the prior six months, investors are concentrating on the upper end of the market, including luxury hotels, wellness resorts and gaming, or “data-rich,” platforms. (Noor Adatia, Hotel Dive)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Settlement Agreements and Contracts Require a Meeting of the Minds
July 20, 2026 —
David Adelstein - Florida Construction Legal UpdatesA settlement agreement does not need to be executed for it to be enforceable as long as there was a MEETING OF THE MINDS. The same rings true for any contract regardless of whether the contract is signed – THERE NEEDS TO BE A MEETING OF THE MINDS.
In a recent case dealing with the settlement agreement on a construction lien, the essential settlement terms (money and mutual release) were memorialized in an e-mail exchange between the parties (owner and subcontractor). The settlement required the owner to pay the principal amount plus some attorney’s fees and then a mutual general release would be prepared. In response to the confirmatory email, the owner sent a check, which the subcontractor deposited, but the owner refused to sign the release signed and sent by the subcontractor. The owner further claimed it doesn’t need to pay the attorney’s fees because the lien amount was paid in full. The subcontractor sued arguing the owner breached the terms of the settlement. The appellate court agreed.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Turnover Traps for Community Associations: Investigate First, Release Claims Later
April 14, 2026 —
Nicholas B. Vargo - Ball Janik LLPTurnover of a community association from developer control to owner control is a uniquely vulnerable moment. Developers are increasingly presenting Florida condominium and homeowners’ associations with “standard” settlement or release agreements at turnover, often being framed as routine steps to finalize the transition of control. In reality, these agreements can have sweeping consequences, including the release of construction-defect claims before the association has conducted any meaningful independent evaluation.
The developer has years of project knowledge and access to plans, subcontractors, and internal records. The newly elected board is just beginning to organize, obtain documents, and understand the property’s condition. Many defects, especially those involving roofing, waterproofing, windows, or structural components, are latent and not yet visible. Signing a release at this stage means the association is making a binding decision under conditions of uncertainty, without full information, to release all future potential claims.
Over the last few years, there has been a rise in reports of developers offering a packaged deal: they agree to complete certain repairs, often minor punch-list or cosmetic items, and to “forgive” an alleged financial deficit (often around $50,000) supposedly owed by the association from the developer-control period. In exchange, the association is asked to sign a broad release covering all claims, including known and unknown construction defects. To a new HOA board that received their community with limited operating and reserve funds, they are left with a difficult decision to either accept the developer’s offer or assess their owners to pay this alleged debt.
These agreements are occasionally presented through community management companies, which may describe them as “standard” or "routine.” Whether due to misunderstanding or influence from the developer, management companies can unintentionally reinforce the idea that signing is expected. Any recommendation provided to HOAs about whether to sign these releases could open community management to liability down the road. The best practice for both associations and community managers is to refer any agreements to be reviewed by general counsel for the association.
The following two case studies illustrate the real-world consequences:
Case Study One: A newly transitioned board relies on its management company to negotiate with the developer-builder to resolve irrigation issues, pond concerns, and signage deficiencies, along with forgiving an asserted financial shortfall. In exchange, the board signs a broad release covering all claims, including latent defects.
Within a year, several punch-list items remain incomplete, and more serious issues arise. When the association demands completion, the developer delays, prompting the association to seek advice on how to enforce the settlement agreement. The association hires counsel to hold the developer responsible for both the previously agreed-upon items and newly identified construction defects. However, when the association brings claims against the developer, the developer points to the release of all potential construction defects in the community. Thus, the only remaining remedy is limited to enforcement of the specific punch-list terms. The community, still relatively new, has no viable claims against the developer-builder for the construction defects. With warranties expired and the release, the association must fund repairs through special assessments, despite defects that would otherwise have been actionable.
Case Study Two: A community is presented with a similar agreement as above. The management company encourages execution, suggesting it is standard and even telling the board to “name your price.” The developer also pressures the newly elected board to sign.
Instead of signing, the board consults with their attorney. Counsel advises the board not to sign the release and recommends further investigation. Engineers are retained and identify early indicators of broader issues, including stucco cracking, water intrusion, and irrigation deficiencies. Based on this information, the association declines to sign the release. Subsequent evaluation reveals potentially significant construction-defect claims, allowing the community to pursue recovery that would have been lost under the proposed agreement.
These scenarios underscore a fundamental point: signing a release at turnover is not an administrative formality—it is a major legal decision. Board members act in a fiduciary capacity on behalf of their community, and their decisions can bind all current and future owners. At turnover, an association’s right is to investigate and pursue claims. Preserving that right until a full and independent evaluation is completed is not adversarial—it is responsible governance.
Accordingly, associations should retain independent evaluations of the property and consult qualified legal counsel before signing any “standard” agreements, especially ones involving a release of future claims.
Nicholas B. Vargo is a partner in Ball Janik LLP’s Construction Practice Group. He may be reached at nvargo@balljanik.com.
Limitations of Liability Provisions in Construction Contracts: A Means to Manage Risk and Limit Financial Exposure
June 23, 2026 —
Ellen Chapelle, Richard Reizen, Hannah Batsche - Construction ExecutiveTaking a cue from architects and engineers, construction contractors have started inserting limitation of
liability clauses in their construction contracts to manage risk and limit financial exposure. This article will address the specific risks that can be limited through an LOL, tips for negotiating the LOL terms with reluctant owners to cover those specific risks, how to limit unintended consequences of an LOL (such as relieving an insurer of its obligations to cover certain losses), and approaches to setting the amount of the liability cap in the LOL.
Addressing Particular Risks
An LOL can address a wide range of risks, including:
- Damages for delay
- Liability for non-conforming or defective work
- Liability for third-party bodily injury or property damage
- Liability excluded by a general liability policy (e.g., pollution and cyber liability)
- Liability related to intellectual property
Reprinted courtesy of
Ellen Chapelle, Richard Reizen, Hannah Batsche, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
“The Superintendent Told Us to Do It:” Why Verbal Approval May Not Be Enough
June 02, 2026 —
Andrew Lintner - Colorado Construction Litigation BlogIn construction defect litigation, one scenario appears repeatedly: a subcontractor installs work in a manner that differs from the plans, specifications, manufacturer instructions, or industry standards after being verbally directed to do so by the general contractor, superintendent, architect, or owner’s representative.
At the time, the decision may seem minor. The project is moving quickly, the field team wants to maintain progress, and nobody wants to stop working over what appears to be a small issue. The subcontractor may trust the superintendent or project manager and assume the conversation will be remembered later if questions arise.
Years later, however, when the project experiences problems, the people involved may deny the conversation occurred, remember it differently, or simply no longer remember the project. Without written documentation, the subcontractor can find itself defending claims for defective work, even though it performed the installation exactly as directed.
Read the full story...Reprinted courtesy of
Andrew Lintner, Higgins, Hopkins, McLain & Roswell, LLCMr. Lintner may be contacted at
alintner@hhmrlaw.com
Oracle's $16B Michigan Data Center Secures Financing as Power Contracts Face Appeals
June 08, 2026 —
Bryan Gottlieb - Engineering News-RecordA $16 billion hyperscale data center under construction outside Ann Arbor, Mich., has secured financing backed by Blackstone and other institutional investors, even as the project's power supply agreements now face a legal challenge before the Michigan Court of Appeals.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com