Court Orders House to be Demolished or Relocated
April 26, 2011 — April 26, 2011 Beverley BevenFlorez - Construction Defect Journal
Decision Affirmed in Central Arkansas Foundation Homes, LLC v. Rebecca Choate
The Arkansas Court of Appeals affirmed the decision by the trial court in Central Arkansas Foundation Homes, LLC v. Rebecca Choate. In the trial case, Central Arkansas Foundation Homes (CAFH) sought payment for a home built for Choate, while Choate alleged that the builders committed multiple construction defects including using the wrong foundation materials and positioning the house in the wrong direction.
After the house was built, CAFH contacted Choate regarding payment, however, Choate alleged that the finished product did not match the contract. “ After CAFH completed construction, it obtained permanent home financing for Choate and tried to contact her to close the transaction. Choate did not respond until October 2005, when she sent CAFH a list of alleged construction defects, including that the house was facing in the wrong direction; that it was not built on a slab; and that the fireplace, garbage disposal, driveway, and storage area were missing. CAFH replied to Choate in writing, telling her that she had until January 6, 2006, to close on the house or CAFH would sell it. The correspondence enclosed worksheets showing that the amount Choate would owe at closing exceeded $94,000, which included interest that had accrued on the as-yet unpaid construction loan.”
Initially, the court found in favor of CAFH. “On April 18, 2007, Choate’s attorney withdrew from representing her. Soon thereafter, CAFH’s attorney asked the court to set a final hearing on the case. The attorney purportedly sent Choate a letter by regular mail on May 15, 2007, advising her that the case was set for trial on July 9, 2007. Choate, however, did not appear. CAFH did appear, and its general manager, John Oldner, testified to events leading up to the case and the amount of damages claimed. According to Oldner, the interest on the construction loan had accrued to the point that CAFH now sought $104,965.88 from Choate. The court found in favor of CAFH and entered judgment for that amount, plus attorney fees, on July 18, 2007. The court ruled that CAFH could sell the house and either remit any excess to Choate or look to Choate for the deficiency if the sales price did not cover the judgment.”
However, Choate successfully argued that she did not receive notice of the trial. A new trial was ordered, and the outcome was quite different. “On June 6, 2008, the circuit court entered judgment for Choate, ruling that the house was not in substantial compliance with the parties’ contract and that the contract should be rescinded. The court found that the house suffered from numerous construction defects, that the contract contemplated a slab rather than a concrete-pier foundation, and that CAFH ignored Choate’s complaints that the house was facing the wrong way. The judgment directed CAFH to hold Choate harmless on the construction loan, to deed Choate’s two acres back to her, and to remove the house from Choate’s property.”
The Court of Appeals “found that Choate would be unjustly enriched by retaining the benefit of the septic systems and utility lines that CAFH installed on her land. The court therefore awarded $5340 to CAFH as a quantum-meruit recovery for the value of that work. CAFH contends that the award is not sufficient, but we see no clear error.” In the end, the Court of Appeals provided this reason for declining to reverse the trial court’s decision: “The court in this case apparently concluded that the house constructed by CAFH was so fundamentally at odds with Choate’s contractual expectations that she was not unjustly enriched and should simply be, as nearly as possible, returned to the status quo ante. Accordingly, the court ordered the house removed from her property and permitted CAFH to either relocate the house or salvage the house’s materials and unused appliances. We decline to reverse the court’s weighing of the equities in this manner.”
Read the court’s decision…
Tennessee Court: Window Openings Too Small, Judgment Too Large
November 18, 2011 — CDJ Staff
The Tennessee Court of Appeals has issued a ruling in the case of Dayton v. Ackerman, upholding the decision of the lower court, even as they found that the award was incorrectly computed. The Daytons purchased a house that had been designed and built by the Ackermans, who operated a construction business. The court noted that the warranty with the house promised that “for a period of 60 days, the following items will be free of defects in materials or workmanship: doors (including hardware); windows; electric switches; receptacles; and fixtures; caulking around exterior openings; pluming fixtures; and cabinet work.”
Soon, the Daytons began to experience problems with the house. Many were addressed by the Ackermans, but the Daytons continued to have problems with the windows. Neither side could specify a firm date when the Ackermans were contacted by the Daytons about the window problems. The Ackermans maintained that more than two years passed before the Daytons complained about the windows. The lower court found the Daytons more credible in this.
Initially, the Daytons included the window manufacturer in their suit, but after preliminary investigations, the Daytons dropped Martin Doors from their suit. Martin Doors concluded that the windows were improperly installed, many of them “jammed into openings that were too small for them.”
After the Daytons dismissed Martin Doors, the Ackermans sought to file a third party complaint against them. This was denied by the court, as too much time had elapsed. The Ackermans also noted that not all of the window installations were defective, however, the courts found that the Daytons ought not to have mismatched windows.
Unfortunately for the Daytons, the window repair was done incorrectly and the windows were now too small for the openings. The firm that did the repair discounted the windows and Daytons concealed the problem with plantation shutters, totalling $400 less than the original lowest estimate. However, the appeals court noted that it was here that the trial court made their computation error. Correcting this, the appeals court assessed the Ackermans $12,016.20 instead of $13,016.20.
Finally, the Ackerman’s expert was excluded as he had changed his testimony between deposition and trial. The trial reviewed the expert’s testimony and had it been admissible, it would not have changed the ruling.
Read the court’s decision…
Safer Schools Rendered Unsafe Due to Construction Defects
February 10, 2012 — CJD Staff
Built on a program for safer school buildings, schools in Neenan County, Colorado have been shown to have mild-to-moderate structural problems, rendering some of them unsafe. The Denver Post reports that a third-party review of schools built by the Neenan Company has shown structural issues in all fifteen school buildings.
One school, Meeker Elementary, has been closed as it could collapse under high winds or during an earthquake. Sargent Junior-Senior High School is in use, but there are plans to evacuate the buildings if winds exceed 25 mile per hour. Two schools have roofs that are unable to bear expected loads of snow during the winter.
The Neenan Company says that the school buildings are not up to their standards and is working with the school districts to repair the buildings. Repairs are expected to be complete by August.
Read the full story…
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 — Douglas Reiser, Builders Cousel
Ever had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Landmark San Diego Hotel Settles Defects Suit for $6.4 Million
March 4, 2011 — April 4, 2011 Beverley BevenFlorez - Construction Defect Journal
After five years of legal battles, the condo owners of the El Cortez Hotel building in downtown San Diego settled for $6.4 million, as reported by The San Diego Union-Tribune on March 28, 2011. The Homeowners Association will net just over $3 million from the settlement.
The litigation may have had an adverse effect on the value of the condos within the El Cortez Hotel building. According to an article by Kelly Bennett of Voice of San Diego, “Many condos in the building originally sold for more than $600,000. Currently, the three units on the market are asking for just more than $200,000, the U-T said.”
Andrew Berman, the owners’ attorney, told The San Diego Union-Tribune that the five years of litigation included six lawsuits, 200 depositions, and multiple construction tests.
Read the full story... (San Diego Union Tribune)
Read the full story... (Voice of San Diego)
Webinar on Insurance Disputes in Construction Defects
July 10, 2012 — CDJ Staff
Seth Lamden, of the firm Neal Gerber Eisenberg will be presenting a webinar on “Insurance Coverage Disputes in Construction Defects” on July 17, 2012 at 1 p.m. EDT. Mr. Lamden’s presentation will focus on “handling both the construction and insurance components of construction defect claims.” He will be discussing recent case law and new insurance products. The presentation will present information on evaluating various types of insurance policies, explaining common issues, contract requirement, and the economic loss doctrine. Mr. Lamden will advise attendees on how to avoid getting into a construction defect case. He will conclude his presentation with a brief question-and-answer session.
Read the full story…
Ensuing Losses From Faulty Workmanship Must be Covered
May 10, 2012 — Tred Eyerly, Insurance Law Hawaii
Coverage for damages resulting from faulty workmanship in the construction of an apartment complex was at issue in The Bartram, LLC v. Landmark Am. Ins. Co., 2012 U.S. Dist. LEXIS 44535 (N.D. Fla. March 30, 2012).
The owner of the apartments, Bartram, had primary coverage and three layers of excess coverage. Each contract excluded loss from faulty workmanship. The policies provided, however, "if loss or damage by a Covered Cause of Loss results, we will pay for that resulting loss or damage."
Bartram contended water intrusion occurred because of faulty workmanship, which caused damage to the buildings’ exterior and interior finishes, wood sheathing, framing, balcony systems, drywall ceilings and stucco walls. This damage was separate from the work needed to simply fix the faulty workmanship. Therefore, Bartram argued, the ensuing losses that resulted from the water intrusion was covered.
The insurer argued the ensuing loss exception was not applicable if the ensuing loss was directly related to the original excluded loss.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Godfather Charged with Insurance Fraud
July 1, 2011 — CDJ Staff
Texas-based Godfather Construction is a recipient of a fraud suit from the Cook County state attorney’s office. The firm incorporated in Illinois in April 2010, moving there to do business after storms damaged homes in the Chicago suburbs, according to a report in the Chicago Tribune. The state attorney alleges that Godfather brought unlicensed out-of-state workers and the work they performed was “incomplete or shoddy.” Godfather is claimed to have received about $60,000 from Illinois homeowners. The prosecutors are seeking restitution for Godfather’s clients and seek to forbid the firm from doing business in Illinois.
Read the full story…
Hawaii State Senate Requires CGL Carriers to Submit Premium Information To State Legislature
March 20, 2011 — March 20, 2011 Construction Defect Journal Staff
In light of the decision in Hawaii’s Intermediate Court of Appeals in Group Builders, Inc.,v. Admiral Insurance Company, 231 P.3d 67(2010), Hawaii’s state senate is requesting that "every domestic and foreign insurance company that has ever issued commercial general liability policies in the State is requested to submit information to the Legislature on the total premiums received for their commercial general liability policies during the past ten years"
Read Full Text of Hawaii State Senate Resolution
Contractor Sues License Board
June 30, 2011 — CDJ Staff
Judge Kendall J. Newman of the US District Court handed down a decision on June 24 on the case of Kent v California Department of Consumer Affairs. Mr. Kent, appearing as his own counsel, had brought the suit against the California Department of Consumer Affairs and the Contractors State Licensing Board after he was arrested in a sting operation and, as the plaintiff put it, “was absurdly arrested and uncooperatively detained for a time longer than necessary or allowed by law under the false pretense of contracting with out a license.” Mr. Kent’s alleged that Rick Lopez, one of the defendants, formed him to read allow from the California Business and Professions Code. He said he was later handcuffed and placed in an uncomfortable chair, “enduring physical pain and emotional agony.”
Although Kent was given a Notice to Appear, he alleged that a further defendant, Stuart Rind, “closed the plaintiff’s case marked citation A7773 without giving written notice to anyone.” As a result, the Placer County District Attorney’s Office had no record of his Notice to Appear.
Kent alleged that subsequently his firm was essentially shut down for two years and that he was prevented from “legally contracting or selling services for any other contractor or qualifying for any other licensed capacity governed by the CSLB.” After this, the CSLB suspended the license for his firm, DSI Construction. He was assessed a $1,500 fine, after which he claims he sent a letter to the CSLB demanding money damages. The judge noted that the letter was not included in the plaintiff’s Ninth Amended Complaint.
Judge Kendall recommended that the plaintiff’s Complaints be dismissed, although he did allow that sixth, and perhaps the eighth and ninth, could be amended with a tenth amended complaint.
Read the court’s decision…
Construction Employment Rises in Half of the States
December 9, 2011 — CDJ Staff
The Labor Department has noted that half the states and the District of Columbia saw increases in construction employment during the month of October. During the same month, twenty-three states lost construction jobs.
The biggest gains were in North Dakota, Oklahoma, DC, Texas, and California. The biggest losses were in Georgia, New Mexico, Wisconsin, and Florida. There was no change for Alabama.
The chief executive officer of the Association of General Contractors of America, Stephen E. Sandherr, called for more infrastructure development. “Allowing water, transportation and energy networks to deteriorate will hurt construction employment and force taxpayers to spend more later, to fix broken infrastructure.”
Read the full story…
Green Buildings Could Lead to Liabilities
March 28, 2012 — CDJ Staff
Attempts to build “green,” reducing energy costs and increasing the use of sustainable building materials, may lead to more lawsuits, according to a report issued by the British Columbia Construction Association. The report warned those who were going to build green look into the implications. The report looked at the result of green building practices and requirements adopted in the United States.
The report warns that “the use of novel, less harmful building material or new construction techniques may give rise to liability due to: contractor inexperience with installation; lack of long-term evaluation of green materials; lack of understanding of how new building materials may impact existing traditional building systems; or warranties provided unintentionally about the durability or effectiveness of unproven materials or techniques.”
Manley McLachlan, president of the BCAA noted that they are aware of “legal action around the performance of the buildings,” noting that while fast-growing trees help toward LEED certification, their wood is more prone to mold. He also felt that low-VOC paints needed more testing to prove their durability as exterior finishes.
Read the full story…
Homeowner Loses Suit against Architect and Contractor of Resold Home
June 14, 2011 — CDJ Staff
The California Court of Appeals in the case of Kizor v. Architects ruled that Mr. Kizor could not make construction defect claims against the architect and contractor of his home, as the defects had caused significant damage to the former owners, and it was they, not Kizor, who could have asserted those claims.
The background of the case was that John and Miranda Redig hired BRU Architects to design a home. During construction in 2000, they wrote to the roofing supplier complaining about leaks. The leaks were caulked, but the roof continued leaking during rains. The Redigs sold their house to Kizor in 2002, with an addendum to the sale contract protecting themselves from liability for further problems with the roof. “Seller has no responsibility for the condition of the roof and stucco and buyer absolves seller of any liability in connection therewith.”
In 2006, Kizor sued the architects, contractor, and subcontractor. The defendants moved for summary judgment which was granted. Kizor appealed, and in this current court case, appeal was denied.
Read the court’s decision
Court Clarifies Sequence in California’s SB800
December 20, 2012 — CDJ Staff
As California’s Right-To-Repair law, SB800, nears its ninth birthday, it has remained “largely untested in the legal system” as noted by Megan MacNee of Wood, Smith, Henning & Berman LLP on the site RealEstateRama. She writes that some homeowners have requested documents prior to filing a claim, which she describes as an attempt to “game the system,” and “analogous to requiring a party to litigation to comply with discovery before a complaint is filed.”
The court determined that homeowners may not request documents from the builder until they have actually filed a claim. The court noted that SB800 lacks any clear indication that homeowners may request documents before filing a claim (and also does not indicate that a builder would have to provide documents in these circumstances). The court concluded that the section that sets up the prelitigation procedures occurs before they section on documents discovery.¬? “Because the document request is part of the prelitigation procedure, and the prelitigation procedure does not begin until the homeowner has served notice of a claim, it follows that there can be no prelitigation obligation to produce documents under section 912, subdivision (a) unless the homeowner has commenced the prelitigation procedure by serving notice of a claim.”
Read the full story…
Judge Kobayashi Determines No Coverage for Construction Defect Claim
October 23, 2012 — Tred Eyerly, Insurance Law Hawaii
Judge Kobayashi of the U.S. District Court, District of Hawaii, largely followed earlier precedent established by Judge Mollway in finding no coverage for construction defect claims. See Evanston v. Nagano, 2012 WL 3800320 (D. Hawaii Aug. 31, 2012).
Evanston issued several liability policies to the insured contractor from 2002 and 2011. The insured entered a contract to build a residence in Honolulu. The homeowners were not happy with their home after the work was completed. They filed suit, alleging that the project was delayed and the construction was "riddled with defects." The complaint included claims for breach of contract and breach of warranties. Negligence was not alleged. Evanston defended, but under a reservation of rights.
Evanston filed suit for a declaratory judgment and moved for summary judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Insurance Policy Provides No Coverage For Slab Collapse in Vision One
August 17, 2011 — Douglas Reiser, Builders Counsel
This post will examine whether Division Two of the Washington Court of Appeals properly reversed and remanded several lower court decisions in the case of Vision One LLC v. Philadelphia Indemnity Insurance. In short, and from the perspective of an appellate attorney, the court of appeals got the decision right. Given the rules of contract interpretation and causation in tort claims, there was really no other way the court could have ruled. I understand that from a contractor’s perspective and insurance perspective, the decision seems odd. But from a purely legal standpoint, the decision is well-reasoned and well-supported. Let me explain.
Background
First, here are the facts in a nutshell. Vision One is a construction company that undertook to construct a condo complex in Tacoma. Vision then contracted with D&D Concrete to pour a concrete slab for a section of the foundation. To shore the concrete slab, D&D further contracted Berg Equipment to provide necessary equipment to stabilize the structure. Well, something down the line went wrong. The shoring failed and the slab collapsed, causing a great deal of damage.
Read the full story…
Read the court’s decision…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Gilroy Homeowners Sue over Leaky Homes
February 10, 2012 — CDJ Staff
Two years into a lawsuit against Shapell Homes, the builder of a subdivision called Eagle Ridge in Gilroy, California, homeowners have joined or left the lawsuit. About fifty homeowners are still in the suit, which contends that construction defects have lead to water intrusion in their homes. The lawyer for the homeowners contends that more than a hundred homes have construction defects.
One homeowner said that soon after he joined the suit, Sharpell sent workers to his home who repaired problems to his satisfaction. “They came in within two weeks and fixed everything,” said Frank Lowry. Another homeowner, Wilson Haddow, said that he was “quite happy” after Shapell repaired problems.
Others weren’t quite so happy. Greg Yancey said that problems had “been a nightmare” and that “it just doesn’t feel like home.” He said that his “house is possessed,” with problems that include walls that bow out and a balcony that drips rainwater to the front door. His home is currently worth far less than the $700,000 he paid in 2007.
Read the full story…
Changes To Indemnification Statute Are Here! Say Hello To Defense Duties
June 19, 2012 — Douglas Reiser, Builders Counsel
A months back, I discussed the passage of SHB 1559. The law changes the existing statutory indemnification regulation to include the costs of defense and to rid contracts of unfair indemnification for someone else’s sole negligence. The law went into effect last week!
Check back to my recent article on the changes set forth in the new law. The amendments to RCW 4.24.115 will broaden the existing law and clarify what types of indemnification are unenforceable. In short, an “up the chain” contractor (such as a general contractor) cannot expect to pass 100% of the defense and indemnification obligations downward if it is partially liable.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com