Lawsuit over Construction Defects Not a Federal Case
August 16, 2012 — CDJ Staff
The United State District Court in California has dismissed the claims of a contractor against the United States government, on the grounds that it was not within the subject matter jurisdiction of the court. The origins of the case are in a related construction defect claim. The current plaintiff, Performance Contracting, Inc., did the lath and plaster work for a building for the Department of Veterans Affairs. After the building was completed, the Veterans Affairs complained to the general contractor, Wynema, Inc., of water intrusion problems.
Wyema and Performance conducted testing and the water intrusion was found to be due to “a variety of design defects and omissions, including: 1) omission of proper window flashing; 2) inadequate waterproof membrane around the windows; 3) inadequate T-molding around the windows; 4) lack of a window sill pan for the windows; 5) lack of any backing in the window framing; 6) lack of any backing for the stucco expansion joints and seams; and 7) failure to require that a performance mock-up of the window assembly and adjacent areas be built and water tested.” Wyema filed a construction defect action against Performance and other subcontractors.
In the current case, Performance claims that Veteran Affairs was negligent, that it “breached its duty to Plaintiff when it provided deficient plants and specifications” and “failed to properly oversee construction and inspect Project work.” The court determined that it could not hear this case, noting that “Federal Courts are presumptively without jurisdiction over civil actions.”
Performance raised its claims under the Federal Tort Claims Act. The judge was not persuaded by this claim, noting that the FTCA does not apply to purported breach of the General Contract. The FTCA waives the government’s sovereign immunity in cases of “injury or loss of property, or personal injury or death caused by the negligent or wrongful act or omission of an employee of the Government while acting within the scope of his office or employment, under circumstances where the United States, if a private person, would be liable to the claimant in accordance with the law of the place where the act or omission occurred.”
Performance was unable to pursue its claims in the Court of Federal Claims as there was no contract between Performance and the government. However, the court noted that Performance’s inability to file suit in the Court of Federal Claims does not open up a path to the District Court. “Litigants are not guaranteed a forum in which to sue the United States.” The court further noted that “if this Court were to accept Plaintiff’s logic, non-parties to contracts, but not parties, would be free to pursue contract claims in the fora of their choosing.”
Read the court’s decision…
California insured’s duty to cooperate and insurer’s right to select defense counsel
April 14, 2011 — April 14, 2011 - CDCoverage.com
In Travelers Property Casualty Co. v. Centex Homes, No. C 10-02757 (N.D. Cal. April 1, 2011), general contractor Centex was sued by homeowners for construction defects. Centex tendered its defense to Travelers as an additional insured under policies issued by Travelers to two Centex subcontractors. Travelers agreed to defend Centex under a reservation of rights and selected defense counsel to defend Centex. Centex refused to accept the defense, asserting that it was entitled to select defense counsel. Travelers filed suit against Centex seeking a declaratory judgment that Centex had breached the duty to cooperate condition in the Travelers’ policy.
Read the full story...
Reprinted courtesy of CDCoverage.com
Nevada Bill Aims to Reduce Legal Fees For Construction Defect Practitioners
March 21, 2011 — March 21, 2011 Construction Defect Journal Staff
Assemblyman Ira Hansen and twelve additional members of Nevada’s Assembly are sponsoring Assembly Bill 285. AB 285 Revises provisions governing an award of attorney’s fees in causes of action for constructional defects. Existing law generally provides that a claimant may recover reasonable attorney’s fees as part of the claimant’s damages in a cause of action for constructional defects. (NRS 40.655)
This bill removes this provision and instead authorizes a court to award reasonable attorney’s fees to a prevailing party involved in such a cause of action if an independent basis for the award exists pursuant to existing law which authorizes a court to award attorney’s fees in certain circumstances, or Rule 68 of the Nevada Rules of Civil Procedure, which provides for the payment of reasonable attorney’s fees by an offeree who rejects an offer and subsequently fails to obtain a more favorable judgment.
In an AP report published in Business Week it is suggested that the target objective of legislators centers on what it refers to as Nevada’s "Rampant construction defect lawsuits".
According to Business Week "The suits bring in hundreds of millions of dollars for lawyers and have put construction companies out of business. Hansen says fewer construction firms mean higher prices for Nevada consumers."
Click Here To Read Full Text and Revisions of Assembly Bill 285
Battle of “Other Insurance” Clauses
March 23, 2011 —
Tred R. Eyerly -
Insurance Law Hawaii - March 23, 2011
The New York Court of Appeals considered the impact of competing “other insurance” provisions located in both a CGL policy and a D&O policy. See Fieldston Property Owners Assoc., Inc. v. Hermitage Ins. Co., Inv., 2011 N.Y. LEXIS 254 (N.Y. Feb. 24, 2011).
In the underlying case, Fieldston’s officers were charged with making false statements and fraudulent claims with respect to a customer's right to access its property from adjacent streets. Suit was eventually filed against Fieldston and its officers, alleging several causes of action including injurious falsehood. Damages were sought.
Fieldston’s CGL policy was issued by Hermitage. The “other insurance” provision stated, “If other valid and collectible insurance is available to the insured for a loss we cover . . . our obligations are limited,” but also stated it would share with all other insurance as a primary policy.
Read the full story...Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
In Oregon Construction Defect Claims, “Contract Is (Still) King”
April 25, 2012 — CDJ Staff
Writing in Oregon’s Daily Journal of Commerce, David Anderson looks at the aftermath of the case Abraham v. T. Henry Construction, Inc. In that case, Anderson notes that “the homeowners hired a contractor to build their house, and subsequently discovered extensive water damage” “after expiration of the time to sue for breach of contract.” The homeowners claimed negligence. Oregon’s Supreme Court concluded that “homeowners only had to prove that the contractor negligently caused reasonably foreseeable harm to the homeowner’s property.”
Anderson views this decision as leading to two risks for contractors. “First, contractors can be held liable in tort for breaching building code standards; second, they can be held liable for violating the often-difficult-to-define ‘reasonable care’ standard.” But here, “contract can be king.” The Oregon Supreme Court noted that the contractor “could have avoided exposure to the general ‘reasonable care’ standard by more carefully defining its obligations in the original construction contract.”
He notes that contractors who fail to define their obligations or use generic definitions “may be exposing themselves to a more vague scope of liability.”
Read the full story…
Insurer’s Discovery Requests Ruled to be Overbroad in Construction Defect Suit
October 28, 2011 — CDJ Staff
The US District Court has ruled in the case of D.R. Horton Los Angeles Holding Co. Inc. v. American Safety Indemnity, Co. D.R. Horton was involved in a real estate development project. Its subcontractor, Ebensteiner Co., was insured by ASIC and named D.R. Horton as an additional insured and third-party beneficiary. D.R. Horton, in response to legal complaints and cross-complaints, filed for coverage from ASIC under the Ebensteiner policy. This was refused by ASIC. ASIC claimed that “there is no potential coverage for Ebensteiner as a Named Insurer and/or D.R. Horton as an Additional Insured.” They stated that “the requirements for coverage are not satisfied.”
The case same to trial with the deadline for discovery set at March 1, 2011. ASIC stated they were seeking the developer’s “job file” for the Canyon Gate project. D.R. Horton claimed that ASIC’s discovery request was overbroad and that it would be “unduly burdensome for it to produce all documents responsive to the overbroad requests.”
D.R. Horton did agree to produce several categories of documents, which included:
“(1) final building inspection sign-offs for the homes that are the subject of the underlying litigation;(2) an updated homeowner matrix for the underlying actions; (3) the concrete subcontractor files; (4) the daily field logs for D.R. Horton’s on-site employee during Ebensteiner’s work; (5) documents relating to concrete work, including documents for concrete suppliers; (6) documents relating to compacting testing; (7) documents relating to grading; and (8) D.R. Horton’s request for proposal for grading”
The court found that the requests from ASIC were overbroad, noting that the language of the ASIC Request for Production of Documents (RFP) 3-5 would include “subcontractor files for plumbing, electric, flooring, etc. - none of these being at issue in the case.” The court denied the ASIC’s motion to compel further documents.
The court also found fault with ASIC’s RFPs 6 and 7. Here, D.R. Horton claimed the language was written so broadly it would require the production of sales information and, again, subcontractors not relevant to the case.
Further, the court found that RFPs 8, 10, 11, and 13 were also overbroad. RFP 8 covered all subcontractors. D.R. Horton replied that they had earlier complied with the documents covered in RFPs 10 and 11. The court concurred. RFP 13 was denied as it went beyond the scope of admissible evidence, even including attorney-client communication.
The court denied all of ASIC’s attempts to compel further discovery.
Read the court’s decision…
Local Government Waives Construction Fees to Spur Jobs
June 19, 2012 — CDJ Staff
Warren Township in New Jersey has waived building and electrical permit fees, up to $5,000, for businesses that create at least five new jobs. The fee reductions are available for construction in areas zones under various designations. Buildings that have received a zoning variance are not eligible. The Echoes-Sentinel notes that other towns in Somerset County, New Jersey have adopted similar ordinances.
Read the full story…
Arbitrator May Use Own Discretion in Consolidating Construction Defect Cases
September 1, 2011 — CJD Staff
The Mississippi Court of Appeals has ruled in the case of Harry Baker Smith Architects II, PLLC v. Sea Breeze I, LLC. Sea Breeze contracted with Harry Baker Smith Architects II, PLLC (HBSA) to design a condominium complex, which would be built by Roy Anderson Corporation. All parties agreed to arbitration.
Subsequently, Sea Breeze alleged defects and sought arbitration against the architectural firm and started a separate arbitration proceeding against the contractor. The special arbitrator appointed by the American Arbitrators Association determined that it would be proper to consolidate the two actions “since they arose from a common question of fact or law.” HBSA filed in chancery court seeking injunctive relief and a reversal of the decision. Sea Breeze and Roy Anderson filed a motion to compel the consolidated arbitration.
The court noted that the special arbitrator “established that the contract between Sea Breeze and Roy Anderson expressly allowed for consolidation of the two cases.” Further, the arbitrator “concluded that HBSA expressly agreed to consolidation by written consent through its 2008 letter, through which it insisted upon Roy Anderson’s involvement ‘in any mediation and/or arbitration.’”
The court concluded that the chancery court “did not have the power to fulfill HBSA’s request.” The court affirmed the chancery court’s judgment.
Read the court’s decision…
Don MacGregor To Speak at 2011 West Coast Casualty Construction Defect Seminar
January 1, 2011 — February 08, 2011 CDJ Staff
“Challenges for Experts in Construction Defect Claims and Litigation” will be held Thursday May 13, 2011 between 1:30 and 3:00 PM at this year’s West Coast Casualty Construction Defect Seminar. Among the various topics covered will be of Right to Repair/Opportunity to Repair statutes, improper testing methodologies, new challenges where a case involves a Wrap Policy, OCIPS, CCIPS, and other owner controlled insurance programs, as well as the need for realistic testing protocols for the party the expert is retained to represent.
During the presentation Mr. MacGregor will be working in connection with a group of construction and design experts each of which have extensive experience with construction defect and claims related litigation. This particular session is expected to attract a standing-room only crowd, drawing in excess of 1700 attendees.
The West Coast Casualty Construction Defect Seminar is the largest seminar of its type. This year’s event is scheduled for will take place on May 12 and 13, 2011, at The Disneyland Hotel and Resort. For more information regarding the years event please visit http://www.westcoastcasualty.com/dyncat.cfm?catid=3322
http://www.westcoastcasualty.com/dyncat.cfm?catid=3322
Boston Tower Project to Create 450 Jobs
November 18, 2011 — CDJ Staff
Continuing the development of Boston’s Theater District, Millennium Partners broke ground for the building of Hayward Place, a 15-story residential tower with street-level shops. The project is expected to take two years to complete and will employ about 450 construction workers.
Thomas Menino, the mayor of Boston said that the “ground breaking of Hayward Place is another sign of economic growth and forward progress on the revitalization of this area.” The project will be built by Suffolk Construction. John Fish, their CEO, said they were “fortunate as a contractor to be the beneficiary of this.”
The report in the Boston Herald notes that a few blocks away, the site of the former Filenes department store is still “an empty eyesore.” Menino joked, “anyone want to bid for it?” He promised that site would also be developed.
Read the full story…
Lien Law Unlikely To Change — Yet
May 26, 2011 — Melissa Brumback, Construction Law in North Carolina
For those of you following the proposed revisions to the NC lien law that is currently at the NC House Judiciary Subcommittee B, a quick update: the proposed bill (HB 489) is unlikely to be voted on this legislative session due to its unpopularity with several constituency groups, including both the AIA-North Carolinaand the NC Home Builders Association.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Arizona Supreme Court Confirms Eight-Year Limit on Construction Defect Lawsuits
July 18, 2011 — CDJ Staff
Acting on the case of Albano v. Shea Homes Ltd. Partnership, the Arizona Supreme Court has ruled that Arizona’s eight-year statute of repose applies. The case was referred to the court by the Ninth Circuit Court of Appeals which had asked for a clarification of Arizona law. The case focused on three questions:
1. Does the filing of a motion for class certification in an Arizona court toll the statute of limitations for individuals, who are included within the class, to file individual causes of action involving the same defendants and the same subject matter?2. If so, does this class-action tolling doctrine apply to statutes of repose, and more specifically, to the statute of repose for construction defects set forth in Arizona Revised Statutes ("A.R.S.") § 12-552?3. If the doctrine applies to statutes of repose, and specifically § 12-552, may a court weigh the equities of the case in determining whether, and to what extent, an action is tolled?
The litigation at hand has a lengthy history, starting with a case referred to as “Hoffman” in 2003. The Albano plaintiffs were not able to join in Hoffman, and they filed their own lawsuit in 2006. An additional lawsuit was filed by the Albano plaintiffs in 2007. The courts decided that the Albano plaintiffs’ lawsuit was untimely.
The Arizona Supreme Court concluded that the statute of repose was the appropriate standard for this case. They noted that “the eight-year statute of repose period began to run on November 6, 1997, the date of the Town of Gilbert’s final inspection. Albano II was filed on November 5, 2007.”
The court found that the plaintiffs had waited too long for start their suit. As a result, they found it unnecessary to answer the first or third questions. Justice A. John Pelander of the Arizona Supreme Court wrote the opinion, dated June 30, 2011.
Read the court’s decision…
A Performance-Based Energy Code in Seattle: Will It Save Existing Buildings?
August 11, 2011 — Douglas Reiser, Builders Counsel
The City of Seattle has one of the most stringent energy codes in the nation. Based upon the Washington State Energy Code (which has been embroiled in litigation over its high standards), the code demands a lot from commercial developers. But, does it prevent developers from saving Seattle?s classic and old buildings? Perhaps.
The general compliance procedure requires buildings to be examined during the permitting process. This means that buildings are examined before they begin operating. The procedure is not malleable and is applicable to all buildings, old and new, big and small.
The downside of this procedure is that it eliminates awarding compliance to those buildings exhibiting a number of passive features, such as siting, thermal mass, and renewable energy production. This problem has prevented a number of interesting and architecturally pleasing existing building retrofits from getting off the ground. The cost of complying with the current system can be 20% more, and it might prevent builders from preserving a building?s historical integrity.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Contractor’s Home Not Covered for Construction Defects
September 13, 2012 — CDJ Staff
The US District Court in Seattle has rejected most of the claims made by a Des Moines man over insurance coverage for water damage to his home. Judge John C. Coughenour granted summary judgment to Liberty Northwest in Ayar v. Liberty Northwest Insurance Corporation.
Sayad Ayar was the general contractor for the construction of his house. As a homeowner held a $1.5 million insurance policy from Liberty Northwest (LNW) that excluded “faulty, inadequate, or defective construction.”
In 2008, less than three years after his house was constructed, Mr. Ayar filed a claim after water leaked through his living room ceiling. LNW hired an engineering firm to investigate the damage. The engineering firm, CASE Forensics, concluded that the water intrusion was due to “the failure to install an adequate and continuous waterproof membrane, flashing, and drainage system within the balcony at the time of construction.” Ayar’s expert attributed the leakage to “damage done to the weather deck waterproofing during a storm event with high winds,” which would be covered under the policy. CASE Forensics reviewed these conclusions and rejected them. LNW denied coverage.
Further problems lead to further investigations, and in each case, LNW attributed the problems to construction defects. During this process, LNW “authorized Ayar to cut into the ceiling’s drywall in order to assist in determining the source of the water intrusion.” Mr. Ayar moved his family to a rental home. He requested that LNW cover the rental and other other costs.
LNW’s adjuster concluded that no coverage was available, but recommended paying Mr. Ayar $19,648.68 to reinstall drywall and repair the hole in the ceiling. The insurance company paid $2,000 to cover the cost of cutting into the ceiling. The also claimed the amount of drywall he removed was “excessive” and would not cover his relocation as “his home had been livable and because the loss was not covered.”
Ayar made four claims to the court in support of the argument that LNW misrepresented “pertinent facts or insurance policy provisions.” The court rejected three of these, noting that as all water damage was excluded, LNW’s citation of other sources of water intrusion was not a misrepresentation. “LNW did not rely on this provision as the reason for denying coverage.” Nor was LNW’s reference to “fungi, wet or dry rot” a misrepresentation. As for their reference to construction defects, it “was clearly appropriate given that the construction defect exclusion was the principal basis or denying the claim.” However, the court found that regarding the removal of drywall, “a triable issue of the facts exists.”
Ayar also claimed that LNW did not conduct a reasonable investigation, but the court found no evidence to support this conclusion. “This is not a case where the insurer failed to investigate or did so only half-heartedly.” Although the thoroughness of the investigation could not questioned, the court concluded that its timing could. Ayar claimed that LNW engaged in unreasonable delays. LNW counters that the delays were due to “Ayar’s own obstructive behavior and failure to cooperate with LNW’s investigation.”
The court dismissed all of Ayar’s claims, with the exception of whether LNW should have informed him that they would not pay for drywall repair unless there was damage, and whether LNW’s investigation failed to conclude its investigation within a thirty-day time line.
Read the court’s decision…
Record-Setting Construction in Fargo
November 7, 2012 — CDJ Staff
Prairie Business reports that Fargo is experiencing the most new construction it has ever seen, totaling $434 million in value, which exceeds the previous high in 2006 of $428 million. Many of the construction starts are for single family homes, although there is also an increase in construction of apartments and townhomes.
The Home Builders Association of Fargo-Moorhead also noted that there was also a large of remodeling projects. Terry Becker, the president of the HBA, said that “remodeling is just huge right now.”
Read the full story…
Defect Claims as Occurrences? Check Your State Laws
July 10, 2012 — CDJ Staff
Although four states have defined construction defect claims as occurrences, contractors are still dealing with “coverage gaps for faulty work construction,” says Mike Tsikoudakis in a piece at Business Insurance. He quotes Julian Ehrlich, the senior VP of claims for Aon Risk Services that “one of the interesting and compelling aspects of the issue of coverage for defective construction is that jurisdictions differ, so policyholders don’t know what they’re going to get.” He further notes that “in context of construction defect, the term ‘occurrence’ is ambiguous.”
One problem, as noted by Jeffrey J. Vita, a partner at Saxe Doernberger & Vita, is that construction firms end up needing to simultaneously defend against defect claims and to also file suit to be certain their insurance firms will cover claims. Insurance for construction defect claims is described as “expensive and somewhat limited.” Mr. Vita expects more states to help this situation with new laws, clarifying what is an occurrence.
Read the full story…
LEED Certified Courthouse Square Negotiating With Insurers, Mulling Over Demolition
June 6, 2011 — Douglas Reiser in the Builders Counsel Blog
Apparently, Courthouse Square is still unresolved. The County hasnow hired an attorney to handle its insurance claim against Affiliated FM. Is there a lawsuit coming?
Right now, no lawsuit is expected. According to officials, the insurer has been acting in good faith. But, its been quite a while since Salem officials learned that the Courthouse Square building had significant concrete issues that would result in probable demolition of the LEED certified building.
If you have yet to hear about Courthouse Square, let me fill you in briefly. The Salem building was substantially completed in 2000 and LEED certified by the US Green Building Council in 2002. The project cost more than $30 Million to complete and the building was revered for its innovation as a crowning achievement for city leaders.
But, structural problems in the building’s core were discovered as early as 2002, writes Chris Cheatham of Green Building Law Update. Final tests earlier in the year, determined that the building had to be vacated. The building has been clear since July 2010.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Bound by Group Builders, Federal District Court Finds No Occurrence
August 11, 2011 — Tred Eyerly, Insurance Law Hawaii
The homeowners sued their contractor, alleging the contractor had defectively constructed and failed to complete their home.  State Farm Fire and Casualty Co. v. Vogelgesang, 2011 U.S. Dist. LEXIS 72618 (D. Haw. July 6, 2011). The homeowners' complaint pled, among other things, damage caused by breach of contract and negligence. State Farm agreed to defend under a reservation of rights.
State Farm filed suit in federal court for declaratory relief. Judge Mollway granted State Farm's motion for summary judgment. Relying on the Hawaii Intermediate Court of Appeal's decision in Group Builders, Inc. v. Admiral Ins. Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010), Judge Mollway determined that the claims asserted in the underlying litigation arose from the contractor's alleged breach of contract.  Group Builders held that breach of contract claims based on allegations of shoddy performance were not covered under CGL policies.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com