Micropiles for bad soil: a Tarheel victory
March 14, 2011 — Original article by by Melissa Brumback on March 14, 2011
Despite foundation challenges, construction is almost complete on the expansion at University of North Carolina’s Kenan stadium. The project started with a deep foundation system from design-build contractor GeoStructures. Known as the Carolina Student-Athlete Center for Excellence, the addition was built on a parcel with a knotty mix of fill soils, subsurface boulders and varying depths to rock. To achieve uniform foundation support, GeoStructures designed a Micropile system (also known as a Mini pile system) which could be drilled into the variable ground conditions.
Read the full story...
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl law.com.
Texas “your work” exclusion
January 6, 2012 — CDCoverage.com
In American Home Assurance Co. v. Cat Tech, L.L.C., No. 10-20499 (5th Cir. Oct. 5, 2011), claimant Ergon hired insured Cat Tech to perform service on a reactor at Ergon’s refinery. During a start-up of the reactor after Cat Tech had completed its work, the reactor suffered damage. Cat Tech performed additional service and repairs. However, again upon start-up of the reactor, it suffered additional damage. Ergon hired another contractor to repair the reactor. Ergon initiated arbitration proceedings against Cat Tech. Cat Tech’s CGL insurer American Home defended Cat Tech against the Ergon arbitration under a reservation of rights.
Read the full story…
Reprinted courtesy of CDCoverage.com
Will They Blow It Up?
March 28, 2012 — CDJ Staff
The issues concerning the Harmon Towers building in Las Vegas continue to make their way through the courts. As we noted in a previous piece, Cook County building officials stated that the building could be a hazard if Las Vegas were struck by an earthquake. The question of whether the building will continue to stand is just one of the issues in front of a judge.
MGM Resorts International argued at a March 13 hearing for permission to implode the Harmon hotel building. They claim that more than 1,700 defects have been discovered in the building and that the building is a public safety hazard. Arguing against demolition, Perini Building Company, the general contractor for the hotel, and its subcontractors are claiming that imploding the building would destroy evidence and prejudice juries in the ongoing construction defect claims. They claim that MGM Resorts wishes to abandon the building due to the economic slowdown. Perini Corp, the contractor for the project, claims that the building can be fixed. Perini claims that MGM’s position in the construction trial would be improved if the building is demolished.
After Judge Elizabeth Gonzalez heard the four days of testimony on the Harmon Towers building and whether it should be demolished, she scheduled more testimony, with two days in April and an entire week in July. Judge Gonzalez will be deciding whether the building will be torn down, imploded, or left in place.
Read the full story…
Read the full story…
Construction Company Head Pleads Guilty to Insurance and Tax Fraud
December 20, 2012 — CDJ Staff
The former head of Orients Construction Company and of Melrose Construciton Company, Herlindo Garcia-Merlos, has entered a guilty plea to charges that the gave false informoation to his insurer, New Jersey Manufacturers Insurance Group, for more than three years in order to lower his workers compensation payments. Mr. Garcia-Merlos was able to underpay by more than $315,000 as a result of this deception.
Mr. Garcia-Merlos additionally failed to file tax returns for his companies and underreported his wages on his own tax returns. The State of New Jersey is seeking an eight-year prison term and restitution of more than $400,000.
Read the full story…
Wisconsin “property damage” caused by an “occurrence.”
April 4, 2011 — April 4, 2011 in CDCoverage.com
In American Family Mut. Ins. Co. v. American Girl, Inc., 673 N.W.2d 65 (Wis. 2004), the insured general contractor was hired by the owner to design and build a warehouse on the owner s property. The general contractor hired a soil engineer to do a soil analysis and make site preparation recommendations. The soil engineer determined that the soil conditions were poor and recommended a compression process which the general contractor followed. After the warehouse was completed and the owner took possession, excessive soil settlement caused the foundation to sink which in turn caused structural damage to the warehouse. The warehouse had to be torn down.
Read the full story...
Reprinted courtesy of CDCoverage.com
Save A Legal Fee? Sometimes You Better Talk With Your Construction Attorney
May 10, 2012 — Douglas Reiser, Builders Counsel
I love writing this column, because I think it’s refreshing for contractors to hear that they don’t always need an attorney. Today’s post is the “Un-Save a Legal Fee” because I want to point out a specific illustration of when you definitely need your attorney. Using a construction contract template can be fine, but you always need to consider its application to each project ? or it could bite you in the rear.
Seattle attorney Paul Cressman published a prime depiction of bad contract management, last week. A Florida appellate court struck down a general contractor’s “pay if paid” clause when it became ambiguous because of some incorporated language from its prime contract. Specifically, a clause in the prime contract required the general contractor to pay all subcontractors before receiving payment from the owner, while the general contractor’s “pay if paid” clause required its subcontractors to wait for payment until it arrived from the owner.
Read the full story…
Businesspeople to Nevada: Revoke the Construction Defect Laws
March 1, 2012 — CDJ Staff
The Nevada chapter of the National Federation of Independent Businesses has said that Nevada’s construction defect and minimum wage laws are hampering job growth. The organization conducted a survey, and although only about two percent of the members responded, they passed the opinions of the group on to Governor Brian Sandoval. Sandoval has said, according to the report by Fox News Reno, that he wants the state to be more business friendly. He supports reforms to Nevada’s construction defect laws, saying that he’d “like to see some reform” on the issue of mandatory attorney’s fees.
Randi Thompson, the spokesperson for the Nevada chapter of the National Federation of Independent Businesses, said that members of her organization would like to see current Nevada construction defect law revoked. She described current law as “driven towards lawyers and not toward protecting consumers.”
Read the full story…
Kansas Man Caught for Construction Scam in Virginia
December 20, 2012 — CDJ Staff
A Virginia court sent charges of construction fraud against a Kansas man to a grand jury. Larry Foster visited homes in Bedford County, Virginia, tested the water, and told homeowners that they needed new water filtration systems. The homeowners paid, but Mr. Foster never delivered. One homeowner who testified paid him $1,690. Another paid even more, giving $3,090 to Mr. Foster. In order to dupe his victims, Foster used the address of a chiropractor as a business address, unbeknownst to the actual business there.. He is wanted for charges in other states as well.
Read the full story…
Building Boom Leads to Construction Defect Cases
August 2, 2012 — CDJ Staff
Professor Evan McKenzie of the University of Illinois at Chicago says that rise of construction defect litigation in the Las Vegas area followed the same pattern it did in other places, according to an article in the Las Vegas Review Journal. “Step one,” according to Professor McKenzie, “there was this enormous growth in construction. Then these attorneys began to swarm in from all over, especially Southern California.” McKenzie noted that during a building boom, construction “outpaces the ability of building inspectors to do their job.”
But, despite his contention that “rapid growth in housing stock” leads to “shoddy construction,” another problem of growth was that “eventually there were too many lawyers chasing too many condominium complexes and subdivisions.” What came next was that “attorneys start coming up with cases that really aren’t good cases.” It’s in the interest of these attorneys that HOA boards sue.
Read the full story…
Condominium Communities Must Complete Construction Defect Repairs, Says FHA
July 10, 2012 — CDJ Staff
Laura K. Sanchez of HindmanSanchez writes that the FHA “will not approve or recertify” any condominium community “where there are any pending or incomplete repairs within the community which are a result of a construction defect claim, regardless of whether the litigation has been resolved and regardless of whether there are funds in the bank paid by the developer to pay for the repairs.” The FHA notes that failure to complete or fund repairs could “put FHA insured loans at risk.” Communities must disclose all maintenance and repair issues to the FHA. Sanchez notes that the FHA has stated that incomplete repairs could put FHA-insured loans at risk.
Read the full story…
Largest Per Unit Settlement Ever in California Construction Defect Case?
October 28, 2011 — CDJ Staff
BusinessWire reports that the Chelsea Court Homeowners Association has settled their construction defect case for $5.4 million. That works out to $169,000 per unit, which BusinessWire describes as “California’s largest per-unit recovery known to be on record to date.”
Most of the money in the settlement is coming from insurance companies for the builder and thirteen subcontractors. Issues included roof and window leaks, deck failures, and unsafe walkways.
Read the full story...
Windows and Lawsuits Fly at W Hotel
July 5, 2011 — CDJ Staff
An Austin, Texas lawyer has filed a lawsuit against Starwood Hotels and Resorts, the operator of the W Hotel Austin, after two people were struck by glass which fell from the hotel’s balconies. YNN in Austin reports that the hotel has been closed indefinitely as construction workers removed panels. An additional three panels fell before work started. Randy Howry, the lawyer representing the injured parties, notes that in May glass falling from the W Hotel in Atlanta killed one woman and injured another. “Seventeen days pass and we put them on notice, our clients have put them on notice, yet nothing has been done an only after the glass fell yesterday did they do something about it,” YNN quotes Howry.
The hotel released a statement that they will be replacing all of the balcony glass to ensure safety for their guests and the general public. They relocated all hotel guests and coordinated with Austin officials to close adjacent sidewalks and roads. The statement identifies the firms involved with the design and construction of the balconies.
Read the full story …
Bar to Raise on Green Standard
November 7, 2012 — CDJ Staff
Next June, members of the U.S. Green Building Council will be voting on changes to the LEED green building standard. “The bar is getting raised,” said Navad Malin of BuildingGreen, a consulting and publishing firm, in an article in USA Today. Under the proposed guidelines, builders would have to project energy and water use for five years as part of the certification process. However, if the occupants aren’t as green as the builders anticipated, the buildings will not lose their certification.
The new rules will include higher energy standards, award points for avoiding potentially hazardous materials, and even determine what kind of plumbing items can be used.
Read the full story…
Arizona Court of Appeals Decision in $8.475 Million Construction Defect Class Action Suit
May 9, 2011 — May 9, 2011 Beverley BevenFlorez - Construction Defect Journal
In the case of Leflet v. Fire (Ariz. App., 2011), which involved an $8.475 million settlement in a construction defect class action suit, the question put forth to the Appeals court was “whether an insured and an insurer can join in a Morris agreement that avoids the primary insurer’s obligation to pay policy limits and passes liability in excess of those limits on to other insurers.” The Appeals court provided several reasons for their decision to affirm the validity of the settlement agreement as to the Non-Participatory Insurers (NPIs) and to vacate and remand the attorney fee awards.
First, the Appeals court stated, “The settlement agreement is not a compliant Morris agreement and provides no basis for claims against the NPIs.” They conclude, “Appellants attempt to avoid the doctrinal underpinnings of Morris by arguing that ‘the cooperation clause did not prohibit Hancock from assigning its rights to anyone, including Appellants.’ This narrow reading of the cooperation clause ignores the fact that Hancock did not merely assign its rights — it assigned its rights after stipulating to an $8.475 million judgment that neither it nor its Direct Insurers could ever be liable to pay. Neither Morris nor any other case defines such conduct as actual ‘cooperation’—rather, Morris simply defines limited circumstances in which an insured is relieved of its duty to cooperate. Because Morris agreements are fraught with risk of abuse, a settlement that mimics Morris in form but does not find support in the legal and economic realities that gave rise to that decision is both unenforceable and offensive to the policy’s cooperation clause.”
The Appeals court further concluded that “even if the agreement had qualified under Morris, plaintiffs did not provide the required notice to the NPIs.” The court continued, “Because an insurer who defends under a reservation of rights is always aware of the possibility of a Morris agreement, the mere threat of Morris in the course of settlement negotiations does not constitute sufficient notice. Instead, the insurer must be made aware that it may waive its reservation of rights and provide an unqualified defense, or defend solely on coverage and reasonableness grounds against the judgment resulting from the Morris agreement. The NPIs were not given the protections of this choice before the agreement was entered, and therefore can face no liability for the resulting stipulated judgment.”
Next, the Appeals court declared that “the trial court abused its discretion in awarding attorney’s fees under A.R.S § 12-341.” The Appeals court reasoned, “In this case, the NPIs prevailed in their attack on the settlement. But the litigation did not test the merits of their coverage defenses or the reasonableness of the settlement amount. And Plaintiffs never sued the NPIs, either in their own right or as the assignees of Hancock. Rather, the NPIs intervened to test the conceptual validity of the settlement agreement (to which they were not parties) before such an action could commence. In these circumstances, though it might be appropriate to offset a fee award against some future recovery by the Plaintiff Leflet v. Fire (Ariz. App., 2011) class, the purposes of A.R.S. § 12-341.01 would not be served by an award of fees against them jointly and severally. We therefore conclude that the trial court abused its discretion in awarding fees against Plaintiffs ‘jointly and severally.’”
The Appeals court made the following conclusion: “we affirm the judgment of the trial court concerning the validity of the settlement agreement as to the NPIs. We vacate and remand the award of attorney’s fees. In our discretion, we decline to award the NPIs the attorney’s fees they have requested on appeal pursuant to A.R.S. § 12-341.01(A).”
Read the court’s decision…
Condo Board May Be Negligent for not Filing Construction Defect Suit in a Timely Fashion
December 9, 2011 — CDJ Staff
The Maryland Court of Special Appeals has ruled that condominium association boards have a duty to “properly pursue any claims,” overturning the decision of a lower court that said that it had no legal duty to file suit. Tom Schild, writing at Marylandcondominiumlaw.net, writes about Greenstein v. Avalon Courts Six Condominium, Inc.
In this case, the condominium board waited six years after residents complained about water intrusion problems before suing the developer. The court ruled that the suit could not be filed, as the statute of limitations was only three years. After residents were assessed for the repairs, homeowners sued the board, arguing that their delay lead to the need for the special assessment.
After overturning the decision, the Court of Special Appeals has asked the trial court to review the negligence claim.
Read the full story…
MGM Seeks to Demolish Harmon Towers
September 1, 2011 — CJD Staff
Citing public safety concerns and the cost of repair, MGM Resorts International is seeking to demolish the unfinished hotel tower. The company has a few hurdles to go through before they start laying the charges to implode the structure. Any plans would have to be approved by not only Clark County officials, but also the district court has an order blocking any activity during litigation between MGM and the general contractor on the project, Perini Building Company.
Architectural Record reports that MGM states it would take “approximately 18 months to conduct test and come up with an approved, permitted design to fix the Harmon.” MGM feels that repairs would then take another two to three years. Perini contends that they could “provide stamped drawings detailing all necessary repairs within three months.” They attribute MGM’s desire to demolish the building as “buyer’s remorse.”
Read the full story…
Coverage Rejected Under Owned Property and Alienated Property Exclusions
June 6, 2011 —
Tred R. Eyerly,
Insurance Law HawaiiThe insured’s request for a defense when sued in a construction defect action was denied under the owned property exclusion and the alienated property exclusion in1777 Lafayette Partners v. Golden Gate Ins. Co., 2011 U.S. Dist. LEXIS 48562 (N.D. Cal. April 29, 2011).
In 1999, Lafayette Partners purchased an abandoned walnut processing factory to convert into living and working units. The property was developed into a rental property from 2000-2001, and thereafter rented. In May 2003, Lafayette Partners entered into a sales agreement with Wolff Enterprises LLC. The sale closed in February 2005. Wolff then converted the rental units into condominiums.
In December 2007, the Walnut Factory Owners Association sued Wolff for construction defects. In Lafayette Partners was added to the suit in 2009. The suit alleged a variety of defective conditions, including the roofs, exteriors, windows, electrical , plumbing, and mechanical components and systems.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Remodels Replace Construction in Redding
September 9, 2011 — CDJ Staff
The Record Searchlight reports that while new construction is down in Redding, California, residential and commercial remodel permits are up 17 percent. By August 2010, there had been 63 housing and commercial business starts in Redding, while this year has seen only 15.
One such remodel, that of Parkview Market, will cost about $201,000. Safeway is planning on two $80,000 remodels of its grocery stores in Redding. In all, the 150 building permits for remodels are worth a total of $2.8 million.
Read the full story…