Kahana Feld Obtains Favorable Result in High-Exposure NY Premises Liability Case
June 15, 2026 —
Leigh Katz - Kahana FeldKahana Feld partner Leigh Katz obtained a significant victory in a recent matter involving a videotaped alleged trip and fall on the sidewalk in front of the client’s commercial residence. The plaintiff claimed he suffered a knee injury that necessitated surgery, along with other assorted injuries that prevented him from continuing high-level athletic activities. Leigh was able to demonstrate that the fall was staged and received a voluntary discontinuance with prejudice.
At mediation, Leigh emphasized that KF’s expert witness challenged the plaintiff’s claim that the fall was caused by a sidewalk height differential after reviewing the videotape footage and determining the plaintiff’s fall began before his feet made contact with the alleged defect. Based on this analysis, the expert concluded the reported height differential did not initiate the fall, which supported KF’s position that the incident depicted in the video was unrealistic and appeared staged.
Read the full story...Reprinted courtesy of
Leigh Katz, Kahana FeldMs. Katz may be contacted at
lkatz@kahanafeld.com
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLP’s Fort Lauderdale office. He may be reached at shauptman@balljanik.com.
LA Scores Major Victory in a High-Exposure Premises Liability Action
July 06, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPOur firm is proud to announce a decisive defense victory obtained by Partner
Daniel Crespo and Associate
Lauren Landau for our client in a high-exposure premises liability action arising from a 2022 incident at an active school construction site in Perris, California. On March 10, 2026, the Riverside County Superior Court granted Summary Judgment in full for our client, dismissing all claims brought by Plaintiff, who alleged she tripped and fell over a curb while picking up her daughter from school and sustained ankle and wrist injuries as a result.
Through meticulous preparation and the strategic use of construction plans, contractual documents, and onsite surveillance video evidence, our team demonstrated that our client had no ownership, possession, or control over the portion of the existing sidewalk where the incident occurred, with construction plans unambiguously designating the area as pre-existing concrete outside our client’s scope of work, and the Construction Services Agreement expressly reserving control over all existing site improvements to the school district.
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Yet Another Reason That Your Contract Matters
February 10, 2026 —
Christopher G. Hill - Construction Law MusingsI have discussed on several occasions the fact that
construction contracts matter. The words in contracts matter and, in Virginia (as well as other states), most provisions, if not all
will be enforced to the letter. Recently, the Western District of Virginia federal court ruled in a way that reminded me of another reason for a well-drafted contract.
In
Rockingham Precast, Inc. v. American Infrastructure – Maryland, Inc. the Western District of Virginia Court considered a motion to transfer the venue to Maryland filed by American Infrastructure. The plaintiff, Rockingham Precast, a Virginia-based company sued in Virginia. American Infrastructure conceded that VA could be a proper forum for the lawsuit but argued that the form was much too inconvenient and costly for the party and non-party witnesses and that the cost made the forum an unfair place to try the case.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Lewis Brisbois Welcomes Clients and Community Leaders to New Garden City Office Opening
July 27, 2026 —
Lewis BrisboisOn July 15, Lewis Brisbois hosted a ribbon-cutting event for its new Garden City office, which opened in April to serve the Long Island community and beyond.
The event was attended by more than 100 people, including Lewis Brisbois attorneys and staff as well as clients, local business and government leaders, Nassau County Supreme Court judges, and members of the press. Nassau County Executive Bruce Blakeman delivered remarks and cut the ribbon for the office.
Read the full story...Reprinted courtesy of
Lewis Brisbois
2026 Colorado Super Lawyers Recognizes 11 Snell & Wilmer Attorneys
May 05, 2026 —
Snell & WilmerDENVER – Snell & Wilmer is pleased to announce that eleven attorneys in its Denver office have been selected for inclusion in the 2026 Colorado Super Lawyers publication. Of those eleven, four were recognized as Rising Stars.
Super Lawyers is a listing of lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The selection process is multi-phased and includes independent research, peer nominations, and peer evaluations. The final published list represents no more than 5 percent of the lawyers in the state.
Read the full story...Reprinted courtesy of
Snell & Wilmer
Motion for Summary Judgment Granted in Significant California Public Utilities Suit
May 12, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Partner Mike D’Andrea and Associates Ruth Rasiah and Kaylah Abdullah in the Los Angeles office for obtaining a complete dismissal of their clients in a significant claim involving California’s Public Utilities regulations.
After lengthy litigation, BWB&O’s Motion for Summary Judgment was granted against Claimant, Spectrum (Charter Communications), which resulted in a complete dismissal of the action against BWB&O’s clients. At issue was whether California’s Public Utilities Code shifted the common law duty to maintain certain utility equipment in residential areas within Southern California. After significant briefing, the Superior Court found that BWB&O correctly argued that the Public Utilities Code required utility companies, like Spectrum, to fully maintain utility equipment, and that private residents are not responsible for utility maintenance (even if the physical equipment is located on private property).
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Amended Again?! Critical Changes to RPAPL § 881: What New York Contractors and Construction Managers Need to Know
March 10, 2026 —
Mark A. Snyder & David Polazzi - Peckar & Abramson, P.C.Recent amendments to New York’s RPAPL § 881 will significantly change how project teams obtain and maintain access to adjoining properties for construction-related work. The 2025 amendment signed into law by Governor Hochul, and the newly enacted 2026 revisions, will directly impact general contractors (GCs) and construction managers (CMs), as well as their trade contractors who regularly confront neighbor‑access, support‑of‑excavation, and protection‑of‑adjoining‑property challenges. Although we do not advise that GCs and CMs get involved in the “weeds” of license agreements or the prosecution of an action to obtain access pursuant to an RPAPL § 881 action, which are typically owner responsibilities, GCs and CMs should understand the change in law, as there may be circumstances where they are responsible for securing access.
This alert outlines the key statutory changes and explains the operational, scheduling, insurance, and risk‑management implications for the New York construction industry.
Reprinted courtesy of
Mark A. Snyder, Peckar & Abramson, P.C. and
David Polazzi, Peckar & Abramson, P.C.
Mr. Snyder may be contacted at msnyder@pecklaw.com
Mr. Polazzi may be contacted at dpolazzi@pecklaw.com
Read the full story...