Insurer Has Duty to Defend Despite Construction Defects
January 6, 2012 — CDJ Staff
In a case the judge attributed to “shoddy masonry work,” the US District Court of Illinois has rendered a decision in AMCO Insurance Company v. Northern Heritage Builders. Northern Heritage built a home in Chicago for Michael McGrath (who joined Northern Heritage as a defendant). According to the decision, “seven months after he moved into the house, McGrath noticed water coming in the house and warped millwork.” This was attributed to porous block, installed by the mason with Northern Heritage’s knowledge.
McGrath sued National Heritage for both the damage to his house and its contents. The court rejected his claim for the contents. For the damages to his house, he was awarded $601,570.50 in damages. He also sued his homeowner’s insurance carrier for damages not covered in his suit against National Heritage. There he was awarded $1,130,680.16.
AMCO informed National Heritage that it had neither duty to defend nor duty to indemnify. The judge considered whether AMCO had a duty to defend. Under Illinois law, “damage to a construction project resulting from construction defects is not an ‘accident’ or ‘occurrence’ because it represents the natural and ordinary consequence of faulty construction.” However, it is noted that while if the defects lead only to damage to the project itself, there is no occurrence, “if the building owner asserts damages to other property besides the construction itself, there is an ‘occurrence’ and ‘property damage.’” The judge further noted that were construction defects an occurrence, “shoddy work” would be rewarded by double pay, once by the homeowner and a second time by the insurer. Judge Kendall concluded that as McGrath had alleged damage to the contents of his house, AMCO had a duty to defend National Heritage.
She then looked at the issue of whether AMCO had a duty to indemnify. Should they pay the $601,570.50? Judge Kendall noted that “the duty to indemnify is narrower than the duty to defend.” The key point here was that once McGrath’s insurance carrier covered him for the damage to the contents of his house, “AMCO’s duty to defend ended.” Once McGrath “only sought damages for the natural consequences of faulty workmanship” there was no occurrence, hence nothing for AMCO to cover.
Judge Kendall granted a summary dismissal of AMCO’s claim that they had no duty to defend while upholding their claim that they had no duty to indemnify.
Read the court’s decision…
Policyholder Fails to Build Adequate Record to Support Bad Faith Claim
May 19, 2011 — May 19, 2011 -
Tred R. Eyerly,
Insurance Law HawaiiThe importance of careful preparation and documentation was the take away lesson in a Texas bad faith case, C.K. Lee v. Catlin Specialty Ins. Co., 2011 U.S. Dist. LEXIS 19145 (S.D. Tex. Feb. 28, 2011).
C.K. Lee owned a commercial shopping center in Houston. Catlin issued a commercial property policy to Lee. On September 12, 2008, Hurricane Ike hit and caused substantial property damage throughout the Texas Gulf Coast area. On September 24, 2008, Lee submitted a claim for damage to the roof of his shopping center to Catlin.
Catlin hired Engle Martin to represent its interests in adjusting the claim. Engle Martin eventually adjusted over 200 Ike-related claims for Catlin.
In November 2008, Engle Martin and Emergency Services Inc., retained by Lee, inspected Lee’s property. Engle Martin observed evidence of roof repairs that had apparently been made both before and after Hurricane Ike. Engle Martin decided it was necessary to use an infrared scan of the roof to help identify which damages, if any, were attributable to wind and which, if any, were attributable to sub par, prior repairs or natural deterioration.
Engle Martin retained Project, Time & Cost (PT&C) to conduct the infrared inspection. PT&C’s inspection determined there was no wind-related damage to the roof and no breaches or openings created by wind. Instead, the roof had exceeded its life expectancy and was in need of replacement due to normal wear and weathering. Consequently, Catlin decided that the damage to Lee’s roof was not caused by winds from Hurricane Ike.
Meanwhile, Lee’s contractor, Emergency Services, prepared a report estimating that the total cost of repairing the roof would be $871,187. Engle Martin’s estimate for repair of the roof was $22,864.
Lee filed suit for breach of contract, breach of the duty of good faith and fair dealing, and violations of the Texas Insurance Code. Catlin moved for summary judgment on all claims but breach of contract, arguing that because there was a bona fide dispute concerning the cause of the damages and whether they were covered under the policy, there was no evidence of bad faith or violations of the Texas Insurance Code.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Construction Defects as Occurrences, Better Decided in Law than in Courts
December 9, 2011 — CDJ Staff
Construction defect claims are now occurrences for insurance purposes in four states, Arkansas, Colorado, Hawaii, and South Carolina, yet there are still frustrations for commercial general liability policyholders. Business Insurance describes court decisions on whether construction defect claims are covered as “incongruous,” and this drives up coverage and litigation costs. Construction firms often find they are defending themselves on two fronts, both the construction defect claim and also whether their insurance covers it.
Frank Armstrong, the Senior Vice President and National Director of Construction Claims for Willis North America says that the problem starts with the word “occurrence,” as various state courts have different interpretations of the word. “Certain pieces of it don’t fit well, at lest according to some courts in the country, with coverage for construction defect risks.”
Another insurance executive, Julian Ehlich, the Senior Vice President of Claims for Aon Risk Solutions’ construction services group notes that “jurisdictions differ, so policyholders don’t know what they’re going to get.”
Read the full story…
Illinois Court Determines Insurer Must Defend Property Damage Caused by Faulty Workmanship
July 11, 2011 — Tred R. Eyerly, Insurance Law Hawaii
The Illinois Court of Appeals determined the insurer must defend allegations of property damage arising from faulty workmanship. Milwaukee Mut. Ins. Co. v. J.P. Larsen, Inc., 2011 Ill. App. Unpub. LEXIS 1443 (Ill. Ct. App. June, 20, 2011).
Larsen was a subcontractor for Weather-Tite in a condominium building. Weather-Tite installed windows on the project and hired Larsen to apply sealant to the windows. The windows subsequently leaked and caused water damage within the complex.
The homeowner’s association sued Weather-Tite for breach of express and implied warranties. Weather-Tite filed a third-party complaint against Larsen, seeking contribution and alleging that Larsen was in breach of contract by failing to add Weather-Tite as an additional insured under Larsen’s CGL policy.
Both Weather-Tite and Larsen tendered to Larsen’s insurer. Both tenders were denied because the insurer contended the complaints alleged only construction defects, and not “property damage” or an “occurrence” within the terms of the policy.
The insurer filed suit for a declaratory judgment. The trial court granted the insurer’s motion as to Weather-Tite, but granted Larsen’s cross-motion for summary judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Nevada Bill Aims to Reduce Legal Fees For Construction Defect Practitioners
March 21, 2011 — March 21, 2011 Construction Defect Journal Staff
Assemblyman Ira Hansen and twelve additional members of Nevada’s Assembly are sponsoring Assembly Bill 285. AB 285 Revises provisions governing an award of attorney’s fees in causes of action for constructional defects. Existing law generally provides that a claimant may recover reasonable attorney’s fees as part of the claimant’s damages in a cause of action for constructional defects. (NRS 40.655)
This bill removes this provision and instead authorizes a court to award reasonable attorney’s fees to a prevailing party involved in such a cause of action if an independent basis for the award exists pursuant to existing law which authorizes a court to award attorney’s fees in certain circumstances, or Rule 68 of the Nevada Rules of Civil Procedure, which provides for the payment of reasonable attorney’s fees by an offeree who rejects an offer and subsequently fails to obtain a more favorable judgment.
In an AP report published in Business Week it is suggested that the target objective of legislators centers on what it refers to as Nevada’s "Rampant construction defect lawsuits".
According to Business Week "The suits bring in hundreds of millions of dollars for lawyers and have put construction companies out of business. Hansen says fewer construction firms mean higher prices for Nevada consumers."
Click Here To Read Full Text and Revisions of Assembly Bill 285
Kentucky Court Upholds Arbitration Award, Denies Appeal
June 15, 2011 — CDJ Staff
The Kentucky Court of Appeals has ruled in Lake Cumberland Community Action Agency v. CMW, Inc. affirming the arbitration award. CMW, Inc. was responsible for the construction of a facility to be used for pre-school students and the housing of Alzheimer patients and senior citizens. An agreement was made that any disputes would be heard by an arbitrator selected by the construction industry.
The plaintiff alleged that there were design and construction defects in the building trusses, violation of the Kentucky Building Code, and problems with the HVAC system. The arbitrator awarded $106,000 to the plaintiff which then sought to vacate the award. The circuit court upheld the arbitrator’s decision.
The Court of Appeals found that there was no basis for rejecting the arbitrator’s decision, noting “there is nothing to show that there was any fraud or bias on the part of the arbitrator.” The appeals court, with all three judges concurring, upheld the arbitration award.
Read the court’s decision
Restitution Unlikely in Las Vegas Construction Defect Scam
October 23, 2012 — CDJ Staff
The San Francisco Chronicle reports that the money lost in the Las Vegas HOA fraud cause is probably not recoverable. Victims of the scam have asked the court for restitution, but Judge Lloyd George doubts any of the money will be found, saying “the money is not available, it would appear.”
One Vistana board members not part of the conspiracy told reporters that the $8 million construction defect settlement never went for needed repairs. “Within six months that money was gone,” said Bruce Wallace, a retired Air Force colonel. After the construction defect account was depleted to $450,000, two board members disappeared with the funds.
Read the full story…
North Carolina Exclusion j(6) “That Particular Part”
February 10, 2012 — CDCoverage.com
In Alliance Mutual Insurance Co. v. Dove, 714 S.E.2d 782 (N.C. Ct. App. 2011), claimant Murphy-Brown hired insured Dove to repair a broken elevator belt in a grain elevator in Murphy-Brown’s feed mill. The elevator was inside a metal duct and, to access the broken belt, Dove had to cut out a section of the duct. After replacing the belt, Dove welded the metal section back to the duct. Immediately after Dove completed the welding, dust inside the duct ignited, causing an explosion in the elevator, resulting in property damage to the elevator and other property. Murphy-Brown sued Dove for negligence seeking damages for the repair and replacement of the elevator, repair and replacement of the other property, increased grain handling costs during the repairs, and loss of use.
Read the full story…
Reprinted courtesy of CDCoverage.com
Builder Cannot Receive Setoff in Construction Defect Case
July 10, 2012 — CDJ Staff
The California Court of Appeals has dismissed an appeal in a San Diego construction defect case. In Smith v. Walters Group, Christopher and Maud Smith sued The Walters Group, a real estate developer, and Galen C. Pavelko, Inc, the builder of their home. Walters had bought five lots and hired Pavelko to build houses on them, selling one of these homes to the Smiths. “After moving in, the Smiths noticed a strong and obnoxious odor permeating the house.” The Smiths sued but were ordered to arbitrate instead, pursuant to a clause in the purchase contract. The Smiths were awarded $1.5 million at arbitration.
Walters requested that the arbitration remain open to determine if Walters was entitled to a setoff for settlements from defendants not involved in the arbitration. During this time, Pavelko made a settlement with the Smiths, which the court found was in good faith. At the same time, the arbitrator “reached the opposite conclusion.” The arbitrator concluded that “only settlements made ‘in good faith before verdict or judgment’ qualified for setoff.”
Walters moved that the trial court “‘correct’ the award,” but the trial court declined to do so and confirmed the award. In the appeal, Walters raised the issue of “whether Pavelko’s settlement occurred ‘before verdict or judgment.’” The appeals court dismissed the appeal, noting that “Walters would not be entitled to a $500,000 setoff if we reversed the trial court’s order determining the Smith-Pavelko settlement was made in good faith because Pavelko’s $500,000 payment was expressly conditioned on such an order.” They add that “were we to reverse the trial court’s order, Pavelko would have no obligation to pay the Smiths the $500,000.” This would then “deprive Walters of the corresponding statutory right to a setoff.”
Read the court’s decision…
Summary Judgment in Construction Defect Case Cannot Be Overturned While Facts Are Still in Contention in Related Cases
September 9, 2011 — CDJ Staff
The Alabama Court of Civil Appeals has dismissed an appeal of a summary judgment in the case Bella Investments, Inc. v. Multi Family Services, Inc. MFS was hired by Bella to be the general contractor for a hotel in Gardendale, Alabama. MFS hired various subcontractors, including the architect for the project. After completion of the hotel in April, 2006, Bella made requests for MFS to repair cracked floor tiles.
In August, 2008, Bella sued MFS, the architect, and various fictitiously named defendants. Subsequently, Bella amended its complaint, naming some of the fictitiously named defendants.
MFS in turn claimed that Bella’s claims were void under the statute of limitations and that Bella was in beach of contact by failing to pay MFS the full amount owed. MFS moved for summary judgment under the statute of limitations, which was granted by the court.
Bella requested that the court “alter, amend, or vacate its summary judgment order.” When this was denied, Bella appealed to the Alabama Supreme Court, which transferred the appeal to the Court of Civil Appeals. The Court of Appeals refused to vacate the summary judgment as claims that form part of the case against MFS are also part of Bella’s claims against the other defendants. For this reason, the court upheld the summary judgment.
Read the court’s decision…
Denver Court Rules that Condo Owners Must Follow Arbitration Agreement
November 7, 2012 — CDJ Staff
Prior to initiating a construction defect lawsuit, the Glass House Residential Association voted to invalidate the arbitration agreement that had been written into its declaration and bylaws by the developer and general contractor. After the association started their construction defect claims, the developer and general contractor argued that the case must go to arbitration, as the arbitration clause contained a provision that it could not be altered without the agreement of the developer and general contractor.
The Denver District Court has ruled against that association, determining that the res triction was not in violation of Colorado condominium law. And, as a post from Polsinelli Shughart PC on JDSupra notes, the Colorado Common Interest Ownership Act encourages the use of arbitration procedures to settle disputes. The CCIOA does prohibit “certain restrictions on the homeowners association’s ability to amend the condominium declarations,” however, preserving an arbitration agreement is not one of them.
Read the full story…
Certificate of Merit to Sue Architects or Engineers Bill Proposed
May 3, 2011 — May 3, 2011 Beverley BevenFlorez - Construction Defect Journal
North Carolina may become the twelfth state to require a Certificate of Merit to sue an architect or engineer. If North Carolina Senate Bill 435 (SB435) passes, then plaintiffs when filing a complaint will need to also attach an affidavit of a third-party licensed professional engineer or architect stating that the case has merit.
SB435 is a short two pages in its current form. The bill states that the “third-party licensed professional engineer or licensed architect shall (i) be competent to testify and hold the same professional license and practice in the same area of practice as the defendant design professional and (ii) offer testimony based upon knowledge, skill, experience, education, training, and practice. The affidavit shall specifically state for each theory of recovery for which damages are sought, the negligence, if any, or other action, error, or omission of the design professional in providing the professional service, including any error or omission in providing advice, judgment, opinion, or a similar professional skill claimed to exist and the factual basis for each such claim. The third-party licensed professional engineer or licensed architect shall be licensed in this State and actively engaged in the practice of engineering or architecture respectively.”
A few of the amendments allude to disciplining design professionals who certify civil actions that are without merit. The bill has been referred to the Committee on Judiciary I.
While North Carolina is considering enacting a Certificate of Merit law, eleven other states already require one, including Arizona, California, Colorado, Georgia, Maryland, Minnesota, New Jersey, Oregon, Pennsylvania, South Carolina, and Texas. Christopher D. Montez, a partner with Thomas, Feldman & Wilshusen, LLP, has written a useful summary for each state’s certificate of merit scheme.
Read the text of SB435
Track the progress of SB435
Read more from Christopher D. Montez’s article on Thomas, Feldman & Wilshusen, LLP site
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 — April 28, 2011 Beverley BevenFlorez - Construction Defect Journal
In the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision…
California Posts Nation’s Largest Gain in Construction Jobs
March 28, 2012 — CDJ Staff
California added about 8,900 construction jobs in January, 2012, as compared to December, 2011, leading the nation in the number of added construction jobs. Thirty-four other states also saw added construction jobs. A year prior, only twenty-eight states added construction jobs. The Associated General Contractors of America analyzed the monthly report from the Labor Department. Ken Simonson, the chief economist for the Associated General Contractors of America noted that “the gains this January partly reflect very mild weather this winter and exceptionally cold and snowy conditions a year before.”
Read the full story…
The Flood Insurance Reform Act May be Extended to 2016
April 7, 2011 — April 7, 2011 Beverley BevenFlorez - Construction Defect Journal
The Flood Insurance Reform Act of 2011 (H. R. 1309) has been referred to the House Committee on Financial Services—the first step in the legislative process. The bill, if passed, would extend the program to September 30, 2016. It is currently slated to be terminated September 30 of this year. The bill also contains changes to premium rates, mapping protocols, and privatization initiatives.
H. R. 1309 has garnered the support of several Insurance organizations. Leigh Ann Pusey, president and CEO of the American Insurance Association (AIA), sent a letter of support to the Chair and Ranking member of the House Financial Services Subcommittee. “AIA has advocated for a long term reauthorization of the NFIP to protect consumers and help increase stability for real estate transactions and policyholders,” Pusey said. “AIA believes the five-year extension contained in HR 1309, will provide certainty in the flood program thereby increasing consumer and business confidence in the NFIP.”
Jimi Grande, senior vice president of federal and political affairs for the National Association of Mutual Insurance Companies (NAMIC) spoke out in support of the bill. “For the NFIP to survive, the prices for flood insurance must reflect the actual costs of flood risk for a property,” Grande said. “HR 1309 will provide that transparency. In addition, the Technical Mapping Advisory Council will give communities a voice in the flood mapping process, fostering a better understanding of what flood maps represent and how they are made.”
Read H. R. 1309...
Read the American Insurance Association statement...
Read the NAMIC Press Release...
Arizona Court of Appeals Decision in $8.475 Million Construction Defect Class Action Suit
May 9, 2011 — May 9, 2011 Beverley BevenFlorez - Construction Defect Journal
In the case of Leflet v. Fire (Ariz. App., 2011), which involved an $8.475 million settlement in a construction defect class action suit, the question put forth to the Appeals court was “whether an insured and an insurer can join in a Morris agreement that avoids the primary insurer’s obligation to pay policy limits and passes liability in excess of those limits on to other insurers.” The Appeals court provided several reasons for their decision to affirm the validity of the settlement agreement as to the Non-Participatory Insurers (NPIs) and to vacate and remand the attorney fee awards.
First, the Appeals court stated, “The settlement agreement is not a compliant Morris agreement and provides no basis for claims against the NPIs.” They conclude, “Appellants attempt to avoid the doctrinal underpinnings of Morris by arguing that ‘the cooperation clause did not prohibit Hancock from assigning its rights to anyone, including Appellants.’ This narrow reading of the cooperation clause ignores the fact that Hancock did not merely assign its rights — it assigned its rights after stipulating to an $8.475 million judgment that neither it nor its Direct Insurers could ever be liable to pay. Neither Morris nor any other case defines such conduct as actual ‘cooperation’—rather, Morris simply defines limited circumstances in which an insured is relieved of its duty to cooperate. Because Morris agreements are fraught with risk of abuse, a settlement that mimics Morris in form but does not find support in the legal and economic realities that gave rise to that decision is both unenforceable and offensive to the policy’s cooperation clause.”
The Appeals court further concluded that “even if the agreement had qualified under Morris, plaintiffs did not provide the required notice to the NPIs.” The court continued, “Because an insurer who defends under a reservation of rights is always aware of the possibility of a Morris agreement, the mere threat of Morris in the course of settlement negotiations does not constitute sufficient notice. Instead, the insurer must be made aware that it may waive its reservation of rights and provide an unqualified defense, or defend solely on coverage and reasonableness grounds against the judgment resulting from the Morris agreement. The NPIs were not given the protections of this choice before the agreement was entered, and therefore can face no liability for the resulting stipulated judgment.”
Next, the Appeals court declared that “the trial court abused its discretion in awarding attorney’s fees under A.R.S § 12-341.” The Appeals court reasoned, “In this case, the NPIs prevailed in their attack on the settlement. But the litigation did not test the merits of their coverage defenses or the reasonableness of the settlement amount. And Plaintiffs never sued the NPIs, either in their own right or as the assignees of Hancock. Rather, the NPIs intervened to test the conceptual validity of the settlement agreement (to which they were not parties) before such an action could commence. In these circumstances, though it might be appropriate to offset a fee award against some future recovery by the Plaintiff Leflet v. Fire (Ariz. App., 2011) class, the purposes of A.R.S. § 12-341.01 would not be served by an award of fees against them jointly and severally. We therefore conclude that the trial court abused its discretion in awarding fees against Plaintiffs ‘jointly and severally.’”
The Appeals court made the following conclusion: “we affirm the judgment of the trial court concerning the validity of the settlement agreement as to the NPIs. We vacate and remand the award of attorney’s fees. In our discretion, we decline to award the NPIs the attorney’s fees they have requested on appeal pursuant to A.R.S. § 12-341.01(A).”
Read the court’s decision…
After Katrina Came Homes that Could Withstand Isaac
October 23, 2012 — CDJ Staff
In the aftermath of Hurricane Katrina, Louisiana adopted its first uniform building code. Under the new standards, homes are better able to withstand the winds generated by hurricanes. The owner of one home said that during Hurricane Isaac, “there’s no shaking of the building itself, there’s no sign of a storm except for the rain.”
WWWLTV reports that the new standards require home to be able to withstand 130 mile per hour winds. They also must follow FEMA guidelines for elevation. Build Now, a non-profit organization, is seeking to build green homes that meet the new standards. Their executive director said “we’re building higher. We’re building stronger. We’re building greener.”
Read the full story…
Safe Harbors- not just for Sailors anymore (or, why advance planning can prevent claims of defective plans & specs) (law note)
August 17, 2011 — Melissa Brumback
Have you ever considered a “Safe Harbor Provision” for your Owner-Architect or Owner-Engineer contract? Maybe it is time that you do.
As you are (probably too well) aware, on every construction project there are changes. Some of these are due to the owner’s change of heart, value engineering concerns, contractor failures, and material substitutions. Some may be because of a design error, omission, or drawing conflict. It happens.
A “Safe Harbor Provision” is a provision that establishes an acceptable percentage of increased construction costs (that is, a percentage of the project’s contingency). The idea is that if the construction changes attributable to the designer is within this percentage, no claim will be made by the Owner for design defects.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.