2026 Construction Outlook: Dampening Outlook With Some Potential Bright Spots
February 17, 2026 —
Garret Murai - California Construction Law BlogAccording to Dodge Construction Network’s Outlook 2026 Ebook, “the construction industry came roaring into 2025” – with large government investments through the Infrastructure Bill and the CHIPS Act (promoting investment in the domestic semiconductor industry), as well as outsized spending on data centers to support cloud and AI technology – but “throttled back significantly” due to “rapid changes to economic and fiscal policies.”
These changes include short-term cost impacts due to tariffs and labor impacts due to the federal government’s immigration crackdown and long-term concerns following enactment of the One Big Beautiful Bill (OBBBA) which is anticipated to add $3.4 trillion to the federal deficit over ten years.
Read the full story...Reprinted courtesy of
Garret Murai, NomosMr. Murai may be contacted at
gmurai@nomosllp.com
UPDATED: Dominion Sues Feds Over Offshore Wind Project Halt, With Action Possible on Others Shut
February 02, 2026 —
Debra K. Rubin - Engineering News-RecordUPDATED: Dominion Energy
filed a federal lawsuit Dec. 23 in Norfolk, Va. against the U.S. Interior Dept.
immediate construction pause order for its 2.6-GW Coastal Virginia Offshore Wind energy project (CVOW) off Virginia Beach, Va., which it developing to begin operation next year. The project is one of five large East Coast offshore wind projects under construction that the federal agency paused, claiming new "national security" risks. Dominion and OSW Project LLC, the entity that includes project co-owner Stonepeak Partners, a private investor, said they seek a
temporary restraining order.
Read the full story...Reprinted courtesy of
Debra K. Rubin, Engineering News-RecordMs. Rubin may be contacted at
rubind@enr.com
Congratulations to Las Vegas Partner Jeffrey Saab and Senior Associate Shanna Carter on Winning Another Motion for Summary Judgment!
March 17, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner
Jeffrey Saab and Senior Associate
Shanna Carter’s client owned a condo, which he rented out. The tenant allegedly assaulted Plaintiff across the street from the condo, resulting in personal injury, including nerve damage. Shanna did the research and writing, and Jeff argued the Motion for Summary Judgment. The Court ruled, in pertinent part, that the subject assault off property was not foreseeable, resulting in a complete dismissal of the lawsuit with prejudice.
Read the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Yet Another Reason That Your Contract Matters
February 10, 2026 —
Christopher G. Hill - Construction Law MusingsI have discussed on several occasions the fact that
construction contracts matter. The words in contracts matter and, in Virginia (as well as other states), most provisions, if not all
will be enforced to the letter. Recently, the Western District of Virginia federal court ruled in a way that reminded me of another reason for a well-drafted contract.
In
Rockingham Precast, Inc. v. American Infrastructure – Maryland, Inc. the Western District of Virginia Court considered a motion to transfer the venue to Maryland filed by American Infrastructure. The plaintiff, Rockingham Precast, a Virginia-based company sued in Virginia. American Infrastructure conceded that VA could be a proper forum for the lawsuit but argued that the form was much too inconvenient and costly for the party and non-party witnesses and that the cost made the forum an unfair place to try the case.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Settlement Agreements and Contracts Require a Meeting of the Minds
July 20, 2026 —
David Adelstein - Florida Construction Legal UpdatesA settlement agreement does not need to be executed for it to be enforceable as long as there was a MEETING OF THE MINDS. The same rings true for any contract regardless of whether the contract is signed – THERE NEEDS TO BE A MEETING OF THE MINDS.
In a recent case dealing with the settlement agreement on a construction lien, the essential settlement terms (money and mutual release) were memorialized in an e-mail exchange between the parties (owner and subcontractor). The settlement required the owner to pay the principal amount plus some attorney’s fees and then a mutual general release would be prepared. In response to the confirmatory email, the owner sent a check, which the subcontractor deposited, but the owner refused to sign the release signed and sent by the subcontractor. The owner further claimed it doesn’t need to pay the attorney’s fees because the lien amount was paid in full. The subcontractor sued arguing the owner breached the terms of the settlement. The appellate court agreed.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Differing Site Conditions Claim Requires a Misrepresentation
May 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesIf you are entertaining a
differing site conditions claim, consider this Third District Court of Appeals case from the mid-90s.
In Hendry Corp. v. Metropolitan Dade County, 648 So.2d 140 (Fla. 3d DCA 1995), a contractor was hired by Dade County to demolish the old Rickenbacker Causeway in Miami. The original 1941 plans of the causeway were made available to contractors. The lowest bidding contractor that was awarded the project based its bid “on its conclusion that the pilings supporting the old bridge were made of concrete.” Hendry, supra at 141. The contractor based this conclusion on the original plans, its visual observation, and experience.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
SDV Celebrates 30th Anniversary Press Release
April 08, 2026 —
Saxe Doernberger & Vita, P.C.Trumbull, Connecticut – Saxe Doernberger & Vita, P.C. (SDV) is proud to announce the celebration of its 30th anniversary.
Founded in 1996 by three attorneys in a small New Haven, Connecticut office, SDV was built on a clear and focused mission: representing policyholders in insurance coverage matters. Three decades later, that commitment remains at the core of the firm’s identity and has been instrumental in its continued success and reputation nationwide.
Today, SDV is a nationally recognized boutique firm with 50 attorneys serving policyholders across the United States. Building on its longstanding reputation for excellence and client advocacy, the firm is pleased to announce the opening of its newest office in Massachusetts—an exciting milestone that reflects SDV’s continued growth. The new office is led by Managing Partner Anna Perry.
Read the full story...Reprinted courtesy of
Saxe Doernberger & Vita, P.C.
Turnover Traps for Community Associations: Investigate First, Release Claims Later
April 14, 2026 —
Nicholas B. Vargo - Ball Janik LLPTurnover of a community association from developer control to owner control is a uniquely vulnerable moment. Developers are increasingly presenting Florida condominium and homeowners’ associations with “standard” settlement or release agreements at turnover, often being framed as routine steps to finalize the transition of control. In reality, these agreements can have sweeping consequences, including the release of construction-defect claims before the association has conducted any meaningful independent evaluation.
The developer has years of project knowledge and access to plans, subcontractors, and internal records. The newly elected board is just beginning to organize, obtain documents, and understand the property’s condition. Many defects, especially those involving roofing, waterproofing, windows, or structural components, are latent and not yet visible. Signing a release at this stage means the association is making a binding decision under conditions of uncertainty, without full information, to release all future potential claims.
Over the last few years, there has been a rise in reports of developers offering a packaged deal: they agree to complete certain repairs, often minor punch-list or cosmetic items, and to “forgive” an alleged financial deficit (often around $50,000) supposedly owed by the association from the developer-control period. In exchange, the association is asked to sign a broad release covering all claims, including known and unknown construction defects. To a new HOA board that received their community with limited operating and reserve funds, they are left with a difficult decision to either accept the developer’s offer or assess their owners to pay this alleged debt.
These agreements are occasionally presented through community management companies, which may describe them as “standard” or "routine.” Whether due to misunderstanding or influence from the developer, management companies can unintentionally reinforce the idea that signing is expected. Any recommendation provided to HOAs about whether to sign these releases could open community management to liability down the road. The best practice for both associations and community managers is to refer any agreements to be reviewed by general counsel for the association.
The following two case studies illustrate the real-world consequences:
Case Study One: A newly transitioned board relies on its management company to negotiate with the developer-builder to resolve irrigation issues, pond concerns, and signage deficiencies, along with forgiving an asserted financial shortfall. In exchange, the board signs a broad release covering all claims, including latent defects.
Within a year, several punch-list items remain incomplete, and more serious issues arise. When the association demands completion, the developer delays, prompting the association to seek advice on how to enforce the settlement agreement. The association hires counsel to hold the developer responsible for both the previously agreed-upon items and newly identified construction defects. However, when the association brings claims against the developer, the developer points to the release of all potential construction defects in the community. Thus, the only remaining remedy is limited to enforcement of the specific punch-list terms. The community, still relatively new, has no viable claims against the developer-builder for the construction defects. With warranties expired and the release, the association must fund repairs through special assessments, despite defects that would otherwise have been actionable.
Case Study Two: A community is presented with a similar agreement as above. The management company encourages execution, suggesting it is standard and even telling the board to “name your price.” The developer also pressures the newly elected board to sign.
Instead of signing, the board consults with their attorney. Counsel advises the board not to sign the release and recommends further investigation. Engineers are retained and identify early indicators of broader issues, including stucco cracking, water intrusion, and irrigation deficiencies. Based on this information, the association declines to sign the release. Subsequent evaluation reveals potentially significant construction-defect claims, allowing the community to pursue recovery that would have been lost under the proposed agreement.
These scenarios underscore a fundamental point: signing a release at turnover is not an administrative formality—it is a major legal decision. Board members act in a fiduciary capacity on behalf of their community, and their decisions can bind all current and future owners. At turnover, an association’s right is to investigate and pursue claims. Preserving that right until a full and independent evaluation is completed is not adversarial—it is responsible governance.
Accordingly, associations should retain independent evaluations of the property and consult qualified legal counsel before signing any “standard” agreements, especially ones involving a release of future claims.
Nicholas B. Vargo is a partner in Ball Janik LLP’s Construction Practice Group. He may be reached at nvargo@balljanik.com.