Judge Kobayashi Determines No Coverage for Construction Defect Claim
October 23, 2012 — Tred Eyerly, Insurance Law Hawaii
Judge Kobayashi of the U.S. District Court, District of Hawaii, largely followed earlier precedent established by Judge Mollway in finding no coverage for construction defect claims. See Evanston v. Nagano, 2012 WL 3800320 (D. Hawaii Aug. 31, 2012).
Evanston issued several liability policies to the insured contractor from 2002 and 2011. The insured entered a contract to build a residence in Honolulu. The homeowners were not happy with their home after the work was completed. They filed suit, alleging that the project was delayed and the construction was "riddled with defects." The complaint included claims for breach of contract and breach of warranties. Negligence was not alleged. Evanston defended, but under a reservation of rights.
Evanston filed suit for a declaratory judgment and moved for summary judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Builder Cannot Receive Setoff in Construction Defect Case
July 10, 2012 — CDJ Staff
The California Court of Appeals has dismissed an appeal in a San Diego construction defect case. In Smith v. Walters Group, Christopher and Maud Smith sued The Walters Group, a real estate developer, and Galen C. Pavelko, Inc, the builder of their home. Walters had bought five lots and hired Pavelko to build houses on them, selling one of these homes to the Smiths. “After moving in, the Smiths noticed a strong and obnoxious odor permeating the house.” The Smiths sued but were ordered to arbitrate instead, pursuant to a clause in the purchase contract. The Smiths were awarded $1.5 million at arbitration.
Walters requested that the arbitration remain open to determine if Walters was entitled to a setoff for settlements from defendants not involved in the arbitration. During this time, Pavelko made a settlement with the Smiths, which the court found was in good faith. At the same time, the arbitrator “reached the opposite conclusion.” The arbitrator concluded that “only settlements made ‘in good faith before verdict or judgment’ qualified for setoff.”
Walters moved that the trial court “‘correct’ the award,” but the trial court declined to do so and confirmed the award. In the appeal, Walters raised the issue of “whether Pavelko’s settlement occurred ‘before verdict or judgment.’” The appeals court dismissed the appeal, noting that “Walters would not be entitled to a $500,000 setoff if we reversed the trial court’s order determining the Smith-Pavelko settlement was made in good faith because Pavelko’s $500,000 payment was expressly conditioned on such an order.” They add that “were we to reverse the trial court’s order, Pavelko would have no obligation to pay the Smiths the $500,000.” This would then “deprive Walters of the corresponding statutory right to a setoff.”
Read the court’s decision…
General Contractor/Developer May Not Rely on the Homeowner Protection Act to Avoid a Waiver of Consequential Damages in an AIA Contract
August 4, 2011 — Higgins, Hopkins, McLain & Roswell, LLC
Recently, in Caribou Ridge Homes, LLC v. Zero Energy, LLC, et al., Case No. 10CV1094, Boulder County District Court Judge Ingrid S. Bakke entered a ruling and order on the Plaintiff’s Motion for Determination of Question of Law Pursuant to C.R.C.P. 56(h) on Issue of Damages. The Order found that the Plaintiff was not a homeowner intended to be protected by the Homeowner Protection Act (the “HPA”) and thus could not pursue its claims for consequential damages against Defendant.
By way of background, on June 18, 2008, Plaintiff Caribou Ridge Homes, LLC (“Caribou”) entered into a Standard Form Agreement Between Owner and Contractor AIA Document A114-2001 (the “Contract”) with Defendant Zero Energy, LLC (“Zero Energy”). Plaintiff hired Zero Energy to serve as a general contractor for the construction of a single-family home in the Caribou Ridge subdivision in Nederland, Colorado. A provision in the contract contained a mutual waiver of consequential damages (“Waiver”).
Read the full story…
Reprinted courtesy Higgins, Hopkins, McLain & Roswell, LLC
Insurer Has Duty to Disclose Insured's Interest In Obtaining Written Explanation of Arbitration Award
October 23, 2012 — Tred Eyerly, Insurance Law Hawaii
The issue faced by the Minnesota Supreme Court was whether the insurer had a duty to disclose the insured's interest in obtaining a written explanation of an arbitration award that identified the claims of recovery and the portions of the award attributable to each. Remodeling Dimensions, Inc. v. Integrity Mut. Ins. Co., 2012 LEXIS Minn. 404 (Minn. Sup. Ct., Aug. 22, 2012).
Remodeling Dimensions, Inc. ("RDI") built an addition for the homeowners and installed windows in the original part of the house. After construction began, the homeowners also asked RDI to fix the master bedroom window in the original part of the house.
After completion of the project, the house sustained storm damage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Construction Suit Ends with Just an Apology
February 10, 2012 — CDJ Staff
After suing a contractor for failing to complete the remodeling of their home, an Orange County couple has settled for an apology. Douglas J. Pettibone represented the contractor, who had lost his business after a broken neck, multiple surgeries, and an addiction to pain medicine. Mr. Pettibone represented his client pro bone. The case was settled in arbitration by JAMS.
Mr. Pettibone noted that his client gave “a heartfelt and very moving apology.” The remodeling was completed by another contractor, two years after Thorp Construction stopped work on the project. After the apology, the case was dismissed.
Read the full story…
Plaintiff Not Entitled to Further Damages over Defective Decking
August 2, 2012 — CDJ Staff
The Court of Appeal of the State of California, Third Appellate District has rejected an appeal from the successful plaintiff of a construction defect case in Evilsizor v. Calaveras Lumber Company. John Evilsizor hired Scott Hunton to remove and replace the deck at the rear of his home. Subsequently, the deck, which had been constructed with a product called SmartDeck, a product of the subsequently bankrupt US Plastic Lumber, exhibited problems. Hunton made some repairs. Calaveras Lumber offered replacement decking if Evilsizor would pay the difference in price. Mr. Evilsizor hired another contractor to replace the decking and then sued for lost use and compensation for the amount he paid the second contractor. Replacing the deck a second time cost Mr. Evilsizor $113,065.44.
During the trial, the defendant conceded that the planking was defective. It has been recalled by the manufacturer. Additionally, the jury heard testimony from a construction and building codes consultant, Lonne Haughton, however the trial court found that Mr. Haughton did not have sufficient expertise in wood-plastic composite materials. Further, Haughton had been a California contractor for only three years, and though he claimed a college degree, this was “‘a distance learning diploma’ that required no in-class work.” The appeals court upheld the decision that Mr. Haughton was not qualified to testify as an expert about wood-plastic materials.
The court also upheld the trial court’s exclusion of two pieces of evidence. One was a list of SmartDeck sales. However, the witness asked about it was not able “to testify who prepared it or confirm that it had been prepared by a Cascade employee.” Further, “the fact defendant bought and sold SmartDeck was not disputed.” The other was an e-mail in which US Plastics said they had “some bad product in the field.” This e-mail went to Westmark & Associates, and the plaintiff did not establish that it was ever sent to the defendant.
Though the defense has suggested an award of $18,000 plus loss-of-use damages for one year and an additional $4,000 if the jury believed that leftover material from the front deck was used in the rear. As the plaintiff requested $100 per month of loss of use, this would have totaled $34,000. The jury awarded the cost of the decking, $6,275,82. The court cites earlier decision that the amount of the award is “a question of fact to be determined by the jury.”
In conclusion, Mr. Evilsizor was not only unable to receive a larger award, but the court ruled that he must pay the defendant’s cost on appeal.
Read the court's decision…
Construction Workers Unearth Bones
June 28, 2011 — CDJ Staff
While digging for a new steam line at Eastern Michigan University, workers unearthed some old bones. Experts have yet to determine if the bones are human or animal, however Walter Kraft, the EMU vice president of communications, noted that a handle also unearthed might have come from a casket. Cindy Heflin, reporting in AnnArbor.com notes that until 1900 a Catholic cemetery was located in the area. Although the bodies were relocated, these may have been left behind.
Read the full story…
Home Sales Still Low, But Enough to Spur Homebuilders
August 16, 2012 — CDJ Staff
Although new home sales are still fifty percent below the average over the last forty years, the housing rebound has sent stock of homebuilders up 53 percent this year, during the same period, the S&P 500 rose only 12 percent. The San Francisco Chronicle reports that from 2005 through 2011, homebuilder stocks trailed the S&P 500.
The growth isn’t limited to homebuilders alone. Building suppliers are also seeing a growth in sales, with profits for companies that make gypsum wallboard, cabinetry, plumbing products, and other items used in home building.
Homebuilders have also been able to raise prices. Standard Pacific Corp of Irvine, California has raised prices and cut incentives. Nevertheless, the buyers still come. PulteGroup and D.R. Horton are also raising prices.
Read the full story…
California Supreme Court Binds Homeowner Associations To Arbitration Provisions In CC&Rs
September 13, 2012 — Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP (http://www.gdandb.com).
The California Supreme Court ruled in Pinnacle Museum Tower Assn. v. Pinnacle Market Development (August 16, 2012, S186149) __ Cal.4th __ [2012 WL 3516134], that arbitration provisions within the covenants, conditions, and restrictions (“CC&Rs”) for condominium projects are enforceable against their homeowner associations. The ruling — two years in the making — was based on legislative history of laws governing common interest developments, and decades of decisional authority involving contracts and arbitration provisions.
In Pinnacle, a homeowners association sued a condominium builder for construction defects and resultant property damage to the common areas, and to the separate property interests held by the individual members. The builder moved to compel arbitration, based on a provision contained in the CC&Rs which required resolution of all construction disputes through binding arbitration. The association argued it could not be compelled to arbitrate these claims because it was not a party to the agreement to arbitrate, asserting “the Association did not bargain with [the builder] over the terms of the Project CC&R's or participate in their drafting.”
The Supreme Court rejected the association's argument on the grounds that the builder-authored CC&Rs complied with the Davis-Stirling Act (“the Act”) (Civil Code §1350, et seq.) ? the law that governs all common interest developments in California. Under the Act, builders and sellers of common interest residential units are required to provide a copy of the CC&Rs to all purchasers, as well as copies of the Department of Real Estate's public report, which informs purchasers of their rights and remedies as members of the association, and encourages each prospective purchaser to review the terms carefully before entering into any agreement. Further, the Act states all CC&Rs are enforceable, unless unreasonable, and inure to the benefit of and bind all owners in the development. (Civ. Code, §1354, subd. (a).) The Court found each owner who purchased a condominium in the project either expressly consented to the terms and provisions of the CC&Rs or was deemed to have consented to the terms at the time of purchase.
The Court also did not find the arbitration provision to be unconscionable. The Court indicated the provision was drafted and recorded in accordance with the Act, which allowed each prospective purchaser to make an informed decision prior buying a condominium unit. The provision also limited arbitration to construction defect disputes. The Court did not find any evidence the provision “shocked the conscience” or was “oppressive” in any way.
Pinnacle settles a decades-long conflict over whether arbitration provisions in CC&Rs for condominium projects are enforceable against homeowner associations and their members. It remains unclear, however, whether Pinnacle’s rationale will be applied to cases involving homeowner associations for single-family residences (as opposed to condominiums), assuming those CC&Rs have similar arbitration requirements. Regardless, the result of Pinnacle is clear, if arbitration provisions contained in condominium CC&Rs meet the fairness and unconscionability tests set out by the Court, more condominium construction defect cases brought by homeowner associations will be resolved through the arbitration process.
Read the court’s decision…
Printed courtesy of Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP. Mr. Sunseri can be contacted at ssunseri@gdandb.com and Ms. Kewalramani can be contacted at akewalramani@gdandb.com.
Another Colorado District Court Refuses to Apply HB 10-1394 Retroactively
October 28, 2011 — David M. McLain, Colorado Construction Litigation
In Martinez v. Mike Wells Construction Company, 09CV227, Teller County District Court Judge Edward S. Colt refused to apply C.R.S. § 13-20-808 retroactively to provide coverage for the underlying construction defect allegations. According to the recitation of facts in Judge Colt’s March 2011 order, Martinez contracted with Mike Wells Construction to serve as the general contractor for the construction of a home. At that time, Mike Wells Construction was insured through ProBuilders Specialty Insurance Company, RRG. Disputes arose between Martinez and Mike Wells Construction, resulting in Martinez ordering it off of the project in mid-November 2007 and terminating its right to work there by letter dated November 28, 2007.
Mike Wells, the owner of the corporation, subsequently died. Martinez sued Mike Wells Construction in July 2009 for breach of contract and various claims relating to alleged defecting workmanship. Martinez provided notice of the suit to the special administrator of the probate estate. No answer having been filed, the court entered a default judgment against Mike Wells Construction and Martinez sought to garnish Mike Wells Construction’s ProBuilders insurance policy.
Read the full story...
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. McClain can be contacted at mclain@hhmrlaw.com
Judge Okays Harmon Tower Demolition, Also Calls for More Testing
August 2, 2012 — CDJ Staff
Vegas.Inc reports that Clark County District Court Judge Elizabeth Gonzalez has permitted the demolition the tower, which MGM Resorts has claimed is a safety hazard. Perini Building Co. claims that the building does not need to be demolished. CityCenter claims that repairing the building would take nearly a year longer than a demolition and cost about $200 million. Further, CityCenter assumes that the building’s reputation would cost it another $30 million.
Subsequently, Judge Gonzalez ruled that the pattern of destructive testing would not support a claim that there were an estimated 1,400 defective items in the building. An attorney for CityCenter, Steve Morris, has suggested that they may seek more testing, impossible to do once the building is demolished. CityCenter issued a statement that “nearly every time CityCenter has chipped away concrete to review structural work at the Harmon, we have found defects.” They describe the building as “unusable.”
Tutor Perini contends that it “remains confident that it will prevail when the issues of safety, reparability and responsibility for the issues facing the Harmon tower are considered.
Read the full story…
Fire Reveals Defects, Appeals Court Affirms Judgment against Builder
July 10, 2012 — CDJ Staff
The Arizona Court of Appeals has ruled in the case of Simms v. Nance Construction. After a fire damaged his home, Jerry Simms discovered some construction defects in the work of the builder, Nance Construction. Nance Construction completed the home in 2000 and it was damaged by fire in 2001. In the course of Simms’ suit against his neighbor, “defense experts opined both that Dusty Creek had negligently repaired the damage to Simms’ residence and that many defects found in the houses were the result of defects in the original construction.” Nance offered to make roof repairs. Simms responded with a list of “numerous construction defects,” stating this was “not a comprehensive and final list of items.” Nance offered to repair some while disputing others. Simms entered a lawsuit against Nance and other parties.
Nance first sought a summary judgment, “asserting that Simms had failed to adequately disclose the repairs for which he sought to hold Nance responsible.” The court denied this. It also would not allow Nance to introduce evidence that Simms had been denied a license by the Arizona Department of Gaming over “questionable business practices, illegal activities, and financial transactions with a person purportedly involved in organized crime.”
During the suit, Simms contracted with Advanced Repair Technologies “for repairs that included a complete remodel of the roof and the exterior stucco system.” Nance later claimed that the cost of ART’s repair was unreasonable, claiming that it should have cost about $600,000 instead of the $1.5 million for which Simms contracted. The jury found against Nance, with a judgment of $870,200 of which half was due to the roofing subcontractor.
After the verdict, Nash moved for a new trial, stating that the jury should have heard expert testimony on whether the contract price was reasonable. Nance also “argued that the trial court had erred in refusing to allow Nance to impeach Simms’ credibility with his purported prior acts of dishonesty.” These motions were denied and Nance appealed.
The appeals court upheld the trial court on all counts. The court found that, despite the contention made by Nance, the jury had sufficient information to determine if the cost of the repairs were reasonable. The court also found that Simms had given Nance an opportunity to propose repairs. The law, however, “does not require the Plaintiff to accept an offer for repairs,” adding that “the record makes clear that the parties were far apart in their belief of the nature of repairs necessary.” Nor did the court find that Nance should have been allowed to introduce evidence to impeach Simms’ credibility.
Although judgment of the lower court was affirmed, the court took the discretion to decline to award attorneys’ fees to Simms, although he was awarded costs.
Read the court’s decision…
Arbitration Clause Not Binding on Association in Construction Defect Claim
June 19, 2012 — CDJ Staff
Determining that a community’s CC&Rs do not form an agreement to arbitrate, the California Court of Appeals has reversed the decision of the Superior Court inVerano Condo. Homeowners the Ass’n v. La Cima Dev., LLC (Cal. App., 2012). La Cima purchased an apartment complex in December 2004, which they converted into condominiums. In the process, La Cima created the CC&Rs, under which the Verano Condominium Homeowners Association came into being. One section of the CC&Rs included arbitration clauses. Additionally, the purchase agreements for individual condominium units also contained arbitration clauses. Subsequently, the owners became aware of construction defect both in units and in the common areas. The Association sued La Cima both in its own interest and on behalf of its members. La Cima moved to compel arbitration, which was denied by the trial court. La Cima appealed.
The court concluded that “CC&Rs are insufficient to form an agreement to arbitrate between La Cima and the Association.” The court noted that “no evidence exists to show the Association consented to the terms of the CC&Rs, either explicitly or implicitly.”
The court agreed with La Cima that the arbitration agreement applied to those owners who had purchased their units directly from La Cima. Moreover, as the conversion to condominiums involved interstate commerce, in part because a Delaware company was selling condominiums located in California, the court held that the Federal Arbitration Act (FAA) applied, and as such “even a state constitutional standard, such as the the jury waiver provision requirements of the California Constitution, cannot be used to circumvent the FAA in the face of an otherwise valid arbitration agreement.”
However, the court also held that there was “no agreement in the CC&Rs between La Cima and owners who did not purchase units directly from La Cima,” adding that “no meeting of the minds between La Cima and these later purchasers and their successors occurred.” The court did not believe that “the Legislature intended that CC&Rs would be used to provide continuing and irrevocable contractual development or role as a representative of the owners of the development.”
The purpose of the CC&Rs, according to the court are to “protect owners from one another and permit enforcement of its terms by the Association.” The court stated that “La Cima relinquished its interests in the land by selling its property and may not assert any rights under the CC&Rs following the transfer of its ownership interest.
In its conclusion, the court determined that claims must be organized in three classes. The claims the association made against La Cima for defects in the common area “are not subject to any valid agreement to arbitrate.” The second category are those owners who did not purchase their units directly from La Cima. Here, also, the court found that the units “are similarly not subject to a valid arbitration agreement.”
The third category, however, was “owners who purchased units directly from La Cima.” The court held that these arbitration agreements were valid, and if the claims were to be taken up by the association, the association could only submit these claims to arbitration. The lower court was instructed to separate these claims, as here La Cima’s motion could be granted.
Read the court’s decision…
Mississippi exclusions j(5) and j(6) “that particular part”
June 7, 2011 — CDCoverage.com
In Lafayete Ins. Co. v. Peerboom, No. 3:10cv336 (S.D. Miss. June 2, 2011), claimant homeowner Peerboom hired insured contractor Absolute to raise Peerboom’s house two feet to avoid future flooding. While Absolute was raising the house, it fell, resulting in physical injury to the home. Peerboom sued Absolute for negligence, breach of contract, and fraud, seeking damages for the destruction of the home. Absolute’s CGL insurer Lafayette defended under a reservation of rights and filed a declaratory judgment action.
Read the full story…
Reprinted courtesy of CDCoverage.com
School Sues over Botched Pool
October 23, 2012 — CDJ Staff
The Daily American reports that the Somerset Area School District has alleged that the contractor who repaired and renovated the district’s swimming pool “botched” the job. Now the school has filed a civil case in the Somerset County Court of Common Pleas. The contractor, Wilson Construction Co. would prefer the matter to be settled in binding arbitration.
The school district alleges that the surface installed by Wilson Construction cracked and bubbled due to improper installation. The manufacturer of the waterproofing system, Dryvit Systems, tested the installation and concluded it was an installation failure instead of a product defect. Dryvit told the district that the exterior walls would have be removed.
The school district paid Wilson Construction $591,081 for their work. In their lawsuit, they are seeking $594,596 to cover the cost of draining the pool and repairing it.
Read the full story…
Construction Defect Not Occurrences, Says Hawaii Court
July 10, 2012 — CDJ Staff
Some insurers in Hawaii have made it clear that they will be covering construction defects, despite a court ruling concluding that defects are not occurrences, under Hawaii law. The case, heard by Hawaii’s Intermediate Court of Appeals found that “breach-of-contract claims based on allegations of shoddy performance are not covered under CGL policies and that tort-based claims derivative of such breach of contract claims also are not covered.”
Writing in Business Insider, Michael Bradford notes that the case, Group Builders Inc. and Tradewind Insurance Co. Ltd. vs. Admiral Insurance Co., involved improperly installed insulation at the Hilton Hawaiian Village’s Kalia Tower. Hilton was forced to close 21 floors due to extensive mold in guest rooms. Although the court did recognize this property damage, they did not feel it triggered insurance coverage, noting that if disputes over the quality of work were covered, CGL policies would become professional liability policies or performance bonds.
One critic of the decision, Warren C. Perkins, the risk manager at Boh Bros. Construction of New Orleans, noted that under the decision, “it doesn’t matter what the policy says and there is no need to investigate the policy wording.”
Read the full story…
Arizona Court of Appeals Decision in $8.475 Million Construction Defect Class Action Suit
May 9, 2011 — May 9, 2011 Beverley BevenFlorez - Construction Defect Journal
In the case of Leflet v. Fire (Ariz. App., 2011), which involved an $8.475 million settlement in a construction defect class action suit, the question put forth to the Appeals court was “whether an insured and an insurer can join in a Morris agreement that avoids the primary insurer’s obligation to pay policy limits and passes liability in excess of those limits on to other insurers.” The Appeals court provided several reasons for their decision to affirm the validity of the settlement agreement as to the Non-Participatory Insurers (NPIs) and to vacate and remand the attorney fee awards.
First, the Appeals court stated, “The settlement agreement is not a compliant Morris agreement and provides no basis for claims against the NPIs.” They conclude, “Appellants attempt to avoid the doctrinal underpinnings of Morris by arguing that ‘the cooperation clause did not prohibit Hancock from assigning its rights to anyone, including Appellants.’ This narrow reading of the cooperation clause ignores the fact that Hancock did not merely assign its rights — it assigned its rights after stipulating to an $8.475 million judgment that neither it nor its Direct Insurers could ever be liable to pay. Neither Morris nor any other case defines such conduct as actual ‘cooperation’—rather, Morris simply defines limited circumstances in which an insured is relieved of its duty to cooperate. Because Morris agreements are fraught with risk of abuse, a settlement that mimics Morris in form but does not find support in the legal and economic realities that gave rise to that decision is both unenforceable and offensive to the policy’s cooperation clause.”
The Appeals court further concluded that “even if the agreement had qualified under Morris, plaintiffs did not provide the required notice to the NPIs.” The court continued, “Because an insurer who defends under a reservation of rights is always aware of the possibility of a Morris agreement, the mere threat of Morris in the course of settlement negotiations does not constitute sufficient notice. Instead, the insurer must be made aware that it may waive its reservation of rights and provide an unqualified defense, or defend solely on coverage and reasonableness grounds against the judgment resulting from the Morris agreement. The NPIs were not given the protections of this choice before the agreement was entered, and therefore can face no liability for the resulting stipulated judgment.”
Next, the Appeals court declared that “the trial court abused its discretion in awarding attorney’s fees under A.R.S § 12-341.” The Appeals court reasoned, “In this case, the NPIs prevailed in their attack on the settlement. But the litigation did not test the merits of their coverage defenses or the reasonableness of the settlement amount. And Plaintiffs never sued the NPIs, either in their own right or as the assignees of Hancock. Rather, the NPIs intervened to test the conceptual validity of the settlement agreement (to which they were not parties) before such an action could commence. In these circumstances, though it might be appropriate to offset a fee award against some future recovery by the Plaintiff Leflet v. Fire (Ariz. App., 2011) class, the purposes of A.R.S. § 12-341.01 would not be served by an award of fees against them jointly and severally. We therefore conclude that the trial court abused its discretion in awarding fees against Plaintiffs ‘jointly and severally.’”
The Appeals court made the following conclusion: “we affirm the judgment of the trial court concerning the validity of the settlement agreement as to the NPIs. We vacate and remand the award of attorney’s fees. In our discretion, we decline to award the NPIs the attorney’s fees they have requested on appeal pursuant to A.R.S. § 12-341.01(A).”
Read the court’s decision…
Pennsylvania Court Extends Construction Defect Protections to Subsequent Buyers
December 20, 2012 — CDJ Staff
The Pennsylvania courts have long held that there is an implied warranty of habitability for the initial purchaser of a home. Now, as some defects may not immediately show up, the court has extended that implied warranty to second and subsequent purchasers. As Marc D. Brookman, David I. Haas, and Christopher Bender of Duane Morris note, “this judicially created doctrine shifts the risk of a latent defect in the construction of a new home from the purchaser to the builder-vendor.”
The Pennsylvania Supreme Court concluded that a contractual relationship is not needed for an implied warranty of habitability. The court’s concern was inequalities would result when a home was sold while other homes were protected by being within the statute of repose.
Read the full story…