LEED Certified Courthouse Square Negotiating With Insurers, Mulling Over Demolition
June 6, 2011 — Douglas Reiser in the Builders Counsel Blog
Apparently, Courthouse Square is still unresolved. The County hasnow hired an attorney to handle its insurance claim against Affiliated FM. Is there a lawsuit coming?
Right now, no lawsuit is expected. According to officials, the insurer has been acting in good faith. But, its been quite a while since Salem officials learned that the Courthouse Square building had significant concrete issues that would result in probable demolition of the LEED certified building.
If you have yet to hear about Courthouse Square, let me fill you in briefly. The Salem building was substantially completed in 2000 and LEED certified by the US Green Building Council in 2002. The project cost more than $30 Million to complete and the building was revered for its innovation as a crowning achievement for city leaders.
But, structural problems in the building’s core were discovered as early as 2002, writes Chris Cheatham of Green Building Law Update. Final tests earlier in the year, determined that the building had to be vacated. The building has been clear since July 2010.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Colorado “property damage” caused by an “occurrence” and exclusions j(5) and j(6) “that particular part”
August 11, 2011 — CDCoverage.com
In Continental Western Ins. Co. v. Shay Construction, Inc., No. 10-cv-02126 (D. Col. July 28. 2011), general contractor Milender White subcontracted with insured Shay for framing work.  Shay in turn subcontracted some of its work to others. When Shay?s subcontractors filed suit against Shay and Milender White seeking payment for their work, Milender White cross-claimed against Shay for breach of contract alleging that,Milender White notified Shay during construction that some of Shay?s work was defective and that when Shay repaired its defective work, it damaged work performed by others. Shay’s CGL insurer Continental Western filed suit against Milender White and Shay seeking a judicial declaration of no coverage. The federal district trial court granted Continental Western?s motion for summary judgment.
Read the full story…
Reprinted courtesy of CDCoverage.com
Michigan Supreme Court Concludes No Statute of Repose on Breach of Contract
July 19, 2011 — CDJ Staff
Judge Marilyn Kelly of the Michigan Supreme Court has remanded the case of Miller-Davis Co. v. Ahrens Constr. Inc. (Mich., 2011) to the Court of Appeals, after determining that the court had improperly applied the statute of repose. She reversed their judgment, pending a new trial.
Ahrens Construction was a subcontractor, hired by Miller-Davis to build and install a natatorium room at a YMCA camp in Kalamazoo, Michigan. After its installation, the YMCA discovered a severe condensation problem, causing moisture to “rain” from the roof. The architect, testifying for Miller-Davis, alleged that the problems were due to improper installation by Ahrens. Ahrens claimed that the condensation problem was due to a design error.
When the roof was removed and reconstructed, the moisture problem ended. Ahrens argued that the alleged defects were caused by the removal. Further, in trial Ahrens raised the issue of the statute of repose. The court found in favor of Miller-Davis and did not address the statute of repose.
The Court of Appeals reversed the trial court, determining that the statute of repose had barred the suit. This rendered the other issues moot.
The Michigan Supreme concluded that the issue at hand was “a suit for breach of contract,” and that the Michigan statute of repose is limited to tort actions. They remanded the case to the Court of Appeals to address the issues that had been mooted by the application of the statute of repose.
Read the court’s decision…
An Upward Trend in Commercial Construction?
March 28, 2012 — Melissa Dewey Brumback, Construction Law North Carolina
Year-end economic indicators demonstrate that private commercial construction may be increasing in 2012, primarily as demand grows for new projects built in the United States.
According to an article in Businessweek, the Architecture Billings Index held at 52 in December, indicating a modest expansion in the market. The American Institute of Architects said that the commercial and industrial component of the number climbed to 54.1 in December, the highest in 10 months.
The monthly survey of U.S.-based architecture firms is one of the main indicators of nonresidential construction, and these numbers suggest that modest improvement may be on the horizon.
The information is confirmed by data from the Census Bureau that shows that spending on lodging, office, commercial and manufacturing buildings grew 8.2 percent in November to $9.2 billion from a year ago. These types of commercial and industrial projects are historically canaries in the mine and are usually the first part of the industry to improve as the economy expands.
Read the full story…
Reprinted courtesy of Melissa Dewey Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Georgia Law: “An Occurrence Can Arise Where Faulty Workmanship Causes Unforeseen or Unexpected Damage to Other Property”
March 5, 2011 — By
CDCoverage.com, March 5, 2011
In American Empire Surplus Lines Ins. Co. v. Hathaway Development Co., Inc., No. S10G0521 (Ga. March 7, 2011), insured plumbing subcontractor Whisnant was sued by general contractor Hathaway seeking damages for costs incurred by Hathaway in repairing damage to property other than Whisnant’s plumbing work resulting from Whisnant’s negligently performed plumbing work on three separate projects. On one project, Whisnant installed a pipe smaller
Read the full story...Reprinted courtesy of CDCoverage.com
Save A Legal Fee? Sometimes You Better Talk With Your Construction Attorney
May 10, 2012 — Douglas Reiser, Builders Counsel
I love writing this column, because I think it’s refreshing for contractors to hear that they don’t always need an attorney. Today’s post is the “Un-Save a Legal Fee” because I want to point out a specific illustration of when you definitely need your attorney. Using a construction contract template can be fine, but you always need to consider its application to each project ? or it could bite you in the rear.
Seattle attorney Paul Cressman published a prime depiction of bad contract management, last week. A Florida appellate court struck down a general contractor’s “pay if paid” clause when it became ambiguous because of some incorporated language from its prime contract. Specifically, a clause in the prime contract required the general contractor to pay all subcontractors before receiving payment from the owner, while the general contractor’s “pay if paid” clause required its subcontractors to wait for payment until it arrived from the owner.
Read the full story…
In Oregon Construction Defect Claims, “Contract Is (Still) King”
April 25, 2012 — CDJ Staff
Writing in Oregon’s Daily Journal of Commerce, David Anderson looks at the aftermath of the case Abraham v. T. Henry Construction, Inc. In that case, Anderson notes that “the homeowners hired a contractor to build their house, and subsequently discovered extensive water damage” “after expiration of the time to sue for breach of contract.” The homeowners claimed negligence. Oregon’s Supreme Court concluded that “homeowners only had to prove that the contractor negligently caused reasonably foreseeable harm to the homeowner’s property.”
Anderson views this decision as leading to two risks for contractors. “First, contractors can be held liable in tort for breaching building code standards; second, they can be held liable for violating the often-difficult-to-define ‘reasonable care’ standard.” But here, “contract can be king.” The Oregon Supreme Court noted that the contractor “could have avoided exposure to the general ‘reasonable care’ standard by more carefully defining its obligations in the original construction contract.”
He notes that contractors who fail to define their obligations or use generic definitions “may be exposing themselves to a more vague scope of liability.”
Read the full story…
Housing Prices Up through Most of Country
December 20, 2012 — CDJ Staff
Home prices in October were up more than six percent compared with prices in October 2011. The LA Times noted that some of the strongest gains were in California and Arizona. The Phoenix metropolitan area saw a 24.5% rise in home prices. In California, Riverside and Los Angeles were just above the national average, at 7.3% and 6.4%, contributing to the state’s overall nine percent increase.
The news wasn’t good throughout the entire country, as five states did not see any price increases. Mark Fleming, the chief economist at CoreLogic, a research firm in Irvine, California said that “the housing recovery that started earlier in 2012 continues to gain momentum.
Read the full story…
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 — CDJ Staff
The California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Lien Claimant’s Right to Execute against Bond Upheld in Court of Appeals
February 10, 2012 — Douglas Rieser, Builders Counsel
Stonewood v. Infinity Homes is a simple construction dispute over a matter of about $9,000.00. But sometimes these tiny little disputes turn into expensive legal battles over mere procedural quivering. In Stonewood, a small subcontractor won a big victory yesterday when the Divison 1 Court of Appeals upheld its judgment against a lien release bond posted by an owner.
Infinity Homes contracted with Stonewood Design to lay tile in one of its customer’s homes. Stonewood did the work, but Infinity withheld roughly $9,000.00 of the contract sums for what it alleged were trade damages left on the tile. The two parties were unable to come to an agreement over payment and Stonewood proceeded with a lien under RCW 60.04. It then filed an action to enforce the lien against the homeowner, Infinity and its bonding company.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Minnesota Starts Wide-Ranging Registration of Contractors
July 10, 2012 — CDJ Staff
Minnesota has replaced its Independent Contractor Exemption Certificate program with the Contractor Registration Pilot Project, according to an article in the Martindale-Hubble Legal Library by Michael B. Lapicola. Mr. Lapicola notes that “it will be a violation of the law to contract with or perform construction services for another person without first being registered with the Pilot Project, or to contract with or pay another person to perform construction services if the other person is not registered with the Pilot Project. There are, however, quite a few exceptions, including those who are currently registered with the earlier program. Additionally, independent contractors who do not register can avoid the fine (up to $2,000) by registering within thirty days of fines being levied. Individuals and firms that do not perform building construction or improvements are exempt from the hiring aspects of the statute.
Minnesota’s goal is to “assist state agencies to investigate employee misclassification in the building industry.” Employees of construction firms do not individually register. Rather, the intent of the of law is to stop those who would “require any individual through coercion, misrepresentation or fraudulent means to adopt independent contractor status” or to “knowingly misrepresent or misclassify an individual as an independent contractor.”
Read the full story…
Homebuilding on the Rise in Nation’s Capitol
November 7, 2012 — CDJ Staff
Is the homebuilding crunch over in DC? The Washington Post has reported that while new home construction is up throughout the country, in the DC area, construction has reached levels last seen in 2006. From January to August 2012, there were more than 19,000 building permits issued in the area, nearly doubling the number issued by that point in 2011.
While building is on a quicker pace, what’s being built has changed. As compared to 2006, there are more townhomes, condos, and smaller homes being built. The article notes that 11 percent of new construction is condos, while in 2006, it was only 5 percent.
Read the full story…
The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 — By Shaun McParland Baldwin, March 17, 2011
The Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury or “property damage” be caused by an occurrence and that the “bodily injury or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury” or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivanrsquo;s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing, including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Construction Employment Rises in Half of the States
December 9, 2011 — CDJ Staff
The Labor Department has noted that half the states and the District of Columbia saw increases in construction employment during the month of October. During the same month, twenty-three states lost construction jobs.
The biggest gains were in North Dakota, Oklahoma, DC, Texas, and California. The biggest losses were in Georgia, New Mexico, Wisconsin, and Florida. There was no change for Alabama.
The chief executive officer of the Association of General Contractors of America, Stephen E. Sandherr, called for more infrastructure development. “Allowing water, transportation and energy networks to deteriorate will hurt construction employment and force taxpayers to spend more later, to fix broken infrastructure.”
Read the full story…
Continuous Trigger of Coverage Adopted for Loss Under First Party Policy
August 2, 2012 — Tred Eyerly, Insurance Law Hawaii
The Seventh Circuit predicted that the Wisconsin Supreme Court would adopt the continuous injury trigger for first party property loss that extends over several policy periods. Miller v. Safeco Ins. Co. of Am., 2012 U.S. App. LEXIS 12940 (7th Cir. June 25, 2012).
A home inspection report performed before the Millers purchased their home showed a soft spot on the roof. The stucco's finish color was also uneven and stained. Further, some water damage was found in the study and skylights above the kitchen sink. But the report advised that the exterior walls, chimney, grass roof, flashings, floor joists/beams and columns, garage walls and floor appeared serviceable. A roof specialist determined the soft spot was not significant and could be repaired for $1,500.
The Millers purchased a homeowner's policy from Safeco on June 30, 2005. The policy went into effect the next day when the Millers closed on the property. But the Millers did not see the policy's terms until Safeco mailed them a copy of the policy at the end of July.
Before receiving the policy, the Millers discovered severe inner wall water leaks and significant water infiltration on three of the home's exterior walls.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Repair of Part May Necessitate Replacement of Whole
February 10, 2012 — CDJ Staff
Judge Gleuda E. Edmonds, a magistrate judge in the United States District Court of Arizona issued a ruling in Guadiana v. State Farm on January 25, 2012. Judge Edmonds recommended a partial summary judgment in favor of the plaintiff.
Ms. Guandiana’s home had water damage due to pluming leaks in September 2004. She was informed that polybutylene pluming in her house could not be repaired in parts “it must be completely replaced.” She had had the plumbing replaced. State Farm denied her claim, arguing that “the tear-out provision did not cover the cost of accessing and replacing those pipes that were not leaking.”
In September 2007, State Farm filed a motion to dismiss. The court rejected this motion, stating that “If Guadiana can establish as a matter of fact that the system that caused the covered loss included all the pipes in her house and it was necessary to replace all the pipes to repair that system, State Farm is obligated to pay the tear-out costs necessary to replace all the pipes, even those not leaking.”
In March 2009, State Farm filed for summary judgment, which the court granted. State Farm argued that “the tear-out provision only applied to ‘repair’ and not ‘replace’ the system that caused the covered leak.” As for the rest of the piping, State Farm argued that “the policy does not cover defective materials.”
In December 2011, Ms. Guadiana filed for summary judgment, asking the court to determine that “the policy ‘covers tear-out costs necessary to adequately repair the plumbing system, even if an adequate repair requires replacing all or part of the system.”
In her ruling, Judge Edmonds noted that Ms. Guadiana’s claim is that “the water damage is a covered loss and she is entitled to tear-out costs necessary to repair the pluming system that caused that covered loss.” She rejected State Farm’s claim that it was not obligated to replace presumably defective pipes. Further, she rejected State Farm’s argument that they were only responsible for the leaking portion, noting “Guadiana intends to prove at trial that this is an unusual case where repair of her plumbing system requires replacement of all the PB plumbing.”
Judge Edmonds concluded by directing the District Court to interpret the tear out issue as “the tear-out provision in State Farm’s policy requires State Farm to pay all tear-out costs necessary to repair the plumbing system (that caused the covered loss) even if repair of the system requires accessing more than the leaking portion of the system.”
Read the court’s decision…
No “Special Relationship” in Oregon Construction Defect Claim
July 10, 2012 — CDJ Staff
Writing on his firm’s blog, Justin Stark discusses recent changes in construction defect claims in Oregon where, as he points out, “courts in Oregon have been lowering legal hurdles that construction defect plaintiffs must overcome in bringing their cases.” He cites a case in which water damage was discovered more than six years after construction was complete. The owners claimed breach of contract and negligence. The trial court found for the contractor, who argued “that there was no ‘special relationship’ with the owners that could support the negligence claim.”
This was overturned on appeal, with the court concluding that if there was a violation of the building code, then the negligence claim could stand. This was appealed to the Oregon Supreme court which concluded that “neither a special relationship nor a statutory standard of care, such as the building code, is necessary to bring a negligence claim here.”
Stark notes that “many forms of construction contract incorporate the phrase ‘workmanlike,’ which implicates the ‘common law standard of care’ in negligence law.
Read the full story…
Statute of Repose Dependant on When Subcontractors Finished
July 10, 2012 — CDJ Staff
Scott C. Sandberg of Snell and Wilmer writes a post on the JDSupra site about the Colorado Court of Appeals decision in Shaw Construction v. United Builder Services. Sanberg notes that when the general contractor was sued by an HOA, the contractor turned around and sued its subcontractors. The contractor made three claims. They claimed that “improvement” referred to the whole project, that “substantial completion” was reached when the architect certified completion, and that the statute of repose was tolled by the HOA’s service of a Construction Defect Action Reform Act notice.
The subcontractors claimed that “improvement” only referred to their specific work, which reached “substantial completion” when they finished, despite work to be done by other later, and the HOA’s notice to the contractor did not affect the subcontractors. The Colorado court agreed with the subcontractors.
Sandberg notes that some of the contractor’s were not addressed by the court, noting that “the court did not decide whether an improvement triggering the statute of repose can be determined on a trade-by-trade basis,” and that “the court did not decide whether substantial completion occurs when a certificate of occupancy is issued or when the architect certifies completion.”
Read the full story…