BERT HOWE
  • Nationwide: (800) 482-1822    
    condominiums Everett Washington parking structure Everett Washington retail construction Everett Washington mid-rise construction Everett Washington institutional building Everett Washington production housing Everett Washington high-rise construction Everett Washington landscaping construction Everett Washington custom home Everett Washington structural steel construction Everett Washington hospital construction Everett Washington housing Everett Washington tract home Everett Washington custom homes Everett Washington concrete tilt-up Everett Washington Medical building Everett Washington office building Everett Washington industrial building Everett Washington multi family housing Everett Washington casino resort Everett Washington low-income housing Everett Washington condominium Everett Washington
    Arrange No Cost Consultation
    Construction Expert Witness Builders Information
    Everett, Washington

    Washington Builders Right To Repair Current Law Summary:

    Current Law Summary: (SB 5536) The legislature passed a contractor protection bill that reduces contractors' exposure to lawsuits to six years from 12, and gives builders seven "affirmative defenses" to counter defect complaints from homeowners. Claimant must provide notice no later than 45 days before filing action; within 21 days of notice of claim, "construction professional" must serve response; claimant must accept or reject inspection proposal or settlement offer within 30 days; within 14 days following inspection, construction pro must serve written offer to remedy/compromise/settle; claimant can reject all offers; statutes of limitations are tolled until 60 days after period of time during which filing of action is barred under section 3 of the act. This law applies to single-family dwellings and condos.


    Construction Expert Witness Contractors Licensing
    Guidelines Everett Washington

    A license is required for plumbing, and electrical trades. Businesses must register with the Secretary of State.


    Construction Expert Witness Contractors Building Industry
    Association Directory
    North Peninsula Builders Association
    Local # 4927
    PO Box 748
    Port Angeles, WA 98362


    Jefferson County Home Builders Association
    Local # 4947
    PO Box 1399
    Port Hadlock, WA 98339
    http://www.jeffcohomebuilders.com

    Home Builders Association of Spokane
    Local # 4966
    5813 E 4th Ave Ste 201
    Spokane, WA 99212
    http://www.shba.com

    MBuilders Association of King & Snohomish Counties
    Local # 4955
    335 116th Ave SE
    Bellevue, WA 98004
    http://www.masterbuildersinfo.com

    Home Builders Association of Kitsap County
    Local # 4944
    5251 Auto Ctr Way
    Bremerton, WA 98312
    http://www.kitsaphba.com

    Home Builders Association of North Central
    Local # 4957
    PO Box 2065
    Wenatchee, WA 98801
    http://www.nchba.cc

    Skagit-Island Counties Builders Association
    Local # 4960
    15571-A Peterson Rd
    Burlington, WA 98233
    http://www.sicba.org


    Construction Expert Witness News and Information
    For Everett Washington

    Plaintiff Not Entitled to Further Damages over Defective Decking

    Colorado Court of Appeals holds that insurance companies owe duty of prompt and effective communication to claimants and repair subcontractors

    Unfinished Building Projects Litter Miami

    New Web Site Tracks Settled Construction Defect Claims

    Ohio “property damage” caused by an “occurrence.”

    OSHA Cites Construction Firm for Safety Violations

    District Court Awards Summary Judgment to Insurance Firm in Framing Case

    SB800 Cases Approach the Courts

    Construction Defects Lead to Demolition

    Washington Court of Appeals Upholds Standard of Repose in Fruit Warehouse Case

    The Complete and Accepted Work Doctrine and Construction Defects

    California Bill Would Notify Homeowners on Construction Defect Options

    Fire Reveals Defects, Appeals Court Affirms Judgment against Builder

    Water District Denied New Trial in Construction Defect Claim

    Good and Bad News on Construction Employment

    Timing of Insured’s SIR Payment Has No Effect on Non-Participating Insurer’s Equitable Contribution to Co-Insurer

    Harsh New Time Limits on Construction Defect Claims

    South Carolina Contractors Regain General Liability Coverage

    Water Damage Covered Under Efficient Proximate Cause Doctrine

    Homeowner may pursue negligence claim for construction defect, Oregon Supreme Court holds

    Kentucky Court Upholds Arbitration Award, Denies Appeal

    In Re Golba: The Knaubs v. Golba and Rollison, Debtors

    Texas Court of Appeals Conditionally Grant Petition for Writ of Mandamus to Anderson

    Construction Defects in Home a Breach of Contract

    Tampa Condo Owners Allege Defects

    Water Drainage Case Lacks Standing

    Anti-Assignment Provision Unenforceable in Kentucky

    Application of Efficient Proximate Cause Doctrine Supports Coverage

    Statute of Limitations Upheld in Construction Defect Case

    Washington Court Limits Lien Rights of Construction Managers

    Florida trigger

    Virginia Chinese Drywall “property damage” caused by an “occurrence” and number of “occurrences”

    Mississippi exclusions j(5) and j(6) “that particular part”

    Judge Rejects Extrapolation, Harmon Tower to Remain Standing

    “Other Insurance” and Indemnity Provisions Determine Which Insurer Must Cover

    Florida Law: Defects in Infrastructure Improvements Not Covered in Home Construction Warranties

    Cleveland Condo Board Says Construction Defects Caused Leaks

    Ensuing Loss Provision Does Not Salvage Coverage

    Construction Defects and Contractor-Owners

    Driver’s Death May Be Due to Construction Defect

    Death of Construction Defect Lawyer Ruled a Suicide

    There is No Non-Delegable Duty on the Part of Residential Builders in Colorado

    Pipes May Be Defective, But Owners Lack Standing

    Contractor Sues Supplier over Defective Products

    New Construction Laws, New Forms in California

    Williams v. Athletic Field: Hugely Important Lien Case Argued Before Supreme Court

    Contractor Underpaid Workers, Pocketed the Difference

    Celebrities Lose Case in Construction Defect Arbitration

    Kansas Man Caught for Construction Scam in Virginia

    Guilty Pleas Draw Renewed Interest In Nevada’s Construction Defect Laws

    Ohio Adopts Energy-Efficient Building Code

    Massachusetts Couple Seek to Recuse Judge in Construction Defect Case

    Condo Board May Be Negligent for not Filing Construction Defect Suit in a Timely Fashion

    West Hollywood Building: Historic Building May Be Defective

    Hospital Construction Firm Settles Defect Claim for $1.1 Million

    Texas res judicata and co-insurer defense costs contribution

    MGM Seeks to Demolish Harmon Towers

    Insurer Has Duty to Disclose Insured's Interest In Obtaining Written Explanation of Arbitration Award

    Construction Job Opening Rise in October

    Bound by Group Builders, Federal District Court Finds No Occurrence

    School District Settles Construction Lawsuit

    Homebuilding on the Rise in Nation’s Capitol

    Policing Those Subcontractors: It Might Take Extra Effort To Be An Additional Insured

    Contractors Admit Involvement in Kickbacks

    Construction Defects Are Occurrences, Says Georgia Supreme Court

    Steps to Defending against Construction Defect Lawsuits

    After $15 Million Settlement, Association Gets $7.7 Million From Additional Subcontractor

    Arizona Homeowners Must Give Notice of Construction Defect Claims

    After Breaching its Duty to Defend, Insurer Must Indemnify

    A Performance-Based Energy Code in Seattle: Will It Save Existing Buildings?

    The King of Construction Defect Scams

    Arbitrator May Use Own Discretion in Consolidating Construction Defect Cases

    Follow Up on Continental Western v. Shay Construction

    Colorado Court of Appeals Rejects Retroactive Application of C.R.S. § 13-20-808.

    California Posts Nation’s Largest Gain in Construction Jobs

    Homebuilders Go Green in Response to Homebuyer Demand

    Construction Defect Journal Marks First Anniversary

    “Details Matter” is the Foundation in a Texas Construction Defect Suit

    Building Boom Leads to Construction Defect Cases

    Remodels Replace Construction in Redding

    Contractor Convicted of Additional Fraud

    Late Filing Contractor Barred from Involving Subcontractors in Construction Defect Claim

    Legislatures Shouldn’t Try to Do the Courts’ Job

    Contractor Liable for Soils Settlement in Construction Defect Suit

    The U.S. Tenth Circuit Court of Appeals Rules on Greystone

    Homeowners Must Comply with Arbitration over Construction Defects

    Texas exclusions j(5) and j(6).

    Battle of “Other Insurance” Clauses

    Continuous Trigger of Coverage Adopted for Loss Under First Party Policy

    Record-Setting Construction in Fargo
    Corporate Profile

    EVERETT WASHINGTON CONSTRUCTION EXPERT WITNESS
    DIRECTORY AND CAPABILITIES

    Leveraging from more than 5500 construction defect and claims related expert witness designations, the Everett, Washington Construction Expert Witness Group provides a wide range of trial support and consulting services to Everett's most acknowledged construction practice groups, CGL carriers, builders, owners, and public agencies. Drawing from a diverse pool of construction and design professionals, BHA is able to simultaneously analyze complex claims from the perspective of design, engineering, cost, or standard of care.

    Construction Expert Witness News & Info
    Everett, Washington

    One World Trade Center Due to Be America’s Tallest and World’s Priciest

    February 10, 2012 — CDJ Staff

    As One World Trade Center rises, so does the price tag. After construction delays and cost overruns, the cost of the building at the site of the September 11 attacks has risen to $3.8 billion. Part of the expense of the skyscraper is the heavily reinforced base of the building. The elevator shafts are also heavily reinforced, all part of guarding against future terrorist attacks.

    In comparison, the world’s tallest tower, the Burj Khalifa in Dubai, cost only $1.5 billion, less than half the cost of One World Trade Center. As a result, the Port Authority does not see the building as being profitable in near future. In order to fund it, the agency is raising tolls on bridge and tunnel traffic.

    Currently, about the half the unfinished building is leased. Construction is expected to conclude in 2013.

    Read the full story…


    Foundation Arbitration Doesn’t Preclude Suing Over Cracks

    March 28, 2012 — CDJ Staff

    The Louisiana Court of Appeals has reversed the decision of a lower court, allowing a construction defect case to go through. In Greer v. Town Construction Company, the Greers hired Town Construction to build a home in Baton Rouge. The business relationship went sour, with disputes over “costs, change orders, workmanship, and timeliness issues.”

    Town Construction filed an arbitration claim for the unpaid contract balance. In the counterclaim, the Greers made claims of mold and mildew problems, and wall cracks that they attributed to a “structural defect in the foundation.” In arbitration, Town Construction was awarded the full contract balance plus extra costs and interest, while the Greers were awarded for their structural claims.

    Three years later, the Greers found additional cracks and filed a suit against Town Construction. Town Construction argued that the Greer’s lawsuit should be dismissed, as the claims had already been through the arbitration process. The district court agreed with Town Construction and dismissed the suit.

    The appeals court noted that the Greers would have no ground for a suit if the arbitration was a “valid and final judgment,” and went on to note that there was no evidence in the trial record that the arbitration met this qualification. The court noted that although it was clear that both parties had agreed to the decisions of the arbiter, under Louisiana law, arbitration is not final until it has been “rendered by a court with jurisdiction over subject mater and over parties.”

    The court remanded the case to the lower court, noting that “the district court is obligated to first determine whether a valid arbitration award is in existence and had been confirmed before considering the merits of the exception. The court noted that their decision “should not be read to express any opinion as to the merits of the claims or as to the propriety of damages sought in the Greer’s lawsuit.”

    Read the court’s decision…


    Lockton Expands Construction and Design Team

    July 19, 2011 — CDJ Staff

    Lockton Companies, LLC, the largest privately held independent insurance broker, has announced that it is expanding its construction and design team with the hiring of Karen Erger and Tom Miller.

    Ms. Erger will provide professional liability practice management, loss prevention, contract and complex claims management consulting services to Lockton's architectural, engineering and construction clients in her role as Vice President, Director of Practice Management. Her background includes construction litigation at a leading construction law firm, professional liability claims defense and claims consulting for major professional liability underwriters.

    Miller joins Lockton as a Senior Vice President within the Design and Construction Unit. His role will be dedicated to serving the needs of engineering, architecture and construction firms performing services around the globe. He has spent more than 15 years concentrating on professional liability for design professionals and contractors in multiple roles. He previously managed the professional liability underwriting of one of the largest construction insurers and has developed numerous manuscript insurance products as well as focused on strategic planning to enhance business unit opportunities.

    Read the full story…


    Damage During Roof Repairs Account for Three Occurrences

    August 2, 2012 — Tred Eyerly, Insurance Law Hawaii

    Southgate Gardens Condominium had buildings damaged by Hurricane Wilma in 2005. See Mid-Continent Cas. Co. v. Basedeo, 2012 U.S. App. LEXIS 11864 (11th Cir. June 12, 2012). First State Development Corporation was hired by Southgate to do repairs.

    On November 1, 2005, First State completed tarping on the buildings. Thereafter, on November 11, 2005, First State contracted with Southgate to remove and replace the roofs of the Southgate Buildings.

    The tarps placed by First State were inadequate and allowed water to enter the unit of Wayne Basdeo and cause damage. Further, when it attached the tarps, First State caused holes to be made in the roofs of buildings, leading to additional damage. First State also left open the mansards (a type of roof which has two slopes on all all sides, but with the lower slope steeper that the upper one). Finally, the peeled-back condition of the roofing allowed rain to enter.

    Basdeo filed a claim with Mid-Continent.

    Read the full story…

    Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com


    Excess Carrier Successfully Appeals Primary Insurer’s Summary Judgment Award

    December 9, 2011 — Tred R. Eyerly, Insurance Law Hawaii

    Although the excess carrier was given inadequate notice of the underlying arbitration, the trial court determined it shared responsibility with the primary carrier for the arbitration award. Finding disputed issues of fact, the Washington Court of Appeals reversed in Am. States Ins. Co. v. Century Surety Co., 2011 Wash. App. LEXIS 2488 (Wash. Ct. App. Oct. 31, 2011).

    The primary insurer, American States, issued two liability policies to Professional Home Builders (PHB), a siding contractor. The policies were for successive years, 1998-1999 and 1999-2000. Each policy had annual limits of $1 million per occurrence. PHB also had a commercial excess liability policy for 1999-2000 with Century Surety Company.

    PHB was sued by Residential Investment Partners (RIP) for construction defects after moisture entered the building envelope, causing decay and damage. Century’s expert determined the decay started before the 1999-2000 policy period.

    RIP and PHB went to arbitration.

    Read the full story…

    Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com


    AFL-CIO Joins in $10 Billion Infrastructure Plan

    June 30, 2011 — CDJ Staff

    The AFL-CIO has announced plans to generate up to $10 billion in funding for infrastructure development, training construction workers, and making buildings more energy efficient, pledging $20 million to retrofit buildings. Bloomberg News reports that union officials made the announcement in Chicago at the Clinton Global Initiative, releasing a statement from Richard Trumka, president of the union, “we, at the AFL-CIO, believe that together, with our partners in business and government, we can profitably invest significant resources to make America more competitive and energy efficient.” A foot injury prevented Mr. Trumka from attending the event.

    The statement also quoted Mark Ayers, president of the Building and Construction Trades Department of the AFL-CIO, “the time is now to become intensely focused on the creation of jobs.”

    Read the full story…


    Alabama “occurrence” and subcontractor work exception to the “your completed work” exclusion

    November 18, 2011 — CDCoverage.com

    In Town & Country Property, LLC v. Amerisure Ins. Co., No. 1100009 (Ala. Oct. 21, 2010), property owner Town & Country contracted with insured general contractor Jones-Williams for the construction of a car dealership. All of the construction work was performed by Jones-Williams subcontractors. After completion, Town & Country sued Jones-Williams for defective construction. Jones-Williams’ CGL insurer Amerisure defended. The case was tried and a judgment was entered against Jones-Williams in favor of Town & Country. After Amerisure denied any obligation to pay the judgment, Town & Country sued Amerisure in a statutory direct action.

    Read the full story…

    Reprinted courtesy of CDCoverage.com.


    Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)

    August 11, 2011 — Melissa Brumback

    For today’s law note, I’m addressing a comment that came to me last week from Dave O’Hern of Miller O’Hern Construction.  Dave writes:

    I am a general contractor doing a fuel tank replacement project for our county. In the specifications there is a spec for a UL 142 tank, on the plans the spec references UL 2085 ? a much more expensive tank. My subcontractor bid the UL 142 tank. The specifications state that the specs and plans are on the same level of precedence.

    The county wants me to furnish the more expensive tank without compensation citing the clause that states the plans and specs are complementary and what is called for by one is binding as if called by all and the most stringent requirement will apply.

    Read the full story…

    Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.


    Federal District Court Continues to Find Construction Defects do Not Arise From An Occurrence

    May 10, 2012 — CDJ Staff

    Coverage for construction defects continues to be hotly contested in Hawaii state and federal courts. In a recent decision, Judge Mollway felt bound to follow the Ninth Circuit’s decision in Burlington Ins. Co. v. Oceanic Design & Constr., Inc., 383 F.3d 940, 944 (9th Cir. 2004), where the court found construction defect claims arise from breach of contract, not from an occurrence. Judge Mollway’s most recent decision on the issue is Illinois Nat. Ins. Co. v. Nordic PCL Constr., Inc., 2012 U.S. Dist. LEXIS 58464 (D. Haw. April 26, 2012).

    Nordic constructed a grocery store for Safeway. In addition to the grocery store, Nordic built a 165-space rooftop parking deck, retail shops and related improvements. After opening for business in 2007, Safeway experienced significant leaks. Safeway demanded that Nordic repair the parking deck. Nordic sent the demand letter to the insurer, who agreed to appoint counsel subject to a reservation of rights.

    Safeway filed suit against Nordic in state court alleging, among other things, breach of contract and negligence. The insurer provided Nordic with a defense, but Nordic hired independent counsel.

    The insurer filed for declaratory relief in federal district court.

    Read the full story…


    Environment Decision May Expand Construction Defect Claims

    August 16, 2012 — CDJ Staff

    Could a California Supreme Court decision on environmental claims have an effect on construction defect cases? Jonathan B. Sokol, a lawyer at Greenberg Glusker argues just that in a post on his firm’s blog. He notes that the California Supreme Court has held that “the ‘all sums” method of allocation applies in California” and that “an insurer cannot limit its liability to just the amount of loss that occurred in its particular policy period.” While his focus is on environmental cases, he says that “the decision could also potentially expand the scope of coverage for construction defect claims and other claims involving continuous and progressive property damage and bodily injury.

    Read the full story…


    Counterpoint: Washington Supreme Court to Rule on Resulting Losses in Insurance Disputes

    September 1, 2011 — Douglas Reiser, Builders Counsel

    This is the fourth installment of posts on Vision One v. Philadelphia Indemnity, a Washington Supreme Court case touching on Washington construction and insurance law. After Williams v. Athletic Field got so much coverage, I wished that I had provided a forum for argument on Builders Counsel. While we await that opinion from the Supreme Court, I decided to let a few good writers have at Vision One here on the blog.  Last week, attorney Chris Carr weighed in. Today, insurance expert David Thayer returns to give his final impression. David provided an initial peak at the case earlier this year. Thanks to both Chris and David for contributing to the debate.

    In August 2011 the Washington Supreme Court will rule on a pair of joined cases that involve critical insurance coverage issues. The outcome of the ruling will impact a large swath of policyholders in Washington State including builders, developers, and homeowners to name a few.

    The cases are Vision One vs. Philadelphia Indemnity Insurance and Sprague vs. Safeco. The Vision one case comes from Division Two of the Appellate Court which overturned a lower court decision in favor the plaintiff, Vision One. Division Two decided that the collapse of a concrete pour during the course of construction did not constitute a resulting loss due to faulty workmanship. They further went on to redefine efficient proximate cause in a way that is harmful to policyholders by broadening rather than narrowing the meaning of exclusionary language in Philadelphia’s Builders Risk Policy.

    Read the full story…

    Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com


    Colorado Statutes of Limitations and Repose, A First Step in Construction Defect Litigation

    December 20, 2012 — CDJ Staff

    Grund Dagner, a law firm operating in Denver and Boulder, Colorado notes on their blog that when defending a construction defect claim, one of their first steps is to determine if the claims are affected by the statutes of limitations or repose, and that they “have had much success raising these defenses with the court before trial.”

    Colorado has a two-year statute of limitations, starting from when the homeowner discovers the defect. Further, Colorado’s statute of repose precludes lawsuits beginning “more than six years after the substantial completion of the improvement to the real property.”

    Grund Dagner notes that they “recently obtained dismissal of claims related to eight of 22 buildings in a condominium project, where the homeowners in those building observed the defects more than two years before the HOA initiated its claims against our client.”

    Read the full story…


    San Diego Construction Defect Claim Settled for $2.3 Million

    July 10, 2012 — CDJ Staff

    The Nauman Law firm has settled the lawsuit by the Latitude Owners Association against CS-Crossroads and others, as reported in the Sacramento Bee from a press release by the firm. The owners at Latitude, a condominium community in San Diego, found that hillside crawl spaces were not property waterproofed, leading to rotting plywood, water intrusion, and pipe leaks. There were additional problems with retrofitted windows and repairs of outside decks. The case was filed in San Diego Superior Court, but settled after multiple mediations.

    Read the full story…


    North Carolina Exclusion j(6) “That Particular Part”

    February 10, 2012 — CDCoverage.com

    In Alliance Mutual Insurance Co. v. Dove, 714 S.E.2d 782 (N.C. Ct. App. 2011), claimant Murphy-Brown hired insured Dove to repair a broken elevator belt in a grain elevator in Murphy-Brown’s feed mill. The elevator was inside a metal duct and, to access the broken belt, Dove had to cut out a section of the duct. After replacing the belt, Dove welded the metal section back to the duct. Immediately after Dove completed the welding, dust inside the duct ignited, causing an explosion in the elevator, resulting in property damage to the elevator and other property. Murphy-Brown sued Dove for negligence seeking damages for the repair and replacement of the elevator, repair and replacement of the other property, increased grain handling costs during the repairs, and loss of use.

    Read the full story…

    Reprinted courtesy of CDCoverage.com


    Court Rules on a Long List of Motions in Illinois National Insurance Co v Nordic PCL

    May 10, 2012 — CDJ Staff

    The case Illinois National Insurance Co. v Nordic PCL, et al. “involves a dispute about whether insurance benefits are available to a general contractor who built structures that allegedly have construction defects. Plaintiffs Illinois National Insurance Company (‘Illinois National’) and National Union Fire Insurance Company of Pittsburgh, PA (‘National Union’) (collectively, the ‘Insurers’), commenced this action for declaratory relief against Defendant Nordic PCL Construction, Inc., f/k/a Nordic Construction, Ltd. ("Nordic"), on August 23, 2011.”

    The court was asked to rule on a long list of motions: “Counterclaim Defendants’ Request for Judicial Notice in Support of Their (1) Motion to Dismiss the Counterclaim and (2) Motion to Strike Portions of the Counterclaim, ECF No. 16 (‘Request for Judicial Notice’); Counterclaim Defendants’ Motion to Dismiss Counterclaim Filed October 24, 2011, ECF No. 14 (‘Motion to Dismiss Counterclaim’); Counterclaim Defendants’ Motion to Strike Portions of the Counterclaim Filed October 24, 2011, ECF No. 15 (‘Motion to Strike’); Third-Party Defendant Marsh USA, Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 33 (‘Marsh’s Motion To Dismiss Or Stay’); Defendant and Third-Party Plaintiff Nordic PCL Construction, Inc., f/k/a Nordic Construction Ltd.’s Substantive Joinder to Third-Party Defendant Marsh USA Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 36 (‘Nordic’s Joinder’); and Third-Party Defendant Marsh USA, Inc.’s Motion for Judgment on the Pleadings on Counts V and VI of Defendant/Third-Party Plaintiff Nordic PCL Construction, Inc.’s Third-Party Complaint, ECF No. 29 (‘Marsh’s Motion for Judgment on the Pleadings’).”

    In result, the court reached the following decisions: “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice to the extent it covers matters relevant to these motions; GRANTS IN PART the Insurers’ Motion to Dismiss Counterclaim, but gives Nordic leave to amend the Counterclaim in certain respects; DENIES the Insurers’ Motion to Strike; DENIES Marsh’s Motion To Dismiss Or Stay and Nordic’s Joinder; and GRANTS Marsh’s Motion for Judgment on the Pleadings.”

    The court provides a bit of background on the case: “This action arises out of alleged construction defects involving two projects on which Nordic acted as the general contractor. Nordic is a defendant in a pending state court action with respect to one of the projects and says it spent more than $400,000 on repairs with respect to the other project. Nordic tendered the defense of the pending state court action to the Insurers and sought reimbursement of the cost of repairs already performed. The Insurers responded by filing this action to determine their rights under the insurance policies issued to Nordic.”

    Furthermore, the court presented a brief procedural history: “The Insurers commenced this declaratory action in this court on August 23, 2011. The Complaint asserts two claims, one seeking a declaration that the Insurers have no duty to provide a defense or indemnification regarding the Safeway Action, the other seeking such a declaration regarding the Moanalua Claims. Along with its Answer, Nordic filed a Counterclaim against the Insurers. The Counterclaim asserts breach of contract, breach of the covenant of good faith and fair dealing, misrepresentations and omissions of material fact, and bad faith, and seeks declaratory relief against the Insurers.”

    The procedural history continues: “Nordic also filed a Third-Party Complaint against Marsh, the broker that had procured the Policies from the Insurers for Nordic. Nordic alleges that it reasonably believed that the Policies would provide completed operations insurance coverage for the types of construction defects alleged in the Safeway Action and Moanalua Claims. The Third-Party Complaint asserts breach of contract, negligence, promissory estoppel, breach of fiduciary duties, implied indemnity, and contribution and equitable subrogation.”

    In conclusion, “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice. With regard to the Insurers’ Motion to Dismiss Counterclaim, the court GRANTS the motion as to Count I (breach of contract), Count II (duty of good faith and fair dealing), Count III (fraudulent and negligent misrepresentation), the portion of Count IV (bad faith) premised on fraud, and Count IV (declaratory relief). The court DENIES the motion as to Count IV (bad faith) that is not premised on fraud. Except with respect to the "occurrence" issue, which the court disposes of here on the merits, and Count V, which concerns only a form of relief, Nordic is given leave to amend its Counterclaim within three weeks of the date of this order. The court DENIES the Insurers’ Motion to Strike, DENIES Marsh’s Motion to Dismiss or Stay and Nordic’s Joinder, and GRANTS Marsh’s Motion for Judgment on the Pleadings with respect to Counts V and VI of the Third-Party Complaint.”

    Read the court’s decision…


    The Colorado Court of Appeals Rules that a Statutory Notice of Claim Triggers an Insurer’s Duty to Defend.

    October 23, 2012 — David M. McLain, Higgins, Hopkins, McLain & Roswell

    Gene and Diane Melssen d/b/a Melssen Construction (“Melssen”) built a custom home for the Holleys, during which period of time Melssen retained a CGL insurance coverage from Auto Owners Insurance Company. Soon after completion of the house, the Holleys noticed cracks in the drywall and, eventually, large cracks developed in the exterior stucco and basement slab. Thereafter, the Holleys contacted Melssen, the structural engineer, an attorney, and Auto-Owners, which assigned a claims adjuster to investigate the claim.

    In April 2008, the Holleys sent Melssen a statutory notice of claim pursuant to C.R.S. § 13-20-803.5 (“NOC”). In this NOC, the Holleys claimed approximately $300,000 in damages related to design and construction defects. The Holleys also provided a list of claimed damages and estimated repairs, accompanied by two reports from the Holleys’ consultant regarding the claimed design and construction defects. In June 2008, Melssen tendered the defense and indemnity of the claim to Auto-Owners. While Auto-Owners did not deny the claim at that time, it did not inspect the property or otherwise adjust the claim. Thereafter, in October 2008, Auto-Owners sent Melssen a letter denying coverage on the basis that the damage occurred outside of the applicable policy period.

    Ultimately, Melssen settled the claims against it for $140,000.

    Read the full story…

    Reprinted courtesy of David McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com


    Builder Waits too Long to Dispute Contract in Construction Defect Claim

    May 10, 2012 — CDJ Staff

    The Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.

    The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.

    The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.

    In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.

    The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.

    A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”

    Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.

    Read the court’s decision…


    Yellow Brass Fittings Play a Crucial Role in Baker v Castle & Cooke Homes

    May 10, 2012 — CDJ Staff

    Baker v Castle & Cooke Homes Hawaii, et al. is a “class action filed by homeowners who allege that their homes have a construction defect. They allege that their plumbing systems include brass fittings susceptible to corrosion and likely to cause leaks. They bring this action against the developer of their homes and the manufacturers of the brass fittings.”

    Zurn, the manufacturer of the allegedly defective brass fittings, sought a dismissal, or if that could not be achieved, then “a more definite statement, of five of the six claims.” Zurn moved for summary judgment on the sixth claim, or alternately sought “summary judgment on one of the five claims it” sought to dismiss.” The court granted in part the motion, and denied the motion for summary judgment.

    The developer, Castle & Cooke, sought dismissal of the First Amended Complaint stating “that Plaintiffs have not complied with Hawaii’s Contractor Repair Act, chapter 672E of Hawaii Revised Statutes, which requires, among other things, a plaintiff to give a contractor the results of any testing done before filing an action against that contractor.” The court couldn’t determine “certain facts essential to ruling” on Castle & Cooke’s motion, and therefore denied the motion, but ordered Plaintiffs to submit requested material by the stated deadline.

    The Baker v Castle & Cooke case began with the Plaintiffs claim that the use of yellow brass fittings can lead to construction defects. They allege that “yellow brass is particularly susceptible to dezincification, a corrosion process in which zinc leaches into potable water that comes into contact with the brass. According to Plaintiffs, as the brass corrodes, it becomes porous and mechanically weak. Plaintiffs further allege that the PEX systems in the putative class members’ homes have begun to, or are about to, leak water into the walls, ceilings, and floors of their homes. Plaintiffs allege that the leakage will cause water damage and mold growth, exposing the occupants to toxins.”

    In response to the plaintiffs’ claims, Zurn argued “because their yellow brass fittings have not failed to date, Plaintiffs fail to allege, and have no evidence showing, that they have suffered any actual injury.” Plaintiffs replied, “even if the fittings have not failed as of today, failure in the future is inevitable.”

    However, the court stated, “whether Plaintiffs have suffered any injury, or whether Plaintiffs are attempting to proceed based solely on future injury, implicates Plaintiffs’ standing to bring this action, as well as whether this case is ripe for adjudication.” The court has requested the parties to submit “supplemental briefing on whether this case should be dismissed pursuant to Rule 12(b)(1). In supplemental briefs, Zurn argues that dismissal is appropriate because Plaintiffs lack standing, and Castle & Cooke argues that dismissal is appropriate because Plaintiffs’ claims are not ripe.”

    The court continues to discuss the problem of standing: “To establish standing, a plaintiff must demonstrate three things. First, the plaintiff must suffer an "injury-in-fact," which means that there must be a concrete and particularized "invasion of a legally protected interest" and the invasion is actual or imminent. Lujan v. Defenders of Wildlife, 504 U.S. 555, 560 (1992). Second, the injury must be fairly traceable to the challenged action. Third, a favorable decision must be likely to redress the injury. Id. It is the first element (injury-in-fact) that is in issue here.”

    The court found that the plaintiffs do have standing: “Even if the court could not rely on the allegations that the pipes will soon leak, the court would conclude that, for standing purposes, Plaintiffs have a sufficient injury-in-fact in the form of their alleged economic loss.” In a hearing, Plaintiffs argued that their homes had decreased in value.

    The court also denied Castle & Cooke’s motion to dismiss based on a lack of ripeness, stating “the same reasons Plaintiffs satisfy the injury-in-fact requirement for standing purposes, they satisfy the constitutional ripeness requirement.”

    Plaintiffs asserted six counts against Zurn. Zurn, in response, made a motion to dismiss counts VIII, IX, X, XII, and XIII. The court granted Zurn’s motion for Counts VIII, IX, and X only: “Counts VIII (product liability), IX (negligence), and X (strict liability) sound in tort. Zurn argues that, because Plaintiffs allege no injury other than to the PEX systems and the yellow brass fittings themselves, the economic loss rule bars their tort claims. The court agrees.”

    The court disagreed with Zurn’s motion regarding Count XII: “Count XII asserts that Zurn has breached the implied warranty of merchantability. Zurn argues that Count XII is barred by the applicable statute of limitations and that Plaintiffs do not sufficiently allege an injury. The court disagrees.”

    Zurn’s motion regarding Count XIII was also denied: “Count XIII asserts that Zurn violated section 480-2 of Hawaii Revised Statutes.” Furthermore, “Plaintiffs allege that Zurn ‘engaged in unfair and deceptive acts or practices when [it] designed, manufactured and sold Yellow Brass Fittings.’ Zurn argues that Plaintiffs fail to state a claim under section 480-2(a) because their claims are barred by the statute of limitations and they do not adequately allege reliance or a cognizable injury. The court disagrees.”

    The court denied the motion for summary judgment with respect to Counts XI and XII.

    Castle & Cooke sought to dismiss “Plaintiffs’ claims against it under section 672E-2 of Hawaii Revised Statutes, which provides for dismissal when claimants fail to comply with chapter 672E.” There was some discussion regarding the test results. Apparently, the plaintiffs had failed to provide a written notice of claim at least 90 days before filing the action. However, it is unclear if the Plaintiffs have since complied with the requirements of the chapter. “The court has received no supplemental information from either party about whether any test results from another case have been turned over or whether those materials are subject to a confidentiality agreement. The record at this point does not establish noncompliance with the requirement in chapter 672E to provide such information. The court therefore denies the motion to dismiss.”

    In summary, “Zurn’s motion to dismiss is granted as to Count VIII, Count IX, and Count X. Zurn’s motion to dismiss is denied with respect to Plaintiffs’ other claims. Zurn’s request for a more definite statement and its summary judgment motion are denied. Plaintiffs are given leave to file an amended Complaint no later than May 21, 2012.” Furthermore, “the court denies Castle & Cooke’s motion, but directs Plaintiffs to file, within two weeks, either a certificate of compliance with section 672E-3(c), or an explanation as to why they have not complied. Castle & Cooke may submit a response within two weeks of Plaintiffs’ submission. Each party’s submission is limited to 1000 words.”

    Read the court’s decision…