Las Vegas Home Builder Still in Bankruptcy
October 23, 2012 — CDJ Staff
American West Development attempted to exit Chapter 11 bankruptcy on September 27, but their plan was turned down by U.S. Bankruptcy Court Judge Mike Nakagawa. According to the Las Vegas Review-Journal, Judge Nakagawa rejected the plan over a trust fund for construction defects. America West’s attorney said they were hoping to complete the process by the end of the year.
Under approved portions of the plan, America West’s owner, Lawrence Canarelli, will retain control of the corporation, although he must contribute $10 million into the firm and an additional $1.5 million into the fund for construction defects. America West faces charges for construction defects reported in the broad range of “less than $20 million” to “as much as $80 million.”
Read the full story…
Mississippi exclusions j(5) and j(6) “that particular part”
June 7, 2011 — CDCoverage.com
In Lafayete Ins. Co. v. Peerboom, No. 3:10cv336 (S.D. Miss. June 2, 2011), claimant homeowner Peerboom hired insured contractor Absolute to raise Peerboom’s house two feet to avoid future flooding. While Absolute was raising the house, it fell, resulting in physical injury to the home. Peerboom sued Absolute for negligence, breach of contract, and fraud, seeking damages for the destruction of the home. Absolute’s CGL insurer Lafayette defended under a reservation of rights and filed a declaratory judgment action.
Read the full story…
Reprinted courtesy of CDCoverage.com
Another Guilty Plea in Las Vegas HOA Scandal
December 20, 2012 — CDJ Staff
A twenty-eighth person has plead guilty in the ongoing Las Vegas HOA scandal. Dax Louderman, who had been a construction company manager had acknowledged that he stole more than $495,000 from his former employers, Alpha 1 Construction and the Stone Canyon Homeowners Association, and further that he did not report this improper income on his tax returns. He has agreed to work with prosecutors and to pay $134,860 to the IRS. His actual sentencing will happen on June 24.
Read the full story…
Texas res judicata and co-insurer defense costs contribution
March 23, 2011 — Original story by CDCoverage.com, March 23, 2011
In Truck Ins. Exchange v. Mid-Continent Casualty Co., No. 03-08-00526-CV (Tex. App. 3d Aug. 27, 2010), insured contractor DCI was sued by the project owner seeking damages for defective construction. DCI tendered its defense to its CGL insurers Truck and Mid-Continent. Truck agreed to defend while Mid-Continent denied a defense. While the underlying suit was pending, Mid-Continent sued DCI, but not Truck, and obtained a judicial declaration of no duty to defend or indemnify DCI in the underlying suit. After settling the underlying suit, Truck sued Mid-Continent seeking contribution towards defense costs and indemnity payments. The state trial court entered summary judgment for Mid-Continent. The intermediate appellate court affirmed.
Read the full story...
Reprinted courtesy of CDCoverage.com
Builder Waits too Long to Dispute Contract in Construction Defect Claim
May 10, 2012 — CDJ Staff
The Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.
The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.
The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.
In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.
The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.
A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”
Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.
Read the court’s decision…
Badly Constructed Masonry Walls Not an Occurrence in Arkansas Law
May 10, 2012 — CDJ Staff
The US District Court for Maryland has granted a summary judgment in the case Konover Construction Corp. v. ATC Associates to Massachusetts Bay Insurance Company and denied a request for dismissal from ACT. Konover (KBE) was contracted by Wal-Mart to build a Wal-Mart store and a Sam’s Club in Port Covington, Maryland. Superus, Inc. was hired by KBE to build the masonry walls. Superus purchased a policy from Massachusetts Bay Insurance which named KBE as an additional insured. Wal-Mart hired ATC Associates to independently test and inspect the concrete structural steel, and masonry.
After the building was in use, a large crack appeared which was attributed a latent construction defect. Other cracks were discovered. Upon investigation, it was discovered that there were “voids or foam in the concrete block surrounding the reinforcing steel that should have been filled with grout,” and in some cases, “reinforcing steel was missing or not installed in accordance with the specifications.” KBE paid for the repair and remediation and Wal-Mart assigned all rights and interests against ATC to KBE.
KBE filed suit against ATC. ATC called for dismissal on the grounds that Wal-Mart had no claims as the problems had been remediated. Wal-Mart then provided KBE with additional agreements to give them enforceable rights against ATC and Superus. KBE filed a fourteen claims against ATC, Superus, and Massachusetts Bay. In the current case, Massachusetts Bay sought summary judgment and ATC sought dismissal of all claims against it.
Massachusetts Bay claims that they need not indemnify Superus, as “there is no evidence adequate to establish that Superus’ defective work caused any collateral and/or resulting damage that was not subject to an Impaired Property exclusion, and that, in any event, no damage occurred during the policy period.”
As Wal-Mart is headquarted in Arkansas, certain contracts were under Arkansas law. Under the Arkansas courts, “defective workmanship, standing alone and resulting in damages only to the work product itself, is not an ‘occurrence.’” The court determined that collateral or resultant damage would be covered. The court found that “it is clear under Arkansas law, and the parties appear to agree, that Massachusetts Bay is not obligated to indemnify KBE for any repairs to the masonry walls themselves, including any cracks or gaps in the walls.” The court also found that “there is no evidence adequate to prove that any allegedly resultant property damage was caused by Superus’ faulty construction of the walls.” The court also noted that “if the building code violation and structural integrity problem were ‘property damage,’ insurance coverage would be barred by the Impaired Property Exclusion.” Based on these findings, the court concluded that Massachusetts Bay is entitled to summary judgment.
While the court dismissed the case against Massachusetts Bay, the court declined ATC’s motion to dismiss. The court noted that ACT’s alleged negligence in conducting inspections “created only a risk of economic loss for KBE.” Although hired by Wal-Mart, ATC “transmitted its daily testing and inspection reports of the Wal-Mart and Sam’s Club projects directly to KBE.” The court found that “KBE has made a plausible claim.”
ATC also claimed that KBE contributed to the negligence due to the negligence of its subcontractor. The court concluded that it was plausible that “ATC will not be able to carry its burden of proving KBE was contributorily negligent.” The court was less sanguine about KBE’s fraud claim, but though it “may not now appear likely to have merit, it is above the ‘plausibility’ line.”
In conclusion, KBE may not continue its case against Massachusetts Bay. However, the judge allowed the other proceedings to continue.
Read the court’s decision…
Home Builder Doesn’t See Long Impact from Hurricane
November 7, 2012 — CDJ Staff
No one needs to tell Toll Brothers about the impact of Hurricane Sandy. The Wall Street Journal reports that the home building company lost power as a result of the storm. Martin Connor, the company’s CFO, told the Journal that he did not expect the hurricane to have a big effect on sales. Luckily for the company, many of its large projects are either sufficiently completed to provide shelter or too early in the process to be affected by the storm. “This type of weather event has limited impact on the market. It may move settlements later, and may defer people a weekend or two until they go out shopping. But it doesn’t have a long impact.”
Read the full story…
Green Buildings Could Lead to Liabilities
March 28, 2012 — CDJ Staff
Attempts to build “green,” reducing energy costs and increasing the use of sustainable building materials, may lead to more lawsuits, according to a report issued by the British Columbia Construction Association. The report warned those who were going to build green look into the implications. The report looked at the result of green building practices and requirements adopted in the United States.
The report warns that “the use of novel, less harmful building material or new construction techniques may give rise to liability due to: contractor inexperience with installation; lack of long-term evaluation of green materials; lack of understanding of how new building materials may impact existing traditional building systems; or warranties provided unintentionally about the durability or effectiveness of unproven materials or techniques.”
Manley McLachlan, president of the BCAA noted that they are aware of “legal action around the performance of the buildings,” noting that while fast-growing trees help toward LEED certification, their wood is more prone to mold. He also felt that low-VOC paints needed more testing to prove their durability as exterior finishes.
Read the full story…
Construction Defect Exception Does Not Lift Bar in Payment Dispute
September 13, 2012 — CDJ Staff
The Court of appeals of Oregon has affirmed the ruling of a lower court, agreeing that ORS 701.131(1) bars John Pincetich from pursuing a payment dispute against his clients, Thomas and Frances Nolan. The Nolans hired Mr. Pincetich to build a home, during which time Mr. Pinchtich lost his license due to a lapse in liability insurance. Mr. Pincetich was reinstated after reestablishing insurance.
After the house was concluded, a dispute over payment arose. The Nolans claimed that Mr. Pincetich was unable to bring an action against them as ORS 701.131(1)(b) specifies that the contractor must hold a license “continuously while performing the work for which compensation is sought.” As there were fourteen days in which Mr. Pincetich did not hold a license, the trial court concluded that this law did not apply.
Mr. Pincetich claimed that in hiring him, the defendants became residential developers. Mr. Pincetich argued that developers are exempted under ORS 701.121(2)(C), but this was rejected by the trial court. This formed the basis of his appeal. The appeals court concluded that the exception he cited was motivated to “further benefit consumers by providing authority for unlicensed contractors to pursue third-party claims in construction-defect cases.” The court concluded that Mr. Pincetich’s reasoning would “allow unlicensed contractors to do the very thing that the claims bar is intended to prevent them from doing.”
Read the court’s decision…
Quarter Four a Good One for Luxury Homebuilder
December 20, 2012 — CDJ Staff
Toll Brothers has announced that their fourth-quarter net income is $2.35 per share, which they attribute in part to an income tax benefit. Their revenue, at $632.8 million, easily exceeded analysts’ projections of $565.1 million. Additionally, their number of signed contracts jumped seventy percent while their cancellation rate dropped nearly half to 4.9 percent.
Read the full story…
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 — April 28, 2011 Beverley BevenFlorez - Construction Defect Journal
In the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision…
Nevada Bill Aims to Reduce Legal Fees For Construction Defect Practitioners
March 21, 2011 — March 21, 2011 Construction Defect Journal Staff
Assemblyman Ira Hansen and twelve additional members of Nevada’s Assembly are sponsoring Assembly Bill 285. AB 285 Revises provisions governing an award of attorney’s fees in causes of action for constructional defects. Existing law generally provides that a claimant may recover reasonable attorney’s fees as part of the claimant’s damages in a cause of action for constructional defects. (NRS 40.655)
This bill removes this provision and instead authorizes a court to award reasonable attorney’s fees to a prevailing party involved in such a cause of action if an independent basis for the award exists pursuant to existing law which authorizes a court to award attorney’s fees in certain circumstances, or Rule 68 of the Nevada Rules of Civil Procedure, which provides for the payment of reasonable attorney’s fees by an offeree who rejects an offer and subsequently fails to obtain a more favorable judgment.
In an AP report published in Business Week it is suggested that the target objective of legislators centers on what it refers to as Nevada’s "Rampant construction defect lawsuits".
According to Business Week "The suits bring in hundreds of millions of dollars for lawyers and have put construction companies out of business. Hansen says fewer construction firms mean higher prices for Nevada consumers."
Click Here To Read Full Text and Revisions of Assembly Bill 285
2011 Worst Year Ever for Home Sales
September 9, 2011 — CDJ Staff
So few new single-family homes have sold in 2011 that expectations are that this will be the worst year for new homes sales since the Commerce Department started tracking this in 1963. The Harford Courant notes that previously builders created a new supply to which was added homes under foreclosure.
Ed Leamer, economist and director of UCLA’s Anderson Forecast, says that recovery would be driven by two sectors, manufacturing and construction. “It doesn’t look like there is going to be a big recovery in manufacturing,” he says. “It is going to have to come in housing.”
The soft housing market, however, is leading to a loss of construction jobs, as reported by the Associated General Contractors of America. As a result, stock prices for the twelve largest publicly-traded home builders have declined 22.7 percent in a market that has declined 4.2 percent overall.
Read the full story…
Unit Owners Have No Standing to Sue under Condominium Association’s Policy
February 10, 2012 — Tred Eyerly, Insurance Law Hawaii
If a condominium owner suffers damage caused by a leak from another unit, may it sue the insurer for the Association of Apartment Owner (AOAO) for coverage? The federal district court for Hawaii said "no" in a decision by Judge Mollway. See Peters v. Lexington Ins. Co., 2011 U.S. Dist. LEXIS 148734 (D. Haw. December 27, 2011).
Two cases were consolidated. In each case, Plaintiffs owned condominium units at the Watercrest Resort on Molokai. Water leaking from another unit damaged Plaintiffs’ units.
Watercrest Resort was insured by Lexington pursuant to a policy maintained by the AOAO. Plaintiffs filed claims with Lexington. Lexington hired an adjustor.
Unhappy with the adjustment of their claims, Plaintiffs sued Lexington and the adjustor.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Negligent Construction an Occurrence Says Ninth Circuit
June 30, 2011 — CDJ Staff
One June 27, the US Court of Appeals has rejected an appeal from Mid-Continent Casualty Company. Mid-Continent had appealed a summary judgment granted to Titan Construction Company.
Titan Construction had built condominiums for the Williamsburg Condominium Association, which later filed a construction defect lawsuit against Titan and other defendants. Titan settled with the developer, Kennydale, assigning its rights against Mid-Continent to Kennydale. Mid-Continent filed suit, claiming that “it had no obligation to indemnify or defend Titan, Kennydale, or various other defendants.” The district court found in favor of Mid-Continent, granting a summary judgment, concluding that Titan’s insurance covered “occurrences,” and none had taken place.
On appeal, the court found that the negligent construction of the condominiums constituted an “occurrence” The case was remanded and the district court this time found in favor of Titan, “concluding that Mid-Continent failed to raise a triable issue as to the applicability of the remaining policy exclusions.
The Ninth Circuit Court of Appeals has now affirmed that decision and Titan’s summary judgment stands.
Read the court’s decision…
Firm Sued For Construction Defects in Parking Garage
October 23, 2012 — CDJ Staff
Northhampton County, Pennsylvania is suing a contractor who resurfaced a parking garage in 2009. According to the Express-Times, three years later, the surface is cracked and the county is seeking $700,000 for repairs. Additionally, they have withheld $44,000 of the $2.2 million contract because of the problems. John Stoffa, Northampton County Executive, says that the garage is stable, but not up to safety standards.
Read the full story…
Condominium Exclusion Bars Coverage for Construction Defect
August 17, 2011 — Tred Eyerley, Insurance Law Hawaii
Coverage was denied under the policy’s condominium exclusion in California Traditions, Inc. v. Claremont Liability Ins. Co.,2011 Cal. App.LEXIS912 (Cal. Ct. App., ordered published July 11, 2011).
California Traditions was the developer and general contractor for a housing development. California Traditions subcontracted with Ja-Con to perform the rough framing work for 30 residential units. The project had 146 separate residences that were freestanding with no shared walls, roof, halls, or plumbing or electrical lines. To allow a higher density development, the project was developed, marketed and sold as condominiums.
The purchaser of one of the units filed a complaint against California Traditions alleging property damage from the defective construction. California Traditions cross-complained against Ja-Con.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Anti-Concurrent Causation Clause Bars Coverage for Landslide and Water Leak
June 19, 2012 — Tred Eyerly, Insurance Law Hawaii
The insured unsuccessfully attempted to get around the policy’s anti-concurrent causation clause by arguing a covered cause of loss was a contributing factor. See Stor/Gard, Inc. v. Strathmore Ins. Co., 2012 U.S. Dist. LEXIS 63217 (D. Mass. May 4, 2012).
A building at the insured’s storage facility was damaged when heavy rain caused a mass of soil to slide down a slope, causing soil and a retaining wall to fall on the building. The accident caused a partial collapse of the building. The insurer hired two soil engineers, each of whom concluded that a landslide caused the accident. The reports also noted, however, that a leak from the property’s drainage system resulted in a very small percentage of water infiltrating the ground.
The insurer denied coverage based upon an exclusion for landslides.
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the full story…