BERT HOWE
  • Nationwide: (800) 482-1822    
    office building Morris Pennsylvania condominiums Morris Pennsylvania condominium Morris Pennsylvania mid-rise construction Morris Pennsylvania concrete tilt-up Morris Pennsylvania Subterranean parking Morris Pennsylvania parking structure Morris Pennsylvania townhome construction Morris Pennsylvania Medical building Morris Pennsylvania tract home Morris Pennsylvania high-rise construction Morris Pennsylvania production housing Morris Pennsylvania structural steel construction Morris Pennsylvania institutional building Morris Pennsylvania retail construction Morris Pennsylvania multi family housing Morris Pennsylvania low-income housing Morris Pennsylvania landscaping construction Morris Pennsylvania housing Morris Pennsylvania casino resort Morris Pennsylvania industrial building Morris Pennsylvania custom home Morris Pennsylvania
    Arrange No Cost Consultation
    Construction Expert Witness Builders Information
    Morris, Pennsylvania

    Pennsylvania Builders Right To Repair Current Law Summary:

    Current Law Summary: HB 1875 stipulates that “no later than 90 days before filing an action, serve written notice of claim on the contractor. Upon receipt of notice, builder has 15 days to forward the claim to any subcontractor/supplier and 30 days after service of notice to offer to compromise and settle the claim by monetary payment without inspection, propose to inspect the dwelling that is the subject of the claim; or reject the claim. Contractor has 14 days after inspection to provide written notice of intention.”


    Construction Expert Witness Contractors Licensing
    Guidelines Morris Pennsylvania

    No state license required. For public works projects, see General Services website.


    Construction Expert Witness Contractors Building Industry
    Association Directory
    Home Builders Association of Adams County
    Local # 3920
    PO Box 3321
    Gettysburg, PA 17325


    Builders Association of Fayette County
    Local # 3961
    PO Box 1323
    Uniontown, PA 15401


    Somerset Co Builders Association
    Local # 3958
    PO Box 221
    Berlin, PA 15530
    http://www.SomersetCountyBuilders.org

    Franklin County Builders Association
    Local # 3912
    1102 Sheller Ave Ste C
    Chambersburg, PA 17201
    http://www.franklincountybuilders.com

    Building Industry Association of Philadelphia
    Local # 3946
    1735 Market St Ste A432
    Philadelphia, PA 19103
    http://www.biaofphiladelphia.com

    Home Builders Association of Chester & Delaware Co
    Local # 3941
    1502 McDaniel Dr
    West Chester, PA 19380
    http://www.builderpa.com

    York County Builders Assn
    Local # 3972
    540 Greebriar Road
    York, PA 17404
    http://www.yorkbuilders.com


    Construction Expert Witness News and Information
    For Morris Pennsylvania

    Construction Defects Not Occurrences under Ohio Law

    Construction on the Rise in Washington Town

    Contractor’s Home Not Covered for Construction Defects

    Ohio Adopts Energy-Efficient Building Code

    All Risk Policy Only Covers Repair to Portion of Dock That Sustains Damage

    Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.

    New Construction Laws, New Forms in California

    Architectural Firm Disputes Claim of Fault

    Construction Law Client Alert: California Is One Step Closer to Prohibiting Type I Indemnity Agreements In Private Commercial Projects

    Seller Cannot Compel Arbitration for Its Role in Construction Defect Case<

    Contract Not So Clear in South Carolina Construction Defect Case

    Micropiles for bad soil: a Tarheel victory

    Connecticut Gets Medieval All Over Construction Defects

    Ohio Court Finds No Coverage for Construction Defect Claims

    South Carolina Law Clarifies Statue of Repose

    Construction Spending Dropped in July

    Florida Appeals Court Rules in Favor of Homeowners Unaware of Construction Defects and Lack of Permits

    Insurer Beware: Failure to Defend Ends with Hefty Verdict

    Instant Hotel Tower, But Is It Safe?

    Lockton Expands Construction and Design Team

    School District Settles Construction Lawsuit

    Anti-Assignment Provision Unenforceable in Kentucky

    Water Drainage Case Lacks Standing

    Official Tried to Influence Judge against Shortchanged Subcontractor

    Judge Concludes Drywall Manufacturer Sold in Florida

    Home Sales Still Low, But Enough to Spur Homebuilders

    Allowing the Use of a General Verdict Form in a Construction Defect Case Could Subject Your Client to Prejudgment Interest

    Bar to Raise on Green Standard

    Foundation Arbitration Doesn’t Preclude Suing Over Cracks

    More Charges in Las Vegas HOA Scandal

    Another Guilty Plea in Las Vegas HOA Scandal

    Background Owner of Property Cannot Be Compelled to Arbitrate Construction Defects

    MGM Seeks to Demolish Harmon Towers

    Construction Defect Not an Occurrence in Ohio

    Washington Court of Appeals Upholds Standard of Repose in Fruit Warehouse Case

    Construction Worker Dies after Building Collapse

    Georgia Law: “An Occurrence Can Arise Where Faulty Workmanship Causes Unforeseen or Unexpected Damage to Other Property”

    New Apartment Tower on the Rise in Seattle

    Certificate of Merit to Sue Architects or Engineers Bill Proposed

    Another Guilty Plea In Nevada Construction Defect Fraud Case

    Liability policy covers negligent construction: GA high court

    Construction Suit Ends with Just an Apology

    One to Watch: Case Takes on Economic Loss Rule and Professional Duties

    Granting Stay, Federal Court Reviews Construction Defect Coverage in Hawaii

    Contractor Underpaid Workers, Pocketed the Difference

    Colorado Senate Bill 12-181: 2012’s Version of a Prompt Pay Bill

    Ensuing Loss Found Ambiguous, Allowing Coverage

    Defense for Additional Insured Not Barred By Sole Negligence Provision

    US Courts in Nevada Busy with Yellow Brass

    Oregon agreement to procure insurance, anti-indemnity statute, and self-insured retention

    After $15 Million Settlement, Association Gets $7.7 Million From Additional Subcontractor

    Godfather Charged with Insurance Fraud

    Mobile Home Owners Not a Class in Drainage Lawsuit

    $5 Million Construction Defect Lawsuit over Oregon Townhomes

    Consulting Firm Indicted and Charged with Falsifying Concrete Reports

    Court Requires Adherence to “Good Faith and Fair Dealing” in Construction Defect Coverage

    Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses

    Ensuing Losses From Faulty Workmanship Must be Covered

    New Washington Law Nixes Unfair Indemnification in Construction Contracts

    Homeowners Not Compelled to Arbitration in Construction Defect Lawsuit

    Alabama “occurrence” and subcontractor work exception to the “your completed work” exclusion

    District Court’s Ruling Affirmed in TCD v American Family Mutual Insurance Co.

    Insurance Policy Provides No Coverage For Slab Collapse in Vision One

    Construction Defect Destroys Home, Forty Years Later

    CC&Rs Not the Place for Arbitration Agreement, Court Rules

    Town Files Construction Lawsuit over Dust

    Badly Constructed Masonry Walls Not an Occurrence in Arkansas Law

    California insured’s duty to cooperate and insurer’s right to select defense counsel

    Workers Hurt in Casino Floor Collapse

    Negligent Construction an Occurrence Says Ninth Circuit

    Nevada Budget Remains at Impasse over Construction Defect Law

    Texas Law Bars Coverage under Homeowner’s Policy for Mold Damage

    Insurer Has Duty to Disclose Insured's Interest In Obtaining Written Explanation of Arbitration Award

    Exclusion Bars Coverage for Mold, Fungus

    Remodels Replace Construction in Redding

    Arizona Contractor Designs Water-Repellant Cabinets

    Minnesota Starts Wide-Ranging Registration of Contractors

    Architect Not Responsible for Injuries to Guests

    Know the Minnesota Statute of Limitations for Construction Defect Claims

    After Breaching its Duty to Defend, Insurer Must Indemnify

    Boston’s Tunnel Project Plagued by Water

    Court Sends Construction Defect Case from Kansas to Missouri

    Michigan Supreme Court Concludes No Statute of Repose on Breach of Contract

    Construction Defect Lawsuits? There’s an App for That

    Construction Job Opening Rise in October

    Construction Defect Not Occurrences, Says Hawaii Court

    Appeals Court Reverses Summary Judgment over Defective Archway Construction

    Arizona Supreme Court Confirms Eight-Year Limit on Construction Defect Lawsuits

    General Contractor/Developer May Not Rely on the Homeowner Protection Act to Avoid a Waiver of Consequential Damages in an AIA Contract

    Defect Claims as Occurrences? Check Your State Laws
    Corporate Profile

    MORRIS PENNSYLVANIA CONSTRUCTION EXPERT WITNESS
    DIRECTORY AND CAPABILITIES

    The Morris, Pennsylvania Construction Expert Witness Group at BHA, leverages from the experience gained through more than 5,500 construction related expert witness designations encompassing a wide spectrum of construction related disputes. Drawing from this considerable body of experience, BHA provides construction related trial support and expert services to Morris' most recognized construction litigation practitioners, commercial general liability carriers, owners, construction practice groups, as well as a variety of state and local government agencies.

    Construction Expert Witness News & Info
    Morris, Pennsylvania

    Insurer Rejects Claim on Dolphin Towers

    July 22, 2011 — CDJ Staff

    A year after residents were forced to leave Dolphin Towers in Sarasota, Florida because of concrete problems, some residents are defaulting on their obligations, abandoning their units. In June, the building’s insurer, Great American, rejected a claim, arguing that the building’s problems were due to latent defects, not covered under the policy. Repair estimates, previously put at $8.2 million, have now risen to $11.5 million. If homeowners cover this cost, it would require an assessment of about $100,000 for each unit.

    About thirty owners are in arrears on dues and fees. Charlotte Ryan, the president of the Dolphin Tower board, wrote to owners, that “the board will have no choice but to lien your property and pursue foreclosure if you do nothing to bring your delinquencies up to date.” However, as homeowners default, the funding for repairs is imperiled. The board has already spent more than $500,000 on shoring up the building and hiring consultants. Their lawyers, on the other hand, are working on a contingency basis.

    Read the full story…


    Water Damage Covered Under Efficient Proximate Cause Doctrine

    August 2, 2012 — Tred Eyerly, Insurance Law Hawaii

    A U.S. District Court in Washington found coverage in what it described as a text book study of the efficient proximate cause rule. Hiller v. Allstate Pro. & Cas. Ins. Co., 2012 U.S. Dist. LEXIS 84862 (E.D. Wash. June 19, 2012).

    The Hillers purchased a newly constructed home in December 2006. They also purchased an all-risk homeowner's policy from Allstate.

    In July 2010, the Hillers discovered that the carpet in the basement of the residence was saturated with water. Allstate was immediately notified. Hiller began an investigation to attempt to determine the source of the water. He poured water into a downspout drain at the northwest corner of the residence. This caused water to leak into the northwest corner of the home's basement.

    An area was excavated around the northwest downspout drain. The end of the drain pipe was partially blocked by rocks and had been wrapped with fabric landscaping material. Further, a “T” pipe installed at the foot of the drain was directing water toward the house's concrete foundation. Hiller notified Allstate that the problems with the drain was due to construction defects and the system was designed to fail.

    Allstate denied the claim. Based upon Hiller's information, coverage was excluded under the policy's surface water, subsurface water, inherent vice, and latent defect exclusions.

    Read the full story…

    Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com


    Don MacGregor To Speak at 2011 West Coast Casualty Construction Defect Seminar

    January 1, 2011 — February 08, 2011 CDJ Staff

    “Challenges for Experts in Construction Defect Claims and Litigation” will be held Thursday May 13, 2011 between 1:30 and 3:00 PM at this year’s West Coast Casualty Construction Defect Seminar. Among the various topics covered will be of Right to Repair/Opportunity to Repair statutes, improper testing methodologies, new challenges where a case involves a Wrap Policy, OCIPS, CCIPS, and other owner controlled insurance programs, as well as the need for realistic testing protocols for the party the expert is retained to represent.

    During the presentation Mr. MacGregor will be working in connection with a group of construction and design experts each of which have extensive experience with construction defect and claims related litigation. This particular session is expected to attract a standing-room only crowd, drawing in excess of 1700 attendees.

    The West Coast Casualty Construction Defect Seminar is the largest seminar of its type. This year’s event is scheduled for will take place on May 12 and 13, 2011, at The Disneyland Hotel and Resort. For more information regarding the years event please visit http://www.westcoastcasualty.com/dyncat.cfm?catid=3322

    http://www.westcoastcasualty.com/dyncat.cfm?catid=3322

    HOA Has No Claim to Extend Statute of Limitations in Construction Defect Case

    October 28, 2011 — CDJ Staff

    The California Court of Appeals ruled on September 20, 2011 in the case of Arundel Homeowners Association v. Arundel Green Partners, a construction defect case involving a condominium conversion in San Francisco. Eight years after the Notice of Completion was filed, the homeowners association filed a lawsuit alleging a number of construction defects, including “defective cabinets, waterproofing membranes, wall-cladding, plumbing, electrical wiring, roofing (including slope, drainage and flashings), fire-rated ceilings, and chimney flues.” Three years of settlement negotiations followed.

    Negotiations ended in the eleventh year with the homeowners association filing a lawsuit. Arundel Green argued that the suit should be thrown out as California’s ten-year statute of limitations had passed. The court granted judgment to Arundel Green.

    The homeowners then filed for a new trial and to amend its complaint, arguing that the statute of limitations should not apply due to the doctrine of equitable estoppel as Arundel Green’s actions had lead them to believe the issues could be solved without a lawsuit. “The HOA claimed that it was not until after the statute of limitations ran that the HOA realized Arundel Green would not keep its promises; and after this realization, the HOA promptly brought its lawsuit.” The trial court denied the homeowners association’s motions, which the homeowners association appealed.

    In reviewing the case, the Appeals Court compared Arundel to an earlier California Supreme Court case, Lantzy. (The homeowners also cited Lantzy as the basis of their appeal.) In Lantzy, the California Supreme Court set up a four-part test as to whether estoppel could be applied. The court applied these tests and found, as was the case in Lantzy, that there were no grounds for estoppel.

    In Arundel, the court noted that “there are simply no allegations that Arundel Green made any affirmative statement or promise that would lull the HOA into a reasonable belief that its claims would be resolved without filing a lawsuit.” The court also cited Lesko v. Superior Court which included a recommendation that the plaintiffs “send a stipulation?Ķextending time.” This did not happen and the court upheld the dismissal.

    Read the court’s decision…


    Construction Defects and Contractor-Owners

    July 10, 2012 — CDJ Staff

    On the expert advice site Avvo.com, a user asks if he can be sued for construction defects by the new owner of a building for which he served as general contractor and then owned for four years. He had construction insurance, but does not think he had construction defect insurance.

    A lawyer responding to his question says that “you could be sued.” In the event of a suit, “you would have to bring claims against all of your subcontractors.”

    Read the full story…


    Environment Decision May Expand Construction Defect Claims

    August 16, 2012 — CDJ Staff

    Could a California Supreme Court decision on environmental claims have an effect on construction defect cases? Jonathan B. Sokol, a lawyer at Greenberg Glusker argues just that in a post on his firm’s blog. He notes that the California Supreme Court has held that “the ‘all sums” method of allocation applies in California” and that “an insurer cannot limit its liability to just the amount of loss that occurred in its particular policy period.” While his focus is on environmental cases, he says that “the decision could also potentially expand the scope of coverage for construction defect claims and other claims involving continuous and progressive property damage and bodily injury.

    Read the full story…


    Flooded Courtroom May be Due to Construction Defect

    September 1, 2011 — CDJ Staff

    The General Services Administration wouldn’t pin it on a construction defect, but a spokesperson said that a pipe that was misaligned during installation was the likely cause of a flood in the Thomas F. Eagleton US Courthouse on August 23. According to the St. Louis Dispatch, the burst pipe caused a 17-story waterfall in the courthouse, soaking ceilings and floors, and drenching the building’s contents.

    The building was dedicated eleven years ago. During the nearly ten years before the building was complete, there were construction disputes and soil contamination issues.

    Read the full story…


    Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.

    April 28, 2011 — April 28, 2011 Beverley BevenFlorez - Construction Defect Journal

    In the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”

    The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”

    According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”

    The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”

    The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”

    The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.” The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”

    Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”

    The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”

    In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”

    The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”

    In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”

    The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”

    Read the court’s decision…

    Construction Defect Litigation at San Diego’s Alicante Condominiums?

    March 25, 2011 — Alicante HOA Website

    According to recent posts in the Alicante HOA website, construction experts and legal counsel have been retained. The HOA board has been informed that testing of a variety of the building’s components are underway or will begin in the near future.

    Read More...


    Town Files Construction Lawsuit over Dust

    August 16, 2012 — CDJ Staff

    Washington Township in Ohio has filed a lawsuit against Underground Utilities for their handling of construction fill on a road project. The City of Mansfield had hired the firm to improve road safety. The lawsuit is over the company’s actions in processing soil for fill, which they are doing on three vacant lots that are zoned for residential use. Washington Township Trustee Jack Butler told the Mansfield Journal that “what brought the lawsuit to a head was the fact that the contractor did not control the dust.” Subsequent receiving notices of zoning violations, the company began to move its operation to another site.

    Read the full story…


    Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?

    March 17, 2011 — By Shaun McParland Baldwin, March 17, 2011

    The Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury” or “property damage” be caused by an “occurrence” and that the “bodily injury” or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury” or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury“ or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.

    In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivan’s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing , including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.

    Read the full story...

    Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com


    Construction Workers Face Dangers on the Job

    November 18, 2011 — CDJ Staff

    OSHA calculates that for each 33,000 active construction workers, one will die on the job each year, making their risk over the course of their careers at one out of every 200 workers. This puts it many times over OSHA’s definition of “significant risk” of 1 death per 1,000 workers over the course of their careers. According to an article in People’s World, “the main risk of death is from falls.”

    At a talk at the American Public Health Association’s meeting, one expert noted that “construction workers make up 6 percent to 8 percent of all workers, but account for 20 percent of all deaths on the job every year.”

    Read the full story…


    Insurer Has Duty to Defend Despite Construction Defects

    January 6, 2012 — CDJ Staff

    In a case the judge attributed to “shoddy masonry work,” the US District Court of Illinois has rendered a decision in AMCO Insurance Company v. Northern Heritage Builders. Northern Heritage built a home in Chicago for Michael McGrath (who joined Northern Heritage as a defendant). According to the decision, “seven months after he moved into the house, McGrath noticed water coming in the house and warped millwork.” This was attributed to porous block, installed by the mason with Northern Heritage’s knowledge.

    McGrath sued National Heritage for both the damage to his house and its contents. The court rejected his claim for the contents. For the damages to his house, he was awarded $601,570.50 in damages. He also sued his homeowner’s insurance carrier for damages not covered in his suit against National Heritage. There he was awarded $1,130,680.16.

    AMCO informed National Heritage that it had neither duty to defend nor duty to indemnify. The judge considered whether AMCO had a duty to defend. Under Illinois law, “damage to a construction project resulting from construction defects is not an ‘accident’ or ‘occurrence’ because it represents the natural and ordinary consequence of faulty construction.” However, it is noted that while if the defects lead only to damage to the project itself, there is no occurrence, “if the building owner asserts damages to other property besides the construction itself, there is an ‘occurrence’ and ‘property damage.’” The judge further noted that were construction defects an occurrence, “shoddy work” would be rewarded by double pay, once by the homeowner and a second time by the insurer. Judge Kendall concluded that as McGrath had alleged damage to the contents of his house, AMCO had a duty to defend National Heritage.

    She then looked at the issue of whether AMCO had a duty to indemnify. Should they pay the $601,570.50? Judge Kendall noted that “the duty to indemnify is narrower than the duty to defend.” The key point here was that once McGrath’s insurance carrier covered him for the damage to the contents of his house, “AMCO’s duty to defend ended.” Once McGrath “only sought damages for the natural consequences of faulty workmanship” there was no occurrence, hence nothing for AMCO to cover.

    Judge Kendall granted a summary dismissal of AMCO’s claim that they had no duty to defend while upholding their claim that they had no duty to indemnify.

    Read the court’s decision…


    Court finds subcontractor responsible for defending claim

    May 18, 2011 — May 18, 2011 - CDJ Staff

    In an unpublished decision, the California Fourth Appellate District Court has reversed the judgment of Judge Linda B. Quinn of the Superior Court of San Diego. In the case Inland California, Inc. v. G.A. Abell, Inland, a general contractor had subcontracted with Apache Construction and Precision Electric Company (G.A. Abell).

    Apache alleged that extra demolition and drywall work was needed due to Precision’s electrical work. Inland tendered a defense of Apache’s claims. However, Precision did not provide any defense. Inland withheld payment from Precision.

    At trial, Inland “conceded Precision earned the $98,000 in progress payments Inland withheld.” They were obligated to additionally pay Precision’s costs and attorney fees.

    The Fourth Appellate District court has overturned this and remanded the case back to the lower court. The judges determined that Precision was obligated to defend itself against the claims raised by Apache and therefore vacated the judgment against Inland.

    Read the court’s decision…


    Damron Agreement Questioned in Colorado Casualty Insurance v Safety Control Company, et al.

    February 10, 2012 — CDJ Staff

    Safety Control and EMC appealed the judgment in Colorado Casualty Insurance Company versus Safety Control Company, Inc., et al. (Ariz. App., 2012). The Superior Court in Maricopa County addressed “the validity and effect of a Damron agreement a contractor and its excess insurer entered into that assigned their rights to sue the primary insurer.” Judge Johnsen stated, “We hold the agreement is enforceable but remand for a determination of whether the stipulated judgment falls within the primary insurer’s policy.”

    The Opinion provides some facts and procedural history regarding the claim. “The Arizona Department of Transportation (“ADOT”) hired DBA Construction Company (“DBA”) to perform a road-improvement project on the Loop 101 freeway. Safety Control Company, Inc. was one of DBA’s subcontractors. As required by the subcontract, Safety Control purchased from Employer’s Mutual Casualty Company (“EMC”) a certificate of insurance identifying DBA as an additional insured on a policy providing primary coverage for liability arising out of Safety Control’s work.”

    A collision occurred on site, injuring Hugo Roman. Roman then sued ADT and DBA for damages. “Colorado Casualty tendered DBA’s defense to the subcontractors, including Safety Control. Safety Control and EMC rejected the tender. Roman eventually settled his claims against DBA and ADOT. DBA and ADOT stipulated with Roman for entry of judgment of $750,000; Roman received $75,000 from DBA (paid by Colorado Casualty) and $20,000 from ADOT, and agreed not to execute on the stipulated judgment. Finally, DBA, ADOT and Colorado Casualty assigned to Roman their rights against the subcontractors and other insurers.”

    Colorado Casualty attempted to recover what “it had paid to defend DBA and ADOT and settle with Roman. However, Roman intervened, and argued that “Colorado Casualty had assigned its subrogation rights to him as part of the settlement agreement.” The suit was not dismissed, but the Superior Court allowed Roman to intervene. “Roman then filed a counterclaim against Colorado Casualty and a cross-claim against the subcontractors.”

    All claims were settled against all of the defendants except Safety Control and EMC. “The superior court ruled on summary judgment that EMC breached a duty to defend DBA and that as a result, ‘DBA was entitled to settle with Roman without EMC’s consent as long as the settlement was not collusive or fraudulent.’ After more briefing, the court held the stipulated judgment was neither collusive nor procured by fraud and that EMC therefore was liable to Roman on the stipulated judgment and for his attorney’s fees. The court also held Safety Control breached its subcontract with DBA by failing to procure completed-operations insurance coverage and would be liable for damages to the extent that EMC did not satisfy what remained (after the other settlements) of the stipulated judgment and awards of attorney’s fees.” Safety Control and EMC appealed the judgment.

    Four reasons were given for the decision of the ruling. First, “the disagreement between Roman and Colorado Casualty does not preclude them from pursuing their claims against EMC and Safety Control.” Second, “the settlement agreement is not otherwise invalid.” Third, “issues of fact remain about whether the judgment falls within the EMC policy.” Finally, “Safety Control breached the subcontract by failing to procure ‘Completed Operations’ coverage for DBA.”

    In conclusion, the Superior Court affirmed in part, reversed in part, and remanded . “Although, as stated above, we have affirmed several rulings of the superior court, we reverse the judgment against EMC and remand for further proceedings consistent with this Opinion to determine whether the stipulated judgment was a liability that arose out of Safety Control’s operations. In addition, we affirm the superior court’s declaratory judgment against Safety Control but remand so that the court may clarify the circumstances under which Safety Control may be liable for damages and may conduct whatever further proceedings it deems appropriate to ascertain the amount of those damages. We decline all parties’ requests for attorney’s fees pursuant to A.R.S. § 12-341.01 without prejudice to a request for fees incurred in this appeal to be filed by the prevailing party on remand before the superior court.”

    Read the court’s decision…


    Builder Waits too Long to Dispute Contract in Construction Defect Claim

    May 10, 2012 — CDJ Staff

    The Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.

    The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.

    The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.

    In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.

    The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.

    A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”

    Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.

    Read the court’s decision…


    El Paso Increases Surety Bond Requirement on Contractors

    April 25, 2011 — April 25, 2011 Beverley BevenFlorez - Construction Defect Journal

    The city of El Paso has recently increased surety bonds required of contractors from $10,000 to $50,000, according to the El Paso Times. Proponents of the increase believe it was necessary to protect homeowners from fly-by-night builders, while opponents argue that the increase will have an adverse effect on an industry in that is already suffering due to the economic slowdown.

    Arguments for and against the increase have been flooding the blogosphere with their views. Christian Dorobantescu on the Small Business Entrepreneur Blog claims that “only about 15% of the city’s 2,500 contractors had been able to secure a higher bond to remain eligible for work after the new requirements were announced.” However, insurance companies have a different take. “From a surety broker standpoint, most contractors will be able qualify for the bond; some will just have to pay higher premium rates to obtain it,” a recent post on the Surety1 blog argues.

    While the increased bond may help homeowners deal with construction defect claims, it is not clear what effect it will have on builders in El Paso.

    Read more from the El Paso Times…

    Read more from the Small Business Entrepreneur Blog…

    Read more from the Surety1 Blog…


    Insurance for Defective Construction Now in Third Edition

    November 7, 2012 — CDJ Staff

    Available both in print and online, the International Risk Management Institute, Inc has brought out a third edition of Insurance for Defective Construction. The work is written by Patrick J. Wielinski of Cokinos, Bosien & Young, a Dallas-Fort Worth law firm. Mr. Wielinski practice focuses on insurance coverage. Insurance for Defective Construction is described as “a must read for anyone who buys, sell, or underwrites construction insurance or who becomes involved in construction claims.”

    Read the full story…