Construction Defect Notice in the Mailbox? Respond Appropriately
August 4, 2011 — Douglas Reiser, Builders Counsel
Recently, I have seen a rash of ignored construction defect notices. What is a construction defect notice? It’s a statutorily required notice, sent from a homeowner to a contractor, listing a number of defects found at their property. If you get one, don’t ignore it.
The Revised Code of Washington includes a number of provisions intended for residential construction disputes. Among them is the “Notice to Customer” requirement in RCW 18.27.114, which can preempt a contractor’s lien rights, and the “Notice of Construction Defects” found in RCW 64.50.020.
The Notice of Construction Defects is a standard notice mandated by RCW 64.50, a chapter in the Revised Code of Washington, intended to provide a pre-litigation resolution process for contractors and consumers. The chapter applies only to those losses “caused by a defect in the construction of a residence or in the substantial remodel of a residence.”(See “Action” RCW 64.50.010).
Unfortunately, many contractors will simply ignore these notices or tell the homeowner to make a warranty claim. But, the notice actually provides a contractor with a forty-five (45) day window to alleviate the dispute.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Court finds subcontractor responsible for defending claim
May 18, 2011 — May 18, 2011 - CDJ Staff
In an unpublished decision, the California Fourth Appellate District Court has reversed the judgment of Judge Linda B. Quinn of the Superior Court of San Diego. In the case Inland California, Inc. v. G.A. Abell, Inland, a general contractor had subcontracted with Apache Construction and Precision Electric Company (G.A. Abell).
Apache alleged that extra demolition and drywall work was needed due to Precision’s electrical work. Inland tendered a defense of Apache’s claims. However, Precision did not provide any defense. Inland withheld payment from Precision.
At trial, Inland “conceded Precision earned the $98,000 in progress payments Inland withheld.†They were obligated to additionally pay Precision’s costs and attorney fees.
The Fourth Appellate District court has overturned this and remanded the case back to the lower court. The judges determined that Precision was obligated to defend itself against the claims raised by Apache and therefore vacated the judgment against Inland.
Read the court’s decision…
Construction Defects as Occurrences, Better Decided in Law than in Courts
December 9, 2011 — CDJ Staff
Construction defect claims are now occurrences for insurance purposes in four states, Arkansas, Colorado, Hawaii, and South Carolina, yet there are still frustrations for commercial general liability policyholders. Business Insurance describes court decisions on whether construction defect claims are covered as “incongruous,” and this drives up coverage and litigation costs. Construction firms often find they are defending themselves on two fronts, both the construction defect claim and also whether their insurance covers it.
Frank Armstrong, the Senior Vice President and National Director of Construction Claims for Willis North America says that the problem starts with the word “occurrence,” as various state courts have different interpretations of the word. “Certain pieces of it don’t fit well, at lest according to some courts in the country, with coverage for construction defect risks.”
Another insurance executive, Julian Ehlich, the Senior Vice President of Claims for Aon Risk Solutions’ construction services group notes that “jurisdictions differ, so policyholders don’t know what they’re going to get.”
Read the full story…
Insurer’s Motion for Summary Judgment Based on Earth Movement Exclusion Denied
October 28, 2011 — Tred Eyerley, Insurance Law Hawaii
After carefully dissecting the earth movement exclusion, the court denied the insurer’s motion for summary judgment. High Street Lofts Condominium Assoc., Inc. v. Am. Family Mut. Ins. Co., 2011 U.S. Dist. LEXIS 109043 (D. Colo. Sept. 26, 2011).
The City of Boulder performed road repair work near High Street’s property, some of which involved the use of a vibrating compactor to compact and set the roadbed. High Street noticed damage to its building, such as cracks in walls, sloping of floors and separations of porches from the building itself. High Street contacted the City of Boulder, who forwarded the complaint to its contractor, Concrete Express, Inc.
High Street also filed a claim with its business insurer, American Family, who denied the claim. American Family relied on an opinion letter by High Street’s engineer. The letter indicated that the damage was the result of "soil consolidation/settlement," in response to the construction activities. Based on this letter American Family concluded the claim was excluded under the policy’s earth movement exclusion.
High Street sued American Family, who moved for summary judgment.
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Policing Those Subcontractors: It Might Take Extra Effort To Be An Additional Insured
June 14, 2011 — Douglas Reiser, Builders Council Blog
I just came across a case that I think truly paints the insurance dilemma for contractors. Thanks to this recent Illinois case, I don’t have to make up any factual scenarios—so kudos to Attorney Robert Boylan for posting it.
In reading over my RSS feeds this weekend, I noticed a great writeup on long-time blogger Josh Glazov’s Construction Law Today. Attorney Robert Boylan’s post describes a recent Illinois case where a general contractor was denied its additional insured status on a second-tier subcontractor’s insurance. The reason for the denial: the general contractor failed to procure an agreement in writing with the second-tier subcontractor, requiring it to be listed as an additional insured.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Appeals Court Upholds Decision by Referee in Trial Court for Antagan v Shea Homes
May 10, 2012 — CDJ Staff
In the case Antangan v. Shea Homes Ltd. Partnership (Cal. App., 2012), Plaintiffs appealed “an order vacating a judgment and entering a modified judgment in their construction defect action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership,” while the Defendant, Shea Homes Limited Partnership (Shea Homes) appealed “an order of the judicial referee denying its motion to strike and tax costs.”
On the Antagon issue, the appeals court concluded that “the trial court did not err by vacating and modifying its judgment so that the cost of referee’s fees would be equally divided by the parties and consistent with a prior stipulation they filed in court.”
On the Shea Homes issue, the appeals court concluded: “1) the judicial referee did not err by ruling that plaintiffs’ offers to compromise (§ 998) were validly served on Shea Homes’ counsel, 2) the offers substantially complied with statutory requirements, 3) the offers were not required to be apportioned, and 4) the referee’s award of $5,000 as costs for a person assisting plaintiffs’ counsel was not an abuse of discretion.” The appeals court affirmed the judgment.
Here is a brief history of the trial case: “Plaintiffs Chito Antangan, Jimmy Alcova and other homeowners brought an action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership for damages alleging that the properties they purchased from these ‘developer defendants’ were defective. Plaintiffs claimed numerous construction defects required them ‘to incur expenses’ for ‘restoration and repairs’ and the value of their homes had been diminished.”
In response, Shea Homes filed a motion for an order to appoint a judicial referee. The motion was granted and it was ruled that “a referee would ‘try all issues’ and ‘report a statement of decision to this court.’”
On May 10, 2010 the judicial referee (Thompson) “awarded plaintiffs damages and various costs, and ruled that ‘Shea Homes shall bear all of the Referee’s fees.’” The latter ruling would become a matter for contention later on.
In July of 2010, the plaintiffs “sought, among other things, $54,409.90 for expert fees, and $14,812.50 for the services of Melissa Fox for ‘exhibit preparation & trial presentation.’ Shea Homes filed a motion to strike and/or tax costs claiming: 1) Fox was a paralegal, 2) plaintiffs were not entitled to attorney’s fees, and 3) the fees for Fox’s services were an indirect and improper method to obtain attorney’s fees. The referee disagreed and awarded $5,000 for Fox’s services. The referee also ruled that plaintiffs had properly served valid offers to compromise (§ 998) on Shea Homes’ counsel in 2009. He said those offers to defendants in the case at that time did not have to be apportioned.”
“Antangan contends the trial court erred when it vacated and modified its original judgment, which ordered Shea Homes to pay all the referee’s fees. We disagree.”
Antagon contended that the trial court erred when it vacated and modified its original judgment regarding Shea Homes paying the referee’s fees. The appeals court disagreed: “A trial court has inherent authority to vacate or correct a judgment that is void on its face, incorrect, or entered by mistake. (§ 473; Rochin v. Pat Johnson Manufacturing Co. (1998),67 Cal.App.4th 1228; Olivera
Read the court’s decision…
Construction Law Alert: A Specialty License May Not Be Required If Work Covered By Another License
March 7, 2011 — By
Steve Cvitanovic of
Haight Brown & Bonesteel, LLP.Contractors should always be sure that they understand the licensing in any Subcontract or Prime Contract before entering into any agreement. However, on March 3, 2011, in the case of Pacific Casson & Shoring, Inc. v. Bernards Bros., Inc. 2011 Cal.App.Lexis 236, the Court of Appeal determined that if a specialty license is subsumed within another license, the specialty license may not be required.
Bernards entered into a subcontract with Pacific to excavate, backfill, grade and provide geotechnical design parameters for a hospital. The Prime Contract required the bidder to maintain a Class C-12 specialty earthwork license. However, Pacific only held a Class A general engineering license which it turns out was suspended during the performance of the work. Pacific sued Bernards for nonpayment of $544,567, but the lawsuit was dismissed because the trial court found that Pacific (1) lacked a C-12 license, and (2) Pacific’s Class A license was suspended for failure to pay an unrelated judgment. Pacific was also ordered to disgorge $206,437 in prior payments.
The Court of Appeal reversed and remanded. The Court of Appeal agreed with Pacific and held that a C-12 specialty license was not required despite the Prime Contract. The Court of Appeal found that the C-12 specialty license would have been “superfluous” since it was fully encompassed within the Class A requirements. However, the Court of Appeal also remanded the case for further
Read the full story...
Reprinted courtesy of Steve Cvitanovic of Haight Brown & Bonesteel, LLP.
Know the Minnesota Statute of Limitations for Construction Defect Claims
July 10, 2012 — CDJ Staff
Writing on the Benson Kerrane Storz Nelson web site, Alex Nelson gives an overview of the Minnesota laws covering statutes of limitation and repose. He notes that frequently when his firm declines to take a construction defect case its’ over a missed statute of limitation. He describes the time periods as both “short” and “ambigious.” The briefest limit is that a homeowner “has only 6 months within which to give written notice of the defect to the builder once the defect has manifested itself.” Any legal action must commence within two years of the same point.
The Minnesota statutes also have a six-year limitation, which starts for a single home at transfer of title to the first purchaser or when the purchaser takes possession, whichever happens first. For a condo, it is the last of “completion of the common element,” first unit sale or “Termination of Declarant control.” Fraud or misrepresentation also has a six-year limit, while negligence claims are limited to within the first two years “after the manifestation of the defect.”
The statues of repose also provide limits to filing construction defect lawsuits. Mr. Nelson points out that the longest are for negligence, fraud, and “major construction defects,” all of which have a ten-year limit. On the other hand, claims against general workmanship and materials must be made in the first year.
Read the full story…
Construction Defects Leave Animal Shelter Unusable
October 23, 2012 — CDJ Staff
The Press Democrat reports that the Healdsburg Animal Shelter is proceeding in its lawsuit against the architect, general contractor, and subcontractors of its unfinished new facility. Shelter officials described the building as “effectively uninhabitable,” and the board has suggested that the building might have to be demolished. The chair of the shelter board told donors that “your investment is protected.”
The defects in the building include cracked concrete slabs and gaps around windows. However, even without these defects, the shelter alleges that the architect failed to correct design flaws.
Read the full story…
Seven Former North San Diego County Landfills are Leaking Contaminants
April 7, 2011 — April 7, 2011 Beverley BevenFlorez - Construction Defect Journal
Deborah Sullivan Brennan of the North County Times reported that seven former dumps in San Diego are leaking contaminants into the surrounding groundwater. John R. Odermatt, a senior engineering geologist for the California Regional Water Quality Control Board s San Diego region, told the North County Times, “the risk to most county residents is very small or negligible, while local water supplies located in more rural areas may be at a somewhat elevated but unquantified level of risk.”
This issue is causing heavy scrutiny of a new proposed landfill in Gregory Canyon. The landfill would be located on 308 acres of undeveloped land near Pala, alongside the San Luis Rey River. The group “Save Gregory Canyon” has been speaking out against the landfill, stating that “the project threatens major detrimental impacts to both surface and groundwater, as well as a potential compromise of the two major San Diego Water Authority pipelines nearby.” Richard Felago, a Gregory Canyon Ltd. Consultant, told the North County Times that the 8-foot-thick liner, composed of layers of gravel and synthetic material, would not leak.
The appeal hearing is being rescheduled later this month after one of the three panelists recused himself due to having a competing interest in the property, according to the article by Gary Warth in the North County Times.
Read the full story (link 1)...
Read the full story (link 2)...
General Contractor/Developer May Not Rely on the Homeowner Protection Act to Avoid a Waiver of Consequential Damages in an AIA Contract
August 4, 2011 — Higgins, Hopkins, McLain & Roswell, LLC
Recently, in Caribou Ridge Homes, LLC v. Zero Energy, LLC, et al., Case No. 10CV1094, Boulder County District Court Judge Ingrid S. Bakke entered a ruling and order on the Plaintiff’s Motion for Determination of Question of Law Pursuant to C.R.C.P. 56(h) on Issue of Damages. The Order found that the Plaintiff was not a homeowner intended to be protected by the Homeowner Protection Act (the “HPA”) and thus could not pursue its claims for consequential damages against Defendant.
By way of background, on June 18, 2008, Plaintiff Caribou Ridge Homes, LLC (“Caribou”) entered into a Standard Form Agreement Between Owner and Contractor AIA Document A114-2001 (the “Contract”) with Defendant Zero Energy, LLC (“Zero Energy”). Plaintiff hired Zero Energy to serve as a general contractor for the construction of a single-family home in the Caribou Ridge subdivision in Nederland, Colorado. A provision in the contract contained a mutual waiver of consequential damages (“Waiver”).
Read the full story…
Reprinted courtesy Higgins, Hopkins, McLain & Roswell, LLC
Homeowner’s Policy Excludes Coverage for Loss Caused by Chinese Drywall
November 18, 2011 — Tred Eyerley, Insurance Law Hawaii
Exclusions barred the homeowners from recovering for losses caused by Chinese drywall in their home. Ross v. C. Adams Const. & Design, L.L.C., 2011 La. App. LEXIS 769 (La. Ct. App., released for publication Oct. 5, 2011).
Two years after purchasing their home, the Rosses began experiencing chronic malfunctions in the heating, ventilation and air conditioning system. After discovering the presence of gypsum drywall, or "Chinese drywall", they submitted a claim to their insurer, Louisiana Citizens Property Insurance Company, for damages caused by the Chinese drywall. Louisiana Citizens denied the claim.
The Rosses sued. The trial court granted summary judgment to Louisiana Citizens based upon exclusions in the policy.
On appeal, the appellate court first agreed the Rosses had sustained a direct physical loss. The inherent qualities of the Chinese drywall created a physical loss to the home and the drywall had to be removed and replaced.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Construction Defect Not an Occurrence in Ohio
November 7, 2012 — CDJ Staff
The Ohio Supreme Court has concluded that claims of defective construction or workmanship are not an occurrence under a general liability policy. The court looked at appellate decisions and concluded that CGL policies are not intended to insure against risks under the control and management of the insured. These risks should instead be mitigated with performance bonds.
The question was raised in the case Westfield Ins. Co. v. Custom Agri Systems, Inc. The Sixth District Court of Ohio concluded it was an “open question under Ohio law whether a CGL policy covers defective construction claims.” Westfield filed a motion, granted by the Sixth Circuit, to certify the question to the state Supreme Court. The Sixth Court additionally found that the contractual liability exclusion barred coverage in the case, issues a summary judgment to Westfield.
Read the full story…
Water Drainage Case Lacks Standing
March 28, 2012 — CDJ Staff
The Texas Court of Appeals has ruled in the case La Tierra de Simmons Familia Ltd. V. Main Event Entertainment, LP. The trial court had found for Main Event. On appeal, the court threw out some of the grounds on which the trial court had reached its decision.
The case involved two commercial lots in northwest Austin, Texas. The uphill tract (Phase III of the Anderson Arbor development) diverts its runoff onto the lower tract (the “Ballard tract”). The owners of the Ballard tract claim that “the drainage system was designed or constructed in a manner that has damaged and continues to damage the Ballard tract.”
Both tracts have undergone changes of ownership since the construction of the drainage system in 2004. At the time the drainage system was constructed, the parcel was owned by Sears Roebuck and Co. Sears later sold the property. Main Event Entertainment is the current tenant. Likewise, the Ballard tract was previously owned by the Ballard Estate which sold the property to La Tierra on an “as is” basis in 2007.
After La Tierra bought the Ballard tract, La Tierra’s engineer “witnessed and videotaped what he described as ‘flooding’ on the Ballard tract caused by storm water discharge from the Anderson Arbor drainage system during a rainfall event.” La Tierra determined that an adequate drainage system would cost about $204,000. Development plans were put on hold.
La Tierra sued Main Event and various other parties associated with the uphill tract, seeking “actual damages for (1) decrease and loss in rental income due to delay in obtaining the development permit, (2) interest on carrying costs during that time period, (3) the cost to build a water conveyance system on the Ballard tract, (4) engineering fees incurred to redesign the water conveyance system, (5) unspecified out-of-pocket real estate expenses, and (6) property devaluation occasioned by the need to construct an expensive water conveyance system.” The trial court never reached these claims, ruling instead that La Tierra lacked standing, that its claims were barred under the statute of limitations, and that there was no evidence of damage.
La Tierra appealed, arguing that “(1) the summary-judgment evidence does not conclusively establish that property damage claims accrued or were discovered prior to September 11, 2007, which is within the limitations period and was after La Tierra purchased the property; (2) even if the property was damaged before La Tierra acquired ownership of the Ballard tract, standing exists based on the assignments of interest from the Ballard Estate heirs, and the discovery rule tolls limitations until the injury was discovered on September 11, 2007; (3) limitations does not bar La Tierra's request for injunctive relief; (4) La Tierra's water code claim against Main Event and M.E.E.P. is viable based on their control over the drainage system, which makes them necessary and indispensable parties for injunctive relief; (5) La Tierra presented more than a scintilla of evidence to raise a fact issue on damages, causation, and other essential elements of its causes of action; and (6) the trial court abused its discretion when it sustained the defendants' objections to La Tierra's summary-judgment evidence.”
The appeals court concluded that La Tierra’s second claim was irrelevant to standing, as La Tierra “obtained assignments from the Ballard Estate heirs ? nearly one year after the lawsuit was initially filed.” Nor did the court accept their first point. The water system had been operating unaltered since January, 2004, with monthly maintenance and inspection to maintain its designed operation. Further, a feasibility report La Tierra received stated that “over sixteen acres drain into those ponds, and thus onto this site.” The court noted that “the underlying facts giving rise to a cause of action were known before La Tierra acquired ownership of the Ballard tract.”
The court concluded that the drainage issue is a permanent injury, but that it “accrued before La Tierra acquired an ownership interest in the property.” As La Tierra has standing, the appeals court ruled that it was improper for the trial court to rule on the issues. The appeals court dismissed the questions of whether the case was barred under the statute of limitation and also the question of whether or not La Tierra had damages.
As the issue of standing would not allow La Tierra to bring the suit, the appeals court found for the defendants, dismissing the case for this single reason, and otherwise affirming the ruling of the lower court.
Read the court’s decision…
Supreme Court of Oregon Affirms Decision in Abraham v. T. Henry Construction, et al.
April 20, 2011 — April 20, 2011 Beverley BevenFlorez - Construction Defect Journal
After reviewing the decision in Abraham v. T. Henry Construction, et al., the Oregon Supreme Court affirmed that a tort claim for property damage arising from construction defects may exist even when the homeowner and the builder are in a contractual relationship.
When the case was initially filed, the plaintiffs alleged breach of contract and negligence. The defendants moved for summary judgment arguing that one, the claim was barred by the six-year statute of limitations and two, no special relationship (such as one between a doctor and patient) existed. The court agreed with the defendants. However, the Court of Appeals while affirming the trial court’s decision on breach of contract reversed the decision on negligence. The Court of Appeals stated that an administrative or statute rule could establish a standard of care independent from the contract.
The Oregon Supreme Court gave an example of cases where a tort claim could exist when a contract is present: “If an individual and a contractor enter into a contract to build a house, which provides that the contractor will install only copper pipe, but the contractor installs PVC pipe instead (assuming both kinds of pipe comply with the building code and the use of either would be consistent with the standard of care expected of contractors), that failure would be a breach of contract only. […] If the failure to install the copper pipe caused a reduction in the value of the house, the plaintiff would be able to recover that amount in an action for breach of contract. […] On the other hand, if the contractor installed the PVC pipe in a defective manner and those pipes therefore leaked, causing property damage to the house, the homeowner would have claims in both contract and tort. […] In those circumstances, the obligation to install copper instead of PVC pipe is purely contractual; the manner of installing the pipe, however, implicates both contract and tort because of the foreseeable risk of property damage that can result from improperly installed pipes.”
Read the court’s decision…
Defense for Additional Insured Not Barred By Sole Negligence Provision
August 11, 2011 — Tred Eyerly, Insurance Law Hawaii
A general contractor was entitled to a defense as an additional insured when the underlying complaint did not allege it was solely negligent. A-1 Roofing Co. v. Navigators Ins. Co., 2011 Ill. App. LEXIS 656 (Ill. Ct. App. June 24, 2011).
A-1 was the general contractor for a roof resurfacing job at a high school. Jack Frost Iron Works Inc. (“Frost”) was one of A-1’s subcontractors. Frost had a CGL policy with Navigators Insurance Company under which A-1 was an additional insured.
An employee of Frost’s subcontractor Midwest Sheet Metal Inc. was killed at the job site when a boom-lift he was operating flipped over. The boom-lift had been leased by another Frost subcontractor, Bakes Steel Erectors, Inc. (BSE). The deceased's estate filed suit against A-1, BSE and two other defendants.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
No Coverage For Construction Defects When Complaint Alleges Contractual Damages
September 1, 2011 — Tred Eyerley, Insurance Law Hawaii
The underlying plaintiff’s allegations contended the contractor was in breach of contract for construction defects caused in building her home. Accordingly, the court found no coverage.See Nat’l Builders and Contractors Ins. Co. v. Slocum, 2011 U.S. Dist. LEXIS 81694 (S.D. Miss. July 26, 2011).
Slocum Construction LLC sold a home it built to Laura Peterson. Subsequently, Peterson filed suit, alleging a breach of the contract and seeking rescission and cancellation of the contract. Peterson further alleged at least thirty-three specific defects in the construction of the house.
Slocum tendered to its insurer, National Builders and Contractors Insurance Company (NBCI). NBCI filed suit for a declaratory judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Construction Defect Not a RICO Case, Says Court
August 4, 2011 — CDJ Staff
The US District Court of North Carolina has rejected an attempt by a homeowner to restart her construction defect claim by turning it into a RICO lawsuit. Linda Sharp, the plaintiff in the case of Sharp v. Town of Kitty Hawk, attempted to amend a claim under the Racketeer Influenced and Corrupt Organizations Act (RICO) and argued that her case belonged in the federal courts.
Ms. Sharp sued in November, 2010 claiming construction defects. She sued in federal court, although the court noted that as she and most of the defendants are citizens of North Carolina, the state court would have been the appropriate jurisdiction. Further, the court noted that one federal claim Sharp made was dismissed with prejudice, leaving only the state law claims. These the court dismissed without prejudice, declining to exercise jurisdiction over North Carolina law.
After the dismissal, Ms. Sharp attempted to amend her complaint after the deadline. To do so, according to the court, she would be required to obtain consent from defendants or leave of the court. She did neither.
In his opinion, Judge W. Earl Britt rejected her motion for leave to amend. He also granted the defendants’ motion to dismiss. The clerk was directed to close the case.
Read the court’s decision…