Colorado Supreme Court Reverses Course on Public Project Liens: Key Takeaways From Wadsworth v. Regional Rail Partners
July 27, 2026 —
Amanda E. McKinlay - Snell & WilmerOn April 6, 2026, the Colorado Supreme Court issued a unanimous opinion in Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners, 2026 CO 19, reversing the Colorado Court of Appeals and providing much-needed clarity regarding verified statements of claim (VSOCs) under the Colorado Public Works Act, C.R.S. §§ 38-26-101 et seq. The decision resolves two issues that have generated significant concern among construction industry professionals since the Court of Appeals issued its opinion on August 1, 2024.
Under C.R.S. § 38-26-107(1), a subcontractor on a public works project may file a VSOC with the contracting public entity for amounts due and unpaid for “…furnished labor, materials, sustenance, or other supplies used or consumed by a contractor or his or her subcontractor in or about the performance of the work contracted to be done or that supplies laborers, rental machinery, tools, or equipment to the extent used in the prosecution of the work….” If a claimant files a VSOC for “an amount greater than the amount due” without a reasonable possibility that the amount is due and with knowledge that the claim is excessive, the claimant “shall forfeit all rights to the amount claimed” and becomes liable for the opposing party’s costs and attorneys’ fees. C.R.S. § 38-26-110.
Read the full story...Reprinted courtesy of
Amanda E. McKinlay, Snell & WilmerMs. McKinlay may be contacted at
amckinlay@swlaw.com
Flatiron Said Disputed Concrete Mix Cost Millions on Large Caltrans Project
June 22, 2026 —
Elaine Silver & Richard Korman - Engineering News-RecordFor awhile in 2023, part of the California Dept. of Transportation's (Caltrans) Fix 50 HOV lane and resurfacing project in Sacramento itself needed to be fixed.
Reprinted courtesy of
Elaine Silver, Engineering News-Record and
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story...
Appeals Court Upholds Skanska, Granite Win in ‘I-4 Ultimate’ JV Dispute
June 15, 2026 —
Bryan Gottlieb - Engineering News-RecordA federal appeals court has upheld a lower court’s decision requiring The Lane Construction Corp. to pay roughly $79 million in damages, plus interest, to joint venture partners Skanska USA Civil Southeast and Granite Construction for work on Florida’s I-4 Ultimate highway megaproject in Orlando, which was completed in 2022.
Read the full story...Reprinted courtesy of
Bryan Gottlieb, Engineering News-RecordMr. Gottlieb may be contacted at
gottliebb@enr.com
Builders Risk/Construction All Risks and Delay in Start-Up Coverage for Large Energy Projects: Protecting Revenue Before Operations Begin
September 21, 2026 —
Will Bennett - SDV FenchurchThe Most Significant Loss May Be the Delay, Not the Damage
Power and energy projects are uniquely vulnerable to losses during construction. Whether the project involves a utility-scale solar facility, battery storage installation, a wind farm, transmission project, LNG terminal, or conventional generation facility, loss events in this sector often have consequences far more impactful than the actual cost of repairing damaged property.
Any number of construction losses can delay commercial operation of the facility by months, triggering lost revenues, financing impacts, contractual penalties, and investor concerns. In many cases, those delay-related losses significantly exceed the underlying repair costs.
Construction All Risk (“CAR”) insurance and Delay in Start-Up (“DSU”) coverage are designed to respond to these exposures. However, recovering delay-related losses is far more complicated than many insureds anticipate, particularly when projects involve international stakeholders, global supply chains, and London market insurance placements.
Read the full story...Reprinted courtesy of
Will Bennett, SDV FenchurchMr. Bennett may be contacted at
will.bennett@sdvfenchurch.us
Beyond the Storm: How Non-Hurricane Catastrophes Expose Florida’s Construction Defect Blind Spot
August 11, 2026 —
Franchesco “Frank” Soto & Amanda L. Gonzalez - Ball JanikOn June 8, 2026, a magnitude 6.1 earthquake struck the Gulf near the coast of Cuba, the largest instrumentally recorded earthquake in the Gulf since seismic monitoring began in 1950. Buildings swayed, offices were evacuated, and many residents along the east coast of Florida, from Miami-Dade to Jacksonville, felt the ground shake. Although no tsunami followed and reported structural damage was limited, this event exposed a blind spot that Florida property owners, developers, and their counsel cannot afford to ignore: catastrophic stress on Florida buildings does not always come in the form of a named storm.
Florida property owners have grown accustomed to preparing for wind, storm surge, floods, and torrential rain. Far less attention is paid to earthquakes, sinkholes, tornadoes, hail, and non-tropical flooding, each of which can place unexpected stress on buildings not designed with those forces top of mind and can trigger deficiencies in buildings that were not otherwise known, expose design failures, and create an urgency for both insurance claims and subsequent litigation.
Non-Hurricane Triggers of Latent Defects
Seismic activity is the clearest example. Florida’s building code accounts for wind loads, not seismic forces, meaning even a moderate earthquake can reveal weaknesses in curtain wall systems, structural connections, or foundations that were already marginal. Sinkholes, driven by Florida’s karst limestone geology, remain a persistent threat, particularly in Central Florida, where subsurface voids can undermine foundations without warning. Non-tropical flooding, like the record rainfall that flooded South Florida in June 2024, can intrude through building envelopes and waterproofing systems that were never stress-tested for such volumes of water. Tornadoes and hail, while more localized, can cause roofing and envelope failures that mimic, mask, or trigger latent construction defects.
The Litigation and Coverage Disputes That Follow
When one of these events strikes a building already carrying undisclosed or unresolved construction defects, the resulting disputes become considerably more complex. Property owners and associations must move quickly to document existing conditions and distinguish damage caused by the event from pre-existing defective construction, the same causation issue that arises in the hurricane context under Chapter 558, but often without the benefit of established precedent or adjuster experience with these less common events.
Insurance coverage disputes frequently follow close behind. Carriers may dispute whether an earthquake, flood, or other peril is covered at all, particularly where policies contain earthquake or flood exclusions requiring separate endorsements, or anti-concurrent causation language that can bar coverage entirely when a covered peril combines with an uncovered one, such as pre-existing defective construction, to cause a loss. Sinkhole claims carry their own statutory framework under Florida law, requiring specific testing protocols and reporting before a claim is compensable. Developers and contractors, in turn, may find themselves defending Chapter 558 claims while simultaneously litigating with their own carriers over defense and indemnity obligations.
Practical Risk Mitigation Strategies
Property owners, associations, and developers can take several concrete steps to reduce their exposure. First, maintain thorough documentation, including engineering reports, maintenance logs, and photographs, well before any event occurs. This documentation is often the deciding factor in causation disputes. Second, engage structural engineers and consultants immediately following any seismic event, unusual flooding, or storm damage, regardless of whether a hurricane is involved. Prompt inspection preserves evidence and can help prevent inadvertent waiver of construction defect claims. Third, review insurance policies regularly with counsel or a broker to confirm earthquake, flood, and sinkhole coverage matches the property’s actual risk profile, rather than assuming a standard property policy responds to every peril. Fourth, avoid rushing to remediate before conditions are documented and/or before consulting counsel. Well-intentioned repairs can inadvertently compromise evidence needed to prove a defect claim.
The June earthquake was a reminder that Florida’s catastrophic risk profile extends beyond hurricane season. Property owners, associations, and developers who build readiness plans around all forms of catastrophic stress, not just named storms, will be far better positioned when the next unexpected event occurs.
Franchesco “Frank” Soto is a partner in
Ball Janik’s Construction Defect Practice Group in Miami. He may be reached at fsoto@balljanik.com.
Amanda L. Gonzalez is a litigation attorney in
Ball Janik’s Construction Defect Practice Group in Miami. She may be reached at agonzalez@balljanik.com.
Newmeyer Dillion Ranked in Chambers Spotlight California 2026 Guide
May 26, 2026 —
Newmeyer DillionNEWPORT BEACH, Calif. – May 14, 2026 - Prominent business and real estate law firm Newmeyer Dillion has been ranked in Chambers Spotlight California 2026 guide and recognized as a leading firm in Litigation: General Commercial for Orange County.
Newmeyer Dillion was selected based on an independent and in-depth market analysis, coupled with an assessment of the firm’s experience, expertise and caliber of talent where the firm stood out for its exceptional work and is recognized in Litigation: General Commercial.
Managing Partner Paul Tetzloff expressed the firm's gratitude: “It is an honor for our firm to be recognized by Chambers and Partners in their Spotlight California 2026 guide. This acknowledgment reflects our commitment to providing high quality legal services tailored to the unique needs of our clients.”
Read the full story...Reprinted courtesy of
Newmeyer Dillion
Meet BWB&O’s Super Lawyers Rising Stars in Colorado!
April 08, 2026 —
Dolores Montoya - Bremer Whyte Brown & O’Meara, LLPBremer Whyte Brown & O’Meara, LLP is thrilled to share that Partner
Devin Brunson and Associate
Melissa Youngpeter have been named to the Super Lawyers 2026 Colorado Rising Stars list. This recognition reflects their exceptional work in Personal Injury and Civil Litigation.
SUPER LAWYERS RISING STARS
Devin Brunson: 2024-2026
Melissa Youngpeter: 2026
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara, LLP
Integration Can Inoculate in Utah
July 20, 2026 —
Mark O. Morris - Snell & WilmerThe Utah Court of Appeals recently reaffirmed, in the construction context, Utah’s strict approach to enforcing integration clauses to preclude parol evidence and other legal theories that would vary the written terms of a contract. In Reid v. All Surface LC, 2025 UT App 134, decided last September, the court affirmed in all respects the trial court’s grant of summary judgment based on the strength of an integration clause against a homeowner who sued a contractor for breach of contract, breach of the covenant of good faith and fair dealing, fraud, negligent misrepresentation, civil conspiracy, negligence, and breach of the implied warranty of habitability. More recently, however, the same court rejected those same arguments in Tidwell v. Jensen, 2026 UT App 13 as to tort claims arising from a used car sale.
The facts in Reid were sympathetic to the plaintiff. After being told she had a mold issue near a defective basement shower, the plaintiff solicited bids. A remediation contractor advised that while it could address the mold, the shower replacement should be handled by someone else. The plaintiff contacted All Surface LC, a shower replacement contractor. During an interview, the sales representative stated that All Surface could “do full mold remediation, tear everything out, and reframe the shower.” The plaintiff ultimately retained All Surface, expecting it would both resolve the mold issues and replace the shower.
Read the full story...Reprinted courtesy of
Mark O. Morris, Snell & WilmerMr. Morris may be contacted at