Supreme Court of Oregon Affirms Decision in Abraham v. T. Henry Construction, et al.
April 20, 2011 — April 20, 2011 Beverley BevenFlorez - Construction Defect Journal
After reviewing the decision in Abraham v. T. Henry Construction, et al., the Oregon Supreme Court affirmed that a tort claim for property damage arising from construction defects may exist even when the homeowner and the builder are in a contractual relationship.
When the case was initially filed, the plaintiffs alleged breach of contract and negligence. The defendants moved for summary judgment arguing that one, the claim was barred by the six-year statute of limitations and two, no special relationship (such as one between a doctor and patient) existed. The court agreed with the defendants. However, the Court of Appeals while affirming the trial court’s decision on breach of contract reversed the decision on negligence. The Court of Appeals stated that an administrative or statute rule could establish a standard of care independent from the contract.
The Oregon Supreme Court gave an example of cases where a tort claim could exist when a contract is present: “If an individual and a contractor enter into a contract to build a house, which provides that the contractor will install only copper pipe, but the contractor installs PVC pipe instead (assuming both kinds of pipe comply with the building code and the use of either would be consistent with the standard of care expected of contractors), that failure would be a breach of contract only. […] If the failure to install the copper pipe caused a reduction in the value of the house, the plaintiff would be able to recover that amount in an action for breach of contract. […] On the other hand, if the contractor installed the PVC pipe in a defective manner and those pipes therefore leaked, causing property damage to the house, the homeowner would have claims in both contract and tort. […] In those circumstances, the obligation to install copper instead of PVC pipe is purely contractual; the manner of installing the pipe, however, implicates both contract and tort because of the foreseeable risk of property damage that can result from improperly installed pipes.”
Read the court’s decision…
Construction Defects Lead to Demolition
May 26, 2011 — CDJ Staff
Ten years after it was built, demolition of Seattle’s McGuire Building has begun, as Jeanne Lang Jones reports in the Puget Sound Business Journal. Construction defects had rendered the 25-story apartment building uninhabitable. The major problem was corroded steel cabling. According to the report, “the building’s owners reached an undisclosed settlement last year with St. Louis-based contractor McCarthy Building Companies.”
Read the full story…
Are Construction Defects Covered by Your General Liability Policy?
July 10, 2012 — CDJ Staff
Construction firms are finding that their insurers are denying construction defect claims and the courts are siding with the insurers, according to Kelly M. Gindele, writing in the Martindale-Hubble Legal Library. Ms. Gindele notes that when construction defect claims are not covered, firms can end up with “multi-million dollar claims” that it has to pay “out of its own pocket.” She notes that in Kentucky and Ohio, if “the insured’s work causes an unforeseen and unintended event to occur?Ķthere is not occurrence under the policy.” Further, if there is an occurrence, the court will “look for an exception to coverage.”
She also notes that contractors may not hold sufficient coverage, either by limiting the amounts or the time. She notes that while “insurers generally try to limit coverage for defect claims to one year,” that “construction defects may not be found in a year’s time.”
Ms. Ginele recommends that contractors “hire an insurance company with extensive experience in this field” and “independent legal counsel with insurance knowledge,” to avoid finding themselves “with limited or even no coverage when it needs it most.”
Read the full story…
Time to Repair Nevada’s Construction Defect Laws?
February 10, 2012 — CDJ Staff
The Builders Magazine writes that during the previous session of the Nevada legislature, reforms sought by the building industry were stopped by the Speaker of the Nevada Assembly. The new session brings a new speaker and new hope for construction defect reform in Nevada.
Pat Hickey, a member of the Assembly and a small business owner told The Builders Magazine that “we need to apply pressure on the legislators to fix the law.” He also recommended that people “go to Governor Sandoval and ask for his help.” Builders seeks legislation that will include right to repair and it should “define construction defect in such a way that it allows for a fair process.”
Read the full story…
Judge Kobayashi Determines No Coverage for Construction Defect Claim
October 23, 2012 — Tred Eyerly, Insurance Law Hawaii
Judge Kobayashi of the U.S. District Court, District of Hawaii, largely followed earlier precedent established by Judge Mollway in finding no coverage for construction defect claims. See Evanston v. Nagano, 2012 WL 3800320 (D. Hawaii Aug. 31, 2012).
Evanston issued several liability policies to the insured contractor from 2002 and 2011. The insured entered a contract to build a residence in Honolulu. The homeowners were not happy with their home after the work was completed. They filed suit, alleging that the project was delayed and the construction was "riddled with defects." The complaint included claims for breach of contract and breach of warranties. Negligence was not alleged. Evanston defended, but under a reservation of rights.
Evanston filed suit for a declaratory judgment and moved for summary judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Ambitious Building Plans in Boston
November 18, 2011 — CDJ Staff
Although most are unlikely to change the Boston skyline, there are several large projects on the drawing boards. The site BostInnovation covered ten of them in a recent post. Downtown Boston will be the site of several of these large projects, including three towers to be added to the Christian Science Plaza, a 404-unit residential tower in the Theater District, and perhaps the largest of these projects, a 47-story tower to be built over Copley Plaza, which will tower over the adjacent buildings. None of the planned buildings will challenge the Hancock Tower’s 60 stories.
Read the full story…
Restitution Unlikely in Las Vegas Construction Defect Scam
October 23, 2012 — CDJ Staff
The San Francisco Chronicle reports that the money lost in the Las Vegas HOA fraud cause is probably not recoverable. Victims of the scam have asked the court for restitution, but Judge Lloyd George doubts any of the money will be found, saying “the money is not available, it would appear.”
One Vistana board members not part of the conspiracy told reporters that the $8 million construction defect settlement never went for needed repairs. “Within six months that money was gone,” said Bruce Wallace, a retired Air Force colonel. After the construction defect account was depleted to $450,000, two board members disappeared with the funds.
Read the full story…
Construction Defects Lead to Demolition of Seattle’s 25-story McGuire Apartments Building
March 16, 2011 — March 16, 2011 Construction Defect Journal Staff
According to a story published last Thursday in Seattle PI: " The 25-story McGuire Apartments, at Second Avenue and Wall Street, would cost more to fix than the building is worth, according to its owners. Its most serious defect involves steel cables that are corroding inside of concrete slabs because the ends weren’t properly treated with a rust-proof coating and a pocket in the edge of the concrete that wasn’t properly sealed"
The report by Aubrey Cohen outlines the demolition plans which are expected to take between 12 and 18 months, and will utilize robotic Brokk Machines. The demolition plan calls for one story at a time to be demolished, with the debris to be trucked offsite. Demolition plans aim to minimize disruption to residents and businesses in the area by Limiting work 7 a.m. to 6 p.m. on weekdays and 9 a.m. to 6 p.m. Saturdays with "impact and percussive activities" limited to 8 a.m to 5 p.m weekdays.
Read More...
Lockton Expands Construction and Design Team
July 19, 2011 — CDJ Staff
Lockton Companies, LLC, the largest privately held independent insurance broker, has announced that it is expanding its construction and design team with the hiring of Karen Erger and Tom Miller.
Ms. Erger will provide professional liability practice management, loss prevention, contract and complex claims management consulting services to Lockton's architectural, engineering and construction clients in her role as Vice President, Director of Practice Management. Her background includes construction litigation at a leading construction law firm, professional liability claims defense and claims consulting for major professional liability underwriters.
Miller joins Lockton as a Senior Vice President within the Design and Construction Unit. His role will be dedicated to serving the needs of engineering, architecture and construction firms performing services around the globe. He has spent more than 15 years concentrating on professional liability for design professionals and contractors in multiple roles. He previously managed the professional liability underwriting of one of the largest construction insurers and has developed numerous manuscript insurance products as well as focused on strategic planning to enhance business unit opportunities.
Read the full story…
Hilton Grand Vacations Defect Trial Delayed
October 23, 2012 — CDJ Staff
A settlement agreement between Conti Electric and Westgate Resorts has lead to a delay in starting the trial over construction defect claims and billing disputes over Hilton Grand Vacations a time share tower in Las Vegas. According to the Las Vegas Review-Journal, the dispute includes claims of $23.3 million owed to the general contractor against which the developer has placed $30 million in construction defect claims.
Read the full story…
Construction Firm Sues City and Engineers over Reservoir Project
October 28, 2011 — CDJ Staff
The city of Fremont, Ohio and Arcadis have been sued by Trucco Construction. Trucco had been hired by the city to build a reservoir designed by Arcadis, the News-Messenger reports. Peter Welin, attorney for Trucco, said that he found “startling evidence of the company’s negligence” when he deposed Arcadis engineers. “This project could never be built the way they bid it.”
Their suit alleges that Arcadis and the city were aware that the site was not conducive to construction and also that Arcadis failed to be a neutral party in discussions between Trucco and the city regarding compensation.
Sam Wamper, an attorney for Fremont, said he was going to file a motion which would include “quite an interesting story,” but declined to elaborate.
Read the full story...
Construction Defect Journal Marks First Anniversary
January 6, 2012 — CDJ Staff
November 2011 marked the first anniversary of the Construction Defect Journal. During the first year our staff and contributors in the insurance and legal communities have compiled several hundred articles of interest to the construction defect and claims community.
Each of these articles are maintained in the CDJ archives, and are accessible at http://www.constructiondefectjournal.com/archives.html. Each story in the archives is listed in the order it was posted to the archives. Each story in the archives opens up in its own page, so you can easily locate topics and articles of interest.
If you’re new to Construction Defect Journal, or just want peruse past articles, please take a moment to visit the CDJ Archives page. Also please feel encouraged to submit your firm’s articles or legal publications of interest to the CD community at http://www.constructiondefectjournal.com/submitStory.html.
Construction Upturn in Silicon Valley
August 17, 2011 — CDJ Staff
Work resumed after nearly three years on an office tower in Santa Clara, according to the San Jose Mercury News. Work had stalled on the building due to the economy, but now the developer is planning a second five-story building on the site. Other dormant projects in the area are also getting restarted. Santa Clara County saw the addition of 1,800 construction jobs in June.
A spokesperson for the Operating Engineers Local 3 in Alameda told the paper, “two years ago we had five thousand folks on the out-of-work list. It’s now down to about 1,700.”
Read the full story…
Texas contractual liability exclusion
May 18, 2011 — May 18, 2011 - CDCoverage.com
In Ewing Construction Co., Inc. v. Amerisure Ins. Co., No. C-10-256 (S.D. Tex. April 28, 2011), insured Ewing was the general contractor for an athletic facility constructed for a school district. The school district sued Ewing alleging defective construction of the project. The underlying complaint included contract and negligence causes of action, and sought damages for the repair of the damages and loss of the use of the project. The complaint did not allege damage to any property other than the project itself. Ewing tendered its defense to its CGL insurer Amerisure. Amerisure denied a defense and Ewing filed suit against Amerisure. The federal district trial court entered summary judgment for Amerisure. Applying Texas law, the court held that all of the damages fell within the “contractual liability†exclusion precluding any duty to defend or indemnify.
Read the full story…
Reprinted courtesy of CDCoverage.com
Florida Appeals Court Rules in Favor of Homeowners Unaware of Construction Defects and Lack of Permits
December 9, 2011 — CDJ Staff
The Florida Court of Appeals has ruled that a homeowner is not liable for defects in unpermitted alterations, reversing a lower court’s decision in Jensen v. Bailey. The Jensens sold their house to the Baileys. During the sale, the Jensens filled out a property disclosure statement, checking “no” to a question about “any improvement or additions to the property, whether by your or by others that have been constructed in violation of building codes or without necessary permits.”
After moving in, the Baileys discovered several problems with the home. One involved a defective sewer connection leading to repeated backups. The Baileys also found problems with remodeling the Jensens had done in the kitchen, master bath, and bedroom. The remodeling work was not done with required permits nor was it up to code.
The court noted that an earlier case, Johnson v. Davis, established four criteria: “the seller of a home must have knowledge of a defect in the property; the defect must materially affect the value of the property; the defect must not be readily observable and must be unknown to the buyer; and the buyer must establish that the seller failed to disclose the defect to the buyer.” The court found that the first of these criteria was crucial to determining the case.
In the Johnson ruling, the then Chief Justice dissented, fearing that the courts “would ultimately construe Johnson’s requirement of actual knowledge to permit a finding of liability based on constructive knowledge,” quoting Justice Boyd, “a rule of constructive knowledge will develop based on the reasoning that if the seller did not know of the defect, he should have known about it before attempting to sell the property.” The Appeals Court concluded that the lower court hit this point in ruling on Jensen v. Bailey.
Citing other Florida cases, the court noted that the Johnson rule does require “proof of the seller’s actual knowledge of the defect.” The court cited a case in which it was concluded that the seller “should have known” that there was circumstantial evidence was that the seller did know about the defects, as the seller had been involved in the construction of the home.
In the case of the Jensens, the lower court concluded that they did not know that the work was defective, nor did they know that they were obligated to obtain permits for it. The Appeals Court found this one fact sufficient to reverse the decision and remand the case to the lower court for a final judgment in favor of the Jensens.
Read the court’s decision…
Ensuing Loss Provision Does Not Salvage Coverage
August 2, 2012 — Tred Eyerly, Insurance Law Hawaii
The Minnesota Court of Appeals affirmed the trial court's decision finding no coverage due to exclusions from the all-risk policy for losses related to mold, rot and condensation. Koskovich v. Am Family Mut. Ins. Co., 2012 Minn. App. Unpub. LEXIS 581 (Minn. Ct. App. June 25, 2012).
In 1978, the insureds purchased a home that was built in 1904. From 1991 to 1995, they remodeled, which included rotating the house 45 degrees, removing a wing and adding a new section. Polypropylene vapor barriers were installed, with pinholes for ventilation.
In 2008, water was observed on an interior floor. An investigation revealed that the sheathing under the siding and the house's framing were wet and rotten, requiring removal and replacement of the siding and studs. Repairs were made and a claim was submitted to American Family Mutual Insurance Company.
American's structural engineer inspected and determined that moisture was likely caused by condensation of water vapor where the vapor barrier was held tight to the sheathing and by inward water migration from wet siding during rainy periods through the vapor-barrier perforations. The structural engineer opined that, although the home's framing was deteriorated and structurally compromised, it did not appear as though the home was in imminent danger of collapse.
American denied coverage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Michigan Supreme Court Concludes No Statute of Repose on Breach of Contract
July 19, 2011 — CDJ Staff
Judge Marilyn Kelly of the Michigan Supreme Court has remanded the case of Miller-Davis Co. v. Ahrens Constr. Inc. (Mich., 2011) to the Court of Appeals, after determining that the court had improperly applied the statute of repose. She reversed their judgment, pending a new trial.
Ahrens Construction was a subcontractor, hired by Miller-Davis to build and install a natatorium room at a YMCA camp in Kalamazoo, Michigan. After its installation, the YMCA discovered a severe condensation problem, causing moisture to “rain” from the roof. The architect, testifying for Miller-Davis, alleged that the problems were due to improper installation by Ahrens. Ahrens claimed that the condensation problem was due to a design error.
When the roof was removed and reconstructed, the moisture problem ended. Ahrens argued that the alleged defects were caused by the removal. Further, in trial Ahrens raised the issue of the statute of repose. The court found in favor of Miller-Davis and did not address the statute of repose.
The Court of Appeals reversed the trial court, determining that the statute of repose had barred the suit. This rendered the other issues moot.
The Michigan Supreme concluded that the issue at hand was “a suit for breach of contract,” and that the Michigan statute of repose is limited to tort actions. They remanded the case to the Court of Appeals to address the issues that had been mooted by the application of the statute of repose.
Read the court’s decision…
Court Rules on a Long List of Motions in Illinois National Insurance Co v Nordic PCL
May 10, 2012 — CDJ Staff
The case Illinois National Insurance Co. v Nordic PCL, et al. “involves a dispute about whether insurance benefits are available to a general contractor who built structures that allegedly have construction defects. Plaintiffs Illinois National Insurance Company (‘Illinois National’) and National Union Fire Insurance Company of Pittsburgh, PA (‘National Union’) (collectively, the ‘Insurers’), commenced this action for declaratory relief against Defendant Nordic PCL Construction, Inc., f/k/a Nordic Construction, Ltd. ("Nordic"), on August 23, 2011.”
The court was asked to rule on a long list of motions: “Counterclaim Defendants’ Request for Judicial Notice in Support of Their (1) Motion to Dismiss the Counterclaim and (2) Motion to Strike Portions of the Counterclaim, ECF No. 16 (‘Request for Judicial Notice’); Counterclaim Defendants’ Motion to Dismiss Counterclaim Filed October 24, 2011, ECF No. 14 (‘Motion to Dismiss Counterclaim’); Counterclaim Defendants’ Motion to Strike Portions of the Counterclaim Filed October 24, 2011, ECF No. 15 (‘Motion to Strike’); Third-Party Defendant Marsh USA, Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 33 (‘Marsh’s Motion To Dismiss Or Stay’); Defendant and Third-Party Plaintiff Nordic PCL Construction, Inc., f/k/a Nordic Construction Ltd.’s Substantive Joinder to Third-Party Defendant Marsh USA Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 36 (‘Nordic’s Joinder’); and Third-Party Defendant Marsh USA, Inc.’s Motion for Judgment on the Pleadings on Counts V and VI of Defendant/Third-Party Plaintiff Nordic PCL Construction, Inc.’s Third-Party Complaint, ECF No. 29 (‘Marsh’s Motion for Judgment on the Pleadings’).”
In result, the court reached the following decisions: “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice to the extent it covers matters relevant to these motions; GRANTS IN PART the Insurers’ Motion to Dismiss Counterclaim, but gives Nordic leave to amend the Counterclaim in certain respects; DENIES the Insurers’ Motion to Strike; DENIES Marsh’s Motion To Dismiss Or Stay and Nordic’s Joinder; and GRANTS Marsh’s Motion for Judgment on the Pleadings.”
The court provides a bit of background on the case: “This action arises out of alleged construction defects involving two projects on which Nordic acted as the general contractor. Nordic is a defendant in a pending state court action with respect to one of the projects and says it spent more than $400,000 on repairs with respect to the other project. Nordic tendered the defense of the pending state court action to the Insurers and sought reimbursement of the cost of repairs already performed. The Insurers responded by filing this action to determine their rights under the insurance policies issued to Nordic.”
Furthermore, the court presented a brief procedural history: “The Insurers commenced this declaratory action in this court on August 23, 2011. The Complaint asserts two claims, one seeking a declaration that the Insurers have no duty to provide a defense or indemnification regarding the Safeway Action, the other seeking such a declaration regarding the Moanalua Claims. Along with its Answer, Nordic filed a Counterclaim against the Insurers. The Counterclaim asserts breach of contract, breach of the covenant of good faith and fair dealing, misrepresentations and omissions of material fact, and bad faith, and seeks declaratory relief against the Insurers.”
The procedural history continues: “Nordic also filed a Third-Party Complaint against Marsh, the broker that had procured the Policies from the Insurers for Nordic. Nordic alleges that it reasonably believed that the Policies would provide completed operations insurance coverage for the types of construction defects alleged in the Safeway Action and Moanalua Claims. The Third-Party Complaint asserts breach of contract, negligence, promissory estoppel, breach of fiduciary duties, implied indemnity, and contribution and equitable subrogation.”
In conclusion, “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice. With regard to the Insurers’ Motion to Dismiss Counterclaim, the court GRANTS the motion as to Count I (breach of contract), Count II (duty of good faith and fair dealing), Count III (fraudulent and negligent misrepresentation), the portion of Count IV (bad faith) premised on fraud, and Count IV (declaratory relief). The court DENIES the motion as to Count IV (bad faith) that is not premised on fraud. Except with respect to the "occurrence" issue, which the court disposes of here on the merits, and Count V, which concerns only a form of relief, Nordic is given leave to amend its Counterclaim within three weeks of the date of this order. The court DENIES the Insurers’ Motion to Strike, DENIES Marsh’s Motion to Dismiss or Stay and Nordic’s Joinder, and GRANTS Marsh’s Motion for Judgment on the Pleadings with respect to Counts V and VI of the Third-Party Complaint.”
Read the court’s decision…