What Massachusetts Contractors and Developers Can Learn from Cannistraro v. Columbia Construction
July 13, 2026 —
Anthony LaPlaca & Luke Marston - The Construction SeytIntroduction
On June 26, 2026 the Massachusetts Supreme Judicial Court issued its decision in J.C. Cannistraro, LLC v. Columbia Construction Co.—a holding that sits at the intersection of Prompt Pay Act compliance and the Massachusetts Arbitration Act.
[1]
Most already know that the Massachusetts Prompt Pay Act (PPA) imposes strict timing and certification requirements for rejecting payment applications and proposed change orders on projects valued at $3 million or more. Most notably, the PPA requires the paying party to give the payee written notice of its approval or rejection of progress applications and proposed changes within 15 days of receipt, which notice must include a “factual and contractual basis for the rejection” and must be “certified as made in good faith.”
[2] In the absence of a timely certified notice, payment is “deemed to be approved” unless the payor properly rejects payment before it comes due.
[3]
Reprinted courtesy of
Anthony LaPlaca, Seyfarth Shaw LLP and
Luke Marston, Seyfarth Shaw LLP
Mr. LaPlaca may be contacted at alaplaca@seyfarth.com
Mr. Marston may be contacted at lmarston@seyfarth.com
Read the full story...
Protect Your Projects By Identifying and Controlling Hidden Contract Risks
March 10, 2026 —
Larry Borda & Daniel Lund III - JD SupraIn a recent webinar entitled “
Spreading the Risk and Avoiding Killer Contract Clauses,” Phelps lawyers Daniel Lund and Larry Borda examined contractual provisions that most often expose construction professionals to unexpected financial and legal risk. While construction contracts may appear routine, each contract serves as the primary mechanism for managing, allocating, and mitigating risk among parties involved in complex projects—often valued in the hundreds of millions or billions of dollars. When parties fail to fully understand the terms they sign, costly and avoidable consequences frequently follow.
Contracts as Risk-Transfer Instruments
Construction contracts are the primary method for transferring risk. While contracts authorize work and define scope, they also allocate responsibility for the risks inherent in construction projects. Some may imagine a world where a one-page agreement and a set of plans would suffice. In reality, modern construction requires detailed agreements—particularly provisions designed to anticipate problems, distribute burdens and reduce disputes.
Reprinted courtesy of
Larry Borda, Phelps and
Daniel Lund III, Phelps
Mr. Borda may be contacted at larry.borda@phelps.com
Mr. Lund may be contacted at daniel.lund@phelps.com
Read the full story...
Delay Matters: Florida’s Fourth DCA Reverses Hurricane Irma Dismissal
June 08, 2026 —
Andrea DeField, Machaella Reisman & Cary D. Steklof - Hunton Insurance Recovery BlogThe mantra “delay, deny, defend” is frequently referenced in discussions of insurance claims handling, though insurers will invariably disavow these tactics. While it would be facially improper for an insurer to delay a coverage decision to gain a tactical advantage, empirical examples nonetheless exist. This very dynamic was addressed by Florida’s Fourth District Court of Appeals when it handed policyholders a win in
Hypoluxo Mariner’s Cay Condo. Assoc’n, Inc. v. Underwriters at Lloyd’s London, No. 4D2024‑2250 (Fla. 4th DCA Apr. 1, 2026), reversing a trial court order dismissing a condominium association’s Hurricane Irma coverage lawsuit against its property insurer.
Delay to Run the Statute of Limitations
Following Hurricane Irma, a condominium association suffered roof and exterior envelope damage, reported an insurance claim, and submitted a sworn proof of loss to its property insurer in compliance with Florida Statute § 627.70132 (2020). The statute establishes a timeframe within which a policyholder must submit a claim for hurricane damage.
Reprinted courtesy of
Andrea DeField, Hunton Andrews Kurth LLP,
Machaella Reisman, Hunton Andrews Kurth LLP and
Cary D. Steklof, Hunton Andrews Kurth LLP
Ms. DeField may be contacted at adefield@hunton.com
Ms. Reisman may be contacted at reismanm@hunton.com
Mr. Steklof may be contacted at csteklof@hunton.com
Read the full story...
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLP’s Fort Lauderdale office. He may be reached at shauptman@balljanik.com.
Mandatory Arbitration Isn’t All Bad, if. . .
July 13, 2026 —
Christopher G. Hill - Construction Law MusingsIn the past week or so mandatory arbitration has been all the rage. From those that argue that
arbitration is becoming more burdensome than litigation, to my friend and fellow construction attorney Scott Wolfe who gives great advice on how to make arbitration worth it again. You can place me in the camp of those that think that mandatory arbitration clauses of the type typically found in contracts can add a layer of expense that can be unnecessary.
However, if an arbitration clause is carefully drafted, and properly used, these clauses an be helpful in assuring that the streamlining effect for which arbitration was created actually occurs. Because the
contract is king in Virginia, these provisions can essentially create the rule of civil procedure used to resolve any dispute relating to the project.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Suit Limitation Provision Eliminates Wind Loss Claim
July 27, 2026 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer’s motion for judgment on the pleadings was granted after the insured failed to file suit against the insurer within the policy’s two-year suit limitation provision. Interstate Investments, LLC v. Mt. Hawley Ins Co., 2026 U.S. Dist. LEXIS 98108 (S.D. N. Y. May 4, 2026).
On or before June 27, 2023, a wind, hail and rainstorm damaged Interstate’s property in Oklahoma. Interstate filed a claim under its policy with Mt. Hawley. The policy provided that New York law applied and contained a two- year suit limitation provision.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Reminder: FOLLOW Your Well Drafted Contract Provisions
February 17, 2026 —
Christopher G. Hill - Construction Law MusingsI have early and very often stated that your
contract is the basis for everything relating to your construction project. Everything from “
no damages for delay” clauses to
attorney fees to
indemnity are found in those documents. A well drafted construction contract
sets the expectations for the project clearly and, aside from just making it easier on everyone for a successful project, will ease things
should there be any dispute later.
However, all of the great drafting and pre-construction negotiation in the world won’t do you a bit of good if you don’t follow those provisions. I can’t count the number of times that a contractor or subcontractor has read and even understood the construction documents but then put the contract in the drawer and didn’t look at it again. Your experienced construction attorney, while helpful at the drafting and negotiation stages and beyond, cannot help do the work. Your lawyer can help you negotiate and
highlight the notice provisions of the contract but cannot provide that notice to the Owner or General Contractor when you have a claim. In short, the best contract in the world is
only as good as those that are following it.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.