Architect Not Responsible for Injuries to Guests
September 1, 2011 — CDJ Staff
The Texas Court of Appeals has ruled, with one dissent, that the architectural firm that designed a home was not responsible to the injuries caused to guests when a balcony collapsed. Judge David Puryear wrote the majority opinion in Black + Vernooy Architects v. Smith.
Black + Vernooy designed a vacation home for Robert and Kathy Maxfield in 2000. The Maxfields hired a general contractor to build the home. The general contractor hired a subcontractor to build a balcony; however, the subcontractor did not follow the architect’s design in building the balcony.
A year after the house was completed; the Maxfields were visited by Lou Ann Smith and Karen Gravely. The balcony collapsed under the two women. Ms. Gravely suffered a broken finger, a crushed toe, and bruises. Ms. Smith was rendered a paraplegic as a result of the fall. They sued the Maxfields, the general contractor, and the architects for negligence. The Maxfields and the general contractor settled. A jury found that the architects held 10% of the responsibility. The architects appealed the judgment of the district court.
The Appeals Court reversed this judgment, noting that “there has been no allegation that the Architects negligently designed the balcony or that the Architects actually created the defects at issue.” Further, “the Smiths allege that the defect was caused by the construction practices of the contractor and subcontractor when the balcony was not built in accordance with the design plans of the Architects.”
The court found that even though the architects had a duty “to endeavor to guard against defects and deficiencies in the construction of the home and to generally ascertain whether the home was being built in compliance with the construction plans,” this duty did not extend to third parties.
Read the court’s decision…
Ensuing Loss Provision Does Not Salvage Coverage
December 9, 2011 — Tred R. Eyerly, Insurance Law Hawaii
Water intrusion caused by a construction defect was not covered under the all risk policy’s ensuing loss provision. See Friedberg v. Chubb & Son, Inc., 2011 U.S. Dist. LEXIS 123582 (D. Minn. Oct. 25, 2011).
Extensive water damage was discovered in the insureds’ home when a small hole in the exterior wall was being repaired. Chubb’s adjuster and an expert found water intrusion causing rot, mold, and damage to the home’s wood framing and insulation. Chubb denied coverage because water intruded through the roof and wall, resulting in gradual deterioration. The insureds filed suit.
The policy excluded coverage for construction defects, but insured "ensuing covered loss unless another exclusion applies."
The court agreed there was a prima facie case for coverage because the home suffered a physical loss.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Ohio Casualty’s and Beazer’s Motions were Granted in Part, and Denied in Part
May 10, 2012 — CDJ Staff
The case Trinity Homes LLC and Beazer Homes Investments LLC has reached the summary judgment stage. The remaining plaintiffs are Trinity Homes LLC (Trinity) and Beazer Homes Investments LLC (Beazer), and the only defendant remaining is Ohio Casualty Insurance Company (Ohio Casualty). “Ohio Casualty has filed a motion for summary judgment (Dkt. #409) on all claims against it, and Trinity and Beazer have filed a cross-motion seeking partial summary judgment (Dkt. #431) in their favor.” Ohio Casualty’s Motion for Summary Judgment was granted in part and denied in part, and Beazer’s motion was granted in part and denied in part.
The court’s ruling presented a bit of background on the companies involved in the litigation: “Trinity is an Indiana limited liability company with its principal place of business in Indiana and is one of several construction related companies owned by Beazer, which is a limited liability company incorporated under the laws of Delaware having its principal place of business in Atlanta, Georgia. Beazer’s predecessor, Beazer Homes Investment Corporation, acquired the stock of Crossman Communities, Inc. in 2002. Crossman and its subsidiary owned all interests in Trinity. Beazer and Trinity are in the business of residential real estate development and construction.”
Furthermore, “Ohio Casualty’s home office is in Ohio, where it is incorporated. It sells insurance policies to commercial entities such as Plaintiffs. It purchased a book of business from Great American Insurance Company, a subsidiary of which had sold commercial general liability policies (‘CGL’) and umbrella liability policies to Trinity, covering the period of time between May 1, 1994 through May 1, 1999. For ease of reference, we will refer to these policies as the Ohio Casualty policies. Trinity sold and acted as a general contractor for the construction of new homes in Central Indiana throughout the period of time in which the Ohio Casualty policies were in place.”
The court disagreed with almost every argument put forth by Ohio Casualty. However, they did concede “that Ohio Casualty is obligated to indemnify Trinity only for damages arising during its policy periods for pro rata liability as opposed to several and indivisible, by reason of its having limited its indemnity obligation to ‘those sums’ that Trinity becomes liable to pay for property damage which ‘occurs during the policy period.’”
Finally, the court ruled that “Ohio Casualty Company’s Motion For Summary Judgment (Dkt. #409) is GRANTED IN PART, that is, to the extent that Beazer is not an insured under the Ohio Casualty insurance policies, but the motion is DENIED in all other respects.”
The court further ruled that “Trinity and Beazer’s Motion For Partial Summary Judgment (Dkt. #431) is GRANTED IN PART, that is: (1) Trinity is an insured under the Ohio Casualty CGL and umbrella policies in effect for the time period from May 1, 1994 to May 1, 1999; (2) the claims at issue in the Underlying Lawsuits are "property damage" claims resulting from an "occurrence" and are therefore within the policy coverage provided under the Ohio Casualty Policy; and (3) none of the exclusions in the Ohio Casualty Policy bars coverage. Trinity and Beazer’s Motion is DENIED in all other respects. Moreover, material questions of fact remain with respect to whether payments made to the 54 homeowners, who were part of the putative class in the underlying Colon class action but were not included in the certified settlement class, were voluntary payments and as such do not qualify for indemnification. Material questions of fact also preclude a summary ruling on the issue of whether Ohio Casualty is estopped from raising their voluntary nature as a defense to indemnity.”
Read the court’s decision…
Conspirators Bilked Homeowners in Nevada Construction Defect Claims
March 28, 2012 — CDJ Staff
Courthouse News has a summary of the current lawsuit over a Nevada conspiracy to defraud homeowners by taking control of homeowner boards and then providing inadequate repairs. Homeowners in eight Las Vegas area communities are involved in the suit, which claims that the conspirators purchased units in the communities and then transferred fractional interests to others to allow them to run for HOA board elections. The suit claims that David Amesbury and his firm helped manipulate the elections.
Once homeowner boards were controlled by the conspirators, Nancy Quon, the construction defect attorney whose recent death appears to be by suicide, handled the litigation against homebuilders. She would settle out of court, engaging Silver Lining Construction to “do very minor and superficial repairs” to the homes. The remainder of the money was split by the conspirators. The suit also notes that the construction defect claims were “frivolous,” and?in addition to the negative publicity?caused the homes to lose at least 5% of their value.
Read the full story…
Faulty Workmanship Causing Damage to Other Property Covered as Construction Defect
September 30, 2011 — Tred Eyerley, Insurance Law Hawaii
In yet another recent construction defect case, the Illinois Court of Appeal found for coverage. See Milwaukee Mut. Ins. Co. v. J.P. Larsen, Inc., 2011 Ill. App. Ct. LEXIS 872 (Ill. Ct. App. Aug. 15, 2011).
Weather-Tite, Inc. hired Larson as a subcontractor to apply sealant to windows installed by Weather-Tite in a condominium building. The windows subsequently leaked and caused water damage. The homeowner’s association sued Weather-Tite for breach of express and implied warranties. Weather-Tite filed a third-party complaint against Larsen alleging that, if it was liable to the association for breach of warranty, Larsen was liable for contribution as a joint tortfeasor. Weather-Tite and Larsen both tendered defenses to Milwaukee Insurance. The tenders were denied and Milwaukee Insurance filed suit to determine rights under the policy.
Cross-motions for summary judgment were filed by all parties. The trial court granted Milwaukee Insurance’s summary judgment motion as to Weather-Tite, but granted Larsen’s cross-motion against Milwaukee Insurance.
On appeal, the appellate court considered whether the underlying pleadings alleged facts demonstrating "property damage" resulting from an "occurrence" within the terms of the policy.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Florida Contractor on Trial for Bribing School Official
October 28, 2011 — CDJ Staff
Lloyd Whann, an executive in M. M. Parrish Construction, a Gainesville, Florida firm, is going to trial over claims that he bribed a school district official with more than $50,000 in gifts. The trial has been pushed to March of 2012, in order for his defense to review documents.
Bob Williams, the former school official, plead guilty to conspiracy to commit bribery. He agreed to testify against Whann and M.M. Parrish Construction.
Read the full story...
Ohio “property damage” caused by an “occurrence.”
May 18, 2011 — May 18, 2011 - CDCoverage.com
In JTO, Inc. v. State Automobile Mut. Ins. Co., No. 2010-L-062 (Ohio Ct. App. March 25, 2011), general contractor JTO was sued by hotel project owner Marriott for breach of contract and warranties seeking damages for the repair of construction defects resulting in moisture penetration property damage to interior components. JTO filed a third party complaint against subcontractor Farizel and also tendered its defense as an additional insured under Farizel’s State Auto CGL policy.
Read the full story…
Reprinted courtesy of CDCoverage.com
Census Bureau, HUD Show Declines in Residential Construction
May 17, 2011 – CDJ Staff
The U.S. Census Bureau and the Department of Housing and Urban Development released their summary of residential construction for April 2011 on May 17.
Building permits for privately owned housing units were down 4% from last month and 12% from last year. Similarly, privately-owned housing starts were down 10% from March and 23% below the previous year.
For further details, read the Census Bureau/HUD report
Destruction of Construction Defect Evidence Leads to Sanctions against Plaintiff
July 10, 2012 — CDJ Staff
Stating that the plaintiff’s actions have left the defendants in a situation where they “cannot properly defend the action,” a judge in the US District Court of New York has sanctioned the plaintiffs in Aktas v. JMC Dev. Co.
The plaintiffs hired JMC Development and Stephen Jung, an architect, to renovate their vacation home in Adirnodack, New York. As work progressed, “due to disagreements regarding the completion date and payments for the project, the relationship began to deteriorate.” The plaintiffs hired George Villar as an owner’s representative who “testified that he deemed the workmanship to be ‘poor.’”
Subsequently, the locks where changed on the home, preventing JMC from performing any additional work, after which drywall was removed, which Villar stated was so that “the engineer come and look at the framing.” Subsequently, Villar sent a letter to JMC stating that the work was “performed in an inadequate, negligent and un-professional manner.” Villar informed JMC that they were not to visit the property. Subsequently, the plaintiffs hired another firm. “Plaintiffs testified that the materials were ‘carted away’ and ‘thrown out.’”
The plaintiffs filed a suit against JMC and others. JMC filed a motion requesting that the plaintiffs be sanctioned for their spoliation of evidence. The court noted that “the plaintiffs recognized that litigation was imminent,” and that they “had a duty to preserve the evidence. As all of JMC’s work was destroyed, there is no evidence of whether or not the work was defective. The court concluded that it will “issue an adverse inference charge that permits the jury to infer that the missing evidence was favorable to the defendants.”
In conclusion, the court granted in part the spoliation sanctions. They granted JMC a summary judgment dismissing the plaintiffs’ claims of fraud.
Read the court’s decision…
Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 — CDJ Staff
The Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Official Tried to Influence Judge against Shortchanged Subcontractor
February 10, 2012 — CDJ Staff
A contractor testified in the trial of former Cuyahoga County Commissioner Jimmy Dimora. According to Fox 8 in Cleveland, Ohio, Sean Newman, the president of Letter Perfect testified that his company was a subcontractor on the reconstruction of the locker rooms at the Cleveland Browns Stadium. Newman said his company was paid only $400,000 of their $650,000 bid. When Letter Perfect sued the contractor, D.A.S. Construction, Dimora called the judge to influence her to rule in favor of D.A.S.
The judge in the earlier case, Bridgett McCafferty, has been found guilty of lying to the FBI during their investigation and is serving a 14-month prison sentence.
Read the full story…
Construction Bright Spot in Indianapolis
March 1, 2012 — CDJ Staff
The downtown Indianapolis area is the site of about 85 major building projects that are from groundbreaking to just complete. The Indianapolis Star reports that the cumulative worth of the projects is about $3 billion, a level of construction that Indianapolis has seen only once before.
About thirty of the projects are residential. The main commercial project is a $754 million hospital building. The boom in downtown Indianapolis is not matched elsewhere, with the Indianapolis Star reporting that in the rest of Central Indiana, construction has slowed.
Read the full story…
Fire Reveals Defects, Appeals Court Affirms Judgment against Builder
July 10, 2012 — CDJ Staff
The Arizona Court of Appeals has ruled in the case of Simms v. Nance Construction. After a fire damaged his home, Jerry Simms discovered some construction defects in the work of the builder, Nance Construction. Nance Construction completed the home in 2000 and it was damaged by fire in 2001. In the course of Simms’ suit against his neighbor, “defense experts opined both that Dusty Creek had negligently repaired the damage to Simms’ residence and that many defects found in the houses were the result of defects in the original construction.” Nance offered to make roof repairs. Simms responded with a list of “numerous construction defects,” stating this was “not a comprehensive and final list of items.” Nance offered to repair some while disputing others. Simms entered a lawsuit against Nance and other parties.
Nance first sought a summary judgment, “asserting that Simms had failed to adequately disclose the repairs for which he sought to hold Nance responsible.” The court denied this. It also would not allow Nance to introduce evidence that Simms had been denied a license by the Arizona Department of Gaming over “questionable business practices, illegal activities, and financial transactions with a person purportedly involved in organized crime.”
During the suit, Simms contracted with Advanced Repair Technologies “for repairs that included a complete remodel of the roof and the exterior stucco system.” Nance later claimed that the cost of ART’s repair was unreasonable, claiming that it should have cost about $600,000 instead of the $1.5 million for which Simms contracted. The jury found against Nance, with a judgment of $870,200 of which half was due to the roofing subcontractor.
After the verdict, Nash moved for a new trial, stating that the jury should have heard expert testimony on whether the contract price was reasonable. Nance also “argued that the trial court had erred in refusing to allow Nance to impeach Simms’ credibility with his purported prior acts of dishonesty.” These motions were denied and Nance appealed.
The appeals court upheld the trial court on all counts. The court found that, despite the contention made by Nance, the jury had sufficient information to determine if the cost of the repairs were reasonable. The court also found that Simms had given Nance an opportunity to propose repairs. The law, however, “does not require the Plaintiff to accept an offer for repairs,” adding that “the record makes clear that the parties were far apart in their belief of the nature of repairs necessary.” Nor did the court find that Nance should have been allowed to introduce evidence to impeach Simms’ credibility.
Although judgment of the lower court was affirmed, the court took the discretion to decline to award attorneys’ fees to Simms, although he was awarded costs.
Read the court’s decision…
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 — Douglas Reiser, Builders Cousel
Ever had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
CC&Rs Not the Place for Arbitration Agreement, Court Rules
May 24, 2011 — CDJ Staff
In January, the California Court of Appeals ruled that an arbitration clause inserted in a development’s CC&Rs by the developer could not be enforced. The case, Villa Vicenza Homeowners Association v. Noble Court Development, involved a case in which, according to the opinion, “following the first sale Nobel controlled the board of directors of the Association and because the initial condominium buyers noticed defects in common areas and common facilities and did not believe Nobel had provided a reserve fund sufficient to repair the defects, the condominium owners brought a derivative action on behalf of the Association against Nobel.”
The court concluded, “The use of CC&R's as a means of providing contractual rights to parties with no interest in or responsibility for a common interest development is also problematic from the standpoint of determining what if any consideration would support such third-party agreements. By their terms the CC&R's bind all successors, even those with whom a third party such as Nobel has never had any contractual relationship and to whom Nobel has not provided any consideration.” The court determined that “the trial court did not err in denying Nobel's motion to compel arbitration.”
Read the court’s decision