Federal Bid Protest Standard of Review and Disparate Treatment with Ratings
August 16, 2026 —
David Adelstein - Florida Construction Legal UpdatesA recent decision out of the Federal Claims Court explains the post-award bid protest standard of review.
In Massman Construction Co. v. U.S., 2026 WL 1971985 (Fed.Cl. 2026), a protestor brought a post-award bid protest after the Army Corps of Engineers awarded the contract to another contractor. The protestor argued that the Army Corps (government) acted irrational in its evaluation through disparate treatment. The Court of Federal Claims agreed and remanded for the Army Corps to “either justify this disparity or explain why [awardee’s] lower-priced, but technically inferior proposal provides the best value to the government.” Massman Construction, supra at *1.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Generic Complaint Alleging Bad Faith is Insufficient
August 24, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insurer’s motion for judgment on the pleadings after determining that the insured’s claims for bad faith and unfair claims settlement practices were insufficiently pled. Navia v. State Farm Fire & Cas. Co., 2026 U.S. Dist. LEXIS 111261 (W.D. N. C. May 20, 2026).
The insured submitted a claim for damages to real property owned by the insured allegedly caused by Hurricane Helene. State Farm advised the insured that only some of the claimed damages were covered by the policy and payment for such damages were denied because the estimate for the covered damages did not exceed the policy’s deductible. The insured sued asserting claims for breach of contract, bad faith, and unfair claim settlement practices.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Before Snowbirds Pay That Florida Condo Bill, Ask This
November 18, 2026 —
Jocelyn R. Rocha - Ball Janik LLPFor many seasonal Florida condominium owners, the first unwelcome surprise of snowbird season may not be a hurricane warning or a higher insurance renewal. It may be a special assessment notice.
Before assuming the entire bill reflects the ordinary cost of condominium ownership, owners should ask: What caused the condition the assessment is meant to address?
What the Assessment is Funding
A special assessment is a charge imposed in addition to regular condominium fees. It can help pay for major repairs or address a reserve shortfall. Reserves are funds set aside for future major repairs and replacements.
Florida’s structural integrity reserve requirements generally prevent covered associations from waiving reserve funding for critical components, including roofs, structural systems, waterproofing and plumbing. A structural integrity reserve study estimates those components’ remaining useful lives, repair or replacement costs, and needed reserve contributions.
A limited extension permits qualifying associations to complete a reserve study with a required milestone inspection, but no later than December 31, 2026. Milestone inspections assess a building’s structural condition. As studies reveal funding shortfalls, owners may face special assessments.
When Repairs May Point to Defects
A reserve study is primarily a funding tool. Its visual inspection does not necessarily determine why repairs are needed. An aging roof may simply need replacement. In a newer building, substantial repairs well before the end of a component’s expected service life may point to defective design, materials or installation.
Patterns across a building deserve attention. Recurring leaks around the same window detail in multiple units may indicate improper flashing or sealant installation. Repeated balcony leaks may reveal waterproofing or drainage failures. Widespread premature concrete cracking or corrosion may warrant investigation into construction quality. A qualified professional should assess the cause, considering maintenance and environmental exposure as well.
A newer building may still have time to pursue claims against the developer, contractors and/or design professionals, making early investigation particularly valuable. Older buildings may also have claims involving more recent renovation or replacement work. Insurance should be evaluated separately: coverage for resulting property damage can differ from coverage for correcting defective work, depending on the policy and facts.
When the Right to Bring a Claim Expires
The timing is critical. Florida Statutes section 95.11 generally imposes a seven-year statute of repose, an outside cutoff for filing construction defect lawsuits. The period generally runs from the earliest applicable issuance of a temporary certificate of occupancy, certificate of occupancy or certificate of completion, or abandonment if construction was not completed. Buying a unit, developer turnover or discovering a hidden defect does not restart that seven-year period.
A separate four-year limitations period may expire sooner. For latent defects, that period generally turns on when the defect was discovered or should have been discovered through due diligence. Counsel should calculate the applicable deadlines promptly. Serving a Chapter 558 presuit notice does not pause the seven-year repose period.
What Owners Should Ask Now
Owners should consider when problems first appeared, whether they recur after repairs, and whether neighbors report similar conditions. Ask the board:
- Does the assessment fund repairs, reserves or both, and what reports support the proposed work?
- Has a qualified professional investigated the cause, and has the association identified potentially responsible parties?
- Have applicable insurance, notice requirements and claim deadlines been evaluated?
- How will evidence and potential claims be preserved while repairs proceed?
Prompt investigation can protect the opportunity to recover appropriate costs from responsible parties or available insurance. Necessary safety repairs should proceed, and potential recovery does not suspend the obligation to pay a lawfully imposed assessment.
Reprinted courtesy of
Jocelyn R. Rocha, Ball Janik LLPMs. Rocha may be contacted at
jrocha@balljanik.com
What Prevents Innovation in Construction from Taking Off
September 15, 2026 —
Aarni Heiskanen - AEC BusinessIn construction, we have the knowledge, technology, and innovative people to radically improve our performance, yet we’re still stuck in old ways. Why is that?
I attended an annual gathering for real estate and construction professionals at Rakennustieto Oy, Finland’s leading building information provider. The day before, a half-day seminar was held at the same venue. During both events, we discussed the need for change in the construction sector. Everyone agreed that we need to radically improve how we produce and share information.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC Business
Delay Matters: Florida’s Fourth DCA Reverses Hurricane Irma Dismissal
June 08, 2026 —
Andrea DeField, Machaella Reisman & Cary D. Steklof - Hunton Insurance Recovery BlogThe mantra “delay, deny, defend” is frequently referenced in discussions of insurance claims handling, though insurers will invariably disavow these tactics. While it would be facially improper for an insurer to delay a coverage decision to gain a tactical advantage, empirical examples nonetheless exist. This very dynamic was addressed by Florida’s Fourth District Court of Appeals when it handed policyholders a win in
Hypoluxo Mariner’s Cay Condo. Assoc’n, Inc. v. Underwriters at Lloyd’s London, No. 4D2024‑2250 (Fla. 4th DCA Apr. 1, 2026), reversing a trial court order dismissing a condominium association’s Hurricane Irma coverage lawsuit against its property insurer.
Delay to Run the Statute of Limitations
Following Hurricane Irma, a condominium association suffered roof and exterior envelope damage, reported an insurance claim, and submitted a sworn proof of loss to its property insurer in compliance with Florida Statute § 627.70132 (2020). The statute establishes a timeframe within which a policyholder must submit a claim for hurricane damage.
Reprinted courtesy of
Andrea DeField, Hunton Andrews Kurth LLP,
Machaella Reisman, Hunton Andrews Kurth LLP and
Cary D. Steklof, Hunton Andrews Kurth LLP
Ms. DeField may be contacted at adefield@hunton.com
Ms. Reisman may be contacted at reismanm@hunton.com
Mr. Steklof may be contacted at csteklof@hunton.com
Read the full story...
Micromobility in Smart Cities: Keeping the Wheels in Motion
May 26, 2026 —
James P. Bobotek - Gravel2Gavel Construction & Real Estate Law BlogMobility is the lifeblood of any city. How people are able to travel in, out and within a metropolitan area is vital to its citizens, businesses, supply chains and social services. And as U.S. cities have expanded in size and population density, the strategies for addressing mobility have evolved. Many have taken different approaches to public transit, and each city boasts a dense tapestry of roadways, walking paths and various parking options. But as cities continue to reexamine infrastructure strategies through smart city technology, a new field of transportation has emerged—micromobility.
Designed for short-distance travel using lightweight vehicles (bikes, e-bikes, e-scooters, etc.), the industry’s global net worth has grown exponentially in recent years to the tune of hundreds of billions, with one forecast predicting it could reach
$340 billion by 2030. Micromobility also finds itself at the forefront of various smart city technological improvements. Geofencing has been implemented in
U.S. cities to determine where micromobility vehicles can operate, control speed limits, and park utilizing the vehicles’ GPS location. Internet of Things (IoT) technologies (satellite-based location receivers, cloud communication, internet links, etc.) have
improved vehicle lifespans by keeping track of when vehicles require service and prevent vandalism and theft. Data collected from vehicles’ location tracking is routinely used for
urban planning and smart city development.
Read the full story...Reprinted courtesy of
James P. Bobotek, PillsburyMr. Bobotek may be contacted at
james.bobotek@pillsburylaw.com
Traub Lieberman Partner Ryan Parker and Associates Robert Biferie and Matthew Groteke Win Final Summary Judgment on Behalf of Homeowner’s Insurance Company
November 02, 2026 —
Ryan S. Parker, Robert Biferie & Matthew Groteke - Traub LiebermanTraub Lieberman Partner Ryan Parker and Associates Robert Biferie and Matthew Groteke won final summary judgment on behalf of their client, a homeowner’s insurance company. The case related to a claim for damage caused by Hurricane Milton, which was reported more than ten months after the date of loss. The homeowner’s insurance company reviewed historical aerial photography of the roof and determined that there was no evidence of damage immediately after the Hurricane, which was inconsistent with the condition of the roof when it was inspected more than ten months later. Additionally, the homeowner’s insurance company was unable to determine when the interior water damage occurred due to the delay in reporting the claim. After a lawsuit was filed, the Traub Lieberman team took depositions of the Plaintiffs and the opposing expert and eventually filed a Motion for Summary Judgment based on the failure to timely report the claim and resulting prejudice to their client. The Court granted the Motion for Summary Judgment finding that notice of the claim was untimely as a matter of law and that the Plaintiffs failed to rebut the legal presumption of prejudice to the insurance company. As a result of the ruling, the insurance company has a valid claim for attorney’s fees.
Reprinted courtesy of
Ryan S. Parker, Traub Lieberman,
Robert Biferie, Traub Lieberman and
Matthew Groteke, Traub Lieberman
Mr. Parker may be contacted at rparker@tlsslaw.com
Mr. Biferie may be contacted at rbiferie@tlsslaw.com
Mr. Groteke may be contacted at mgroteke@tlsslaw.com
Read the full story...
In-House Insight at CSC
October 26, 2026 —
Elaine Y. Lee - Peckar & Abramson, P.C.Elaine Y. Lee, Partner in P&A’s Los Angeles office, sat down with Third Thursday to discuss effective collaboration with in-house counsel, strategies for resolving construction disputes, and the factors that can help determine the best path forward. This discussion previews her upcoming
Construction Super Conference panel, “Same But Different: How In-House Legal Teams Vary in Approach, Role, and Decision-Making,” on December 2nd.
Read the full story...Reprinted courtesy of
Elaine Y. Lee, Peckar & Abramson, P.C.Ms. Lee may be contacted at
elee@pecklaw.com