The GKN Aerospace Chemical Release and the Laws Designed to Address It
July 06, 2026 —
Sean M. Sherlock - Snell & WilmerOn May 21, 2026, a 34,000-gallon storage tank at the GKN Aerospace facility in Garden Grove, California began leaking methyl methacrylate (MMA), a volatile and highly flammable industrial chemical used to manufacture high-strength acrylic plastics. GKN Aerospace makes advanced military and commercial transparencies, such as aircraft canopies, windshields, cabin windows, bullet-resistant glass, and spacecraft windows.
In polymer chemistry lingo, MMA is known as a monomer. Monomers are like individual links to a chain. Under the right conditions they link up (react) with each other to form long-chained polymers, or plastics. MMA is an unstable monomer that requires controlled storage conditions to avoid setting off a polymerization (chain) reaction.
According to early reports, the MMA tank at GKN Aerospace overheated. The cause of the overheating is not yet clear, but the overheating may have created conditions enabling the MMA to initiate polymerization, which in turn generated heat, which in turn generated pressure, activating the tank’s pressure-relief system and releasing MMA vapor into the atmosphere. Concerns about a runaway reaction, massive release, and explosion led the Orange County Fire Authority to order evacuation of approximately 40,000 residents and closure of thirteen schools.
Read the full story...Reprinted courtesy of
Sean M. Sherlock, Snell & WilmerMr. Sherlock may be contacted at
ssherlock@swlaw.com
Turnover Traps for Community Associations: Investigate First, Release Claims Later
April 14, 2026 —
Nicholas B. Vargo - Ball Janik LLPTurnover of a community association from developer control to owner control is a uniquely vulnerable moment. Developers are increasingly presenting Florida condominium and homeowners’ associations with “standard” settlement or release agreements at turnover, often being framed as routine steps to finalize the transition of control. In reality, these agreements can have sweeping consequences, including the release of construction-defect claims before the association has conducted any meaningful independent evaluation.
The developer has years of project knowledge and access to plans, subcontractors, and internal records. The newly elected board is just beginning to organize, obtain documents, and understand the property’s condition. Many defects, especially those involving roofing, waterproofing, windows, or structural components, are latent and not yet visible. Signing a release at this stage means the association is making a binding decision under conditions of uncertainty, without full information, to release all future potential claims.
Over the last few years, there has been a rise in reports of developers offering a packaged deal: they agree to complete certain repairs, often minor punch-list or cosmetic items, and to “forgive” an alleged financial deficit (often around $50,000) supposedly owed by the association from the developer-control period. In exchange, the association is asked to sign a broad release covering all claims, including known and unknown construction defects. To a new HOA board that received their community with limited operating and reserve funds, they are left with a difficult decision to either accept the developer’s offer or assess their owners to pay this alleged debt.
These agreements are occasionally presented through community management companies, which may describe them as “standard” or "routine.” Whether due to misunderstanding or influence from the developer, management companies can unintentionally reinforce the idea that signing is expected. Any recommendation provided to HOAs about whether to sign these releases could open community management to liability down the road. The best practice for both associations and community managers is to refer any agreements to be reviewed by general counsel for the association.
The following two case studies illustrate the real-world consequences:
Case Study One: A newly transitioned board relies on its management company to negotiate with the developer-builder to resolve irrigation issues, pond concerns, and signage deficiencies, along with forgiving an asserted financial shortfall. In exchange, the board signs a broad release covering all claims, including latent defects.
Within a year, several punch-list items remain incomplete, and more serious issues arise. When the association demands completion, the developer delays, prompting the association to seek advice on how to enforce the settlement agreement. The association hires counsel to hold the developer responsible for both the previously agreed-upon items and newly identified construction defects. However, when the association brings claims against the developer, the developer points to the release of all potential construction defects in the community. Thus, the only remaining remedy is limited to enforcement of the specific punch-list terms. The community, still relatively new, has no viable claims against the developer-builder for the construction defects. With warranties expired and the release, the association must fund repairs through special assessments, despite defects that would otherwise have been actionable.
Case Study Two: A community is presented with a similar agreement as above. The management company encourages execution, suggesting it is standard and even telling the board to “name your price.” The developer also pressures the newly elected board to sign.
Instead of signing, the board consults with their attorney. Counsel advises the board not to sign the release and recommends further investigation. Engineers are retained and identify early indicators of broader issues, including stucco cracking, water intrusion, and irrigation deficiencies. Based on this information, the association declines to sign the release. Subsequent evaluation reveals potentially significant construction-defect claims, allowing the community to pursue recovery that would have been lost under the proposed agreement.
These scenarios underscore a fundamental point: signing a release at turnover is not an administrative formality—it is a major legal decision. Board members act in a fiduciary capacity on behalf of their community, and their decisions can bind all current and future owners. At turnover, an association’s right is to investigate and pursue claims. Preserving that right until a full and independent evaluation is completed is not adversarial—it is responsible governance.
Accordingly, associations should retain independent evaluations of the property and consult qualified legal counsel before signing any “standard” agreements, especially ones involving a release of future claims.
Nicholas B. Vargo is a partner in Ball Janik LLP’s Construction Practice Group. He may be reached at nvargo@balljanik.com.
Differing Site Conditions Claim Requires a Misrepresentation
May 14, 2026 —
David Adelstein - Florida Construction Legal UpdatesIf you are entertaining a
differing site conditions claim, consider this Third District Court of Appeals case from the mid-90s.
In Hendry Corp. v. Metropolitan Dade County, 648 So.2d 140 (Fla. 3d DCA 1995), a contractor was hired by Dade County to demolish the old Rickenbacker Causeway in Miami. The original 1941 plans of the causeway were made available to contractors. The lowest bidding contractor that was awarded the project based its bid “on its conclusion that the pilings supporting the old bridge were made of concrete.” Hendry, supra at 141. The contractor based this conclusion on the original plans, its visual observation, and experience.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Are Robotic Coworkers Soon a Reality in Construction?
March 24, 2026 —
Aarni Heiskanen - AEC BusinessGeneral-purpose humanoid robots are in the headlines, but is the hype justified? What’s the point of having a robot home assistant when it still needs a “guy behind the curtain” to control it remotely?
Despite the challenges, robots, even those that look like humans, are seriously considered as future coworkers in business environments.
According to the McKinsey report
‘Will embodied AI create robotic coworkers?‘ the idea that AI-powered robots will become general-purpose coworkers is grounded in real technological progress, but not an overnight reality.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Breaking Ground On New California Public Works Prevailing Wage Requirements
April 27, 2026 —
Heather Frisch, Christopher Bouquet & Ashley Stein - The Construction SeytSeyfarth Synopsis: As of January 1, 2026, AB 889 bulldozed California’s Prevailing Wage law, which impacts public works employers—including public agencies, the contractors that work for them, and private owners and developers whose projects may be subject to public works requirements. The amended law reframes the calculation of fringe benefits for individuals who work on public works project and mandates annualization of such benefits, demolishes the practice of frontloading these benefits, and requires employers to maintain inspection-ready records of compliance.
This year, AB 889 significantly revised California’s prevailing wage law, codified at Labor Code section 1773.1, to clarify the state’s prevailing wage regulations and streamline enforcement. Accordingly, as of January 1, 2026, California public works employers are required to annualize employees’ fringe benefits and maintain specific documentation demonstrating statutory compliance. These new obligations impact public agencies and their contractors, as well as private owners and developers whose projects may be subject to public works requirements. Continue reading for the blueprint of how to comply with the state’s amended prevailing wage law.
Reprinted courtesy of
Heather Frisch, Seyfarth Shaw LLP,
Christopher Bouquet, Seyfarth Shaw LLP and
Ashley Stein, Seyfarth Shaw LLP
Ms. Frisch may be contacted at hfrisch@seyfarth.com
Mr. Bouquet may be contacted at cbouquet@seyfarth.com
Ms. Stein may be contacted at astein@seyfarth.com
Read the full story...
Brandy Price, Dean Pillarella Named to Lawdragon's "Next Generation" List
June 22, 2026 —
Lewis BrisboisCharlotte/North Charleston Partner Brandy G. Price and New York Partner Dean Pillarella have been selected to "The 2026 Lawdragon 500 X – The Next Generation," which recognizes emerging leaders in law.
Lawdragon's annual Next Generation listing highlights up-and-coming attorneys with fewer than 15 years in practice. The legal media company selected these honorees through a combination of peer nominations, extensive journalistic research by Lawdragon editors, and independent vetting.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Celebrating BWB&O’s 2026 Super Lawyers Rising Stars in San Diego!
March 31, 2026 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce that Partners
Jocelyn Russo,
Christina Matian, and Associate
Angelo Perillo have been named to the Super Lawyers 2026 San Diego Rising Stars list. This recognition highlights their outstanding dedication and distinguished service in Family Law, Civil Litigation, and Personal Injury Litigation.
SUPER LAWYERS
Jocelyn Russo: 2023-2026
Christina Matian: 2024-2026
Angelo Perillo: 2024-2026
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara, LLP
PSA: Be Sure to Document (Even When Time is Short)
April 14, 2026 —
Christopher G. Hill - Construction Law MusingsWritten
change orders are a big deal. Almost all construction contracts (at least
the well drafted ones) require written contracts. Written change orders are even important enough that Virginia law
requires these provisions in residential construction contracts.
Why are they so important? Because they are a “mini-contract” of sorts. They
set the expectations, price, time, and work to be performed; work that was not included in the original price or scope for the project. Without this in writing, there will be no record of what the parties agreed to do. Does this sound familiar? Sound like its own contract? It should.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com