Celebrities Lose Case in Construction Defect Arbitration
May 26, 2011 — CDJ Staff
An arbitration panel has ruled that problems with the Idaho home of actors Tom Hanks and Rita Wilson were not due to construction defects but rather to “poor design and bad architectural advice.” The couple had settled with the architectural firm, Lake Flato of San Antonio, Texas for $900,000 and was subsequently seeking $3 million from Storey Construction of Ketchum, Idaho.
Problems with the couple’s home “included leaking roofs, inadequate drainage, fireplaces that did not vent properly and an inadequate air-conditioning system. In 2003, sliding snow from the roof damaged kitchen windows and roof components.”
The arbitration panel, according to the report in the Idaho Mountain Express and Guide, noted that “Hanks and Wilson were responsible for the full $167,623 cost of arbitration, but further denied a Storey Construction counterclaim that alleged Hanks and Wilson filed their claim out of malice.”
Read the full story…
Ensuing Losses From Faulty Workmanship Must be Covered
May 10, 2012 — Tred Eyerly, Insurance Law Hawaii
Coverage for damages resulting from faulty workmanship in the construction of an apartment complex was at issue in The Bartram, LLC v. Landmark Am. Ins. Co., 2012 U.S. Dist. LEXIS 44535 (N.D. Fla. March 30, 2012).
The owner of the apartments, Bartram, had primary coverage and three layers of excess coverage. Each contract excluded loss from faulty workmanship. The policies provided, however, "if loss or damage by a Covered Cause of Loss results, we will pay for that resulting loss or damage."
Bartram contended water intrusion occurred because of faulty workmanship, which caused damage to the buildings’ exterior and interior finishes, wood sheathing, framing, balcony systems, drywall ceilings and stucco walls. This damage was separate from the work needed to simply fix the faulty workmanship. Therefore, Bartram argued, the ensuing losses that resulted from the water intrusion was covered.
The insurer argued the ensuing loss exception was not applicable if the ensuing loss was directly related to the original excluded loss.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Condo Board May Be Negligent for not Filing Construction Defect Suit in a Timely Fashion
December 9, 2011 — CDJ Staff
The Maryland Court of Special Appeals has ruled that condominium association boards have a duty to “properly pursue any claims,” overturning the decision of a lower court that said that it had no legal duty to file suit. Tom Schild, writing at Marylandcondominiumlaw.net, writes about Greenstein v. Avalon Courts Six Condominium, Inc.
In this case, the condominium board waited six years after residents complained about water intrusion problems before suing the developer. The court ruled that the suit could not be filed, as the statute of limitations was only three years. After residents were assessed for the repairs, homeowners sued the board, arguing that their delay lead to the need for the special assessment.
After overturning the decision, the Court of Special Appeals has asked the trial court to review the negligence claim.
Read the full story…
Rihanna Finds Construction Defects Hit a Sour Note
August 2, 2012 — CDJ Staff
The pop singer Rihanna is suing the former owners of her Beverley Hills home among others in a construction defect lawsuit. She contends that Adriana and Heather Rudomin concealed defects in the home that lead to water leaks and flooding during a 2010 storm. The Beverly Hills Patch noted that the dollar amount of the singer’s suit was not specified.
The most recent court ruling denied a motion from the owners to be dismissed from the lawsuit. They remain part of it, along Landmark Design Group, LLC, which renovated the home before the sale, and Prudential California Realty which sold the home.
Read the full story…
Federal District Court Predicts Florida Will Adopt Injury In Fact Trigger
October 23, 2012 — Tred Eyerly, Insurance Law Hawaii
The U. S. District Court for the Middle District of Florida was confronted with determining whether Florida would follow the manifestation or injury in fact trigger in Axis Surplus Ins. Co. v. Contravest Constr. Co., 2012 U.S. Dist. LEXIS 104502 (D. Fla. June 5, 2012).
The homeowner's association sued the insureds for alleged negligent construction and development of individual dwelling units and common areas of their condominium. Due to this negligence, severe damage was caused by water intrusion. The Association's members only became aware of the defects through the retention of construction experts.
The insured had CGL coverage with Axis, with policies issued from 2003 to 2007. Coverage was denied for the periods 2003-2004 and 2004-2005. Axis provided a defense under the policies issued for 2005-2006 and 2006-2007, but under a reservation of rights. Axis sought a declaration that it had no duty to defend or indemnify because the damage manifested before its policy periods.
For coverage to exist, "property damage" must have "occurred" during Axis' policy period.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
The Hidden Dangers of Construction Defect Litigation
March 28, 2012 — David M. McLain, Colorado Construction Litigation
David M. McLain, writing at Colorado Construction Litigation, has an interesting blog post republishing his article in Common Interests magazine, the monthly periodical of the Rocky Mountain Chapter of the Community Associations Institute. In his article, he touches on a number of pitfalls in construction defect litigation, including the potential conflicts of interests facing HOAs. He also considers the problems homeowners can face, including both “strong-arm tactics” taken by attorneys to compel homeowners to join the lawsuit, or situations in which the interests of the HOA do not match those of the homeowners. He writes:
There is also a conflict of interest with individual owners who attempt to opt out of the case. This can lead to shocking strong-arm tactics on the part of plaintiffs’ attorneys. In one instance, a plaintiffs’ attorney sent a letter to an individual homeowner that stated that as a 1/58th owner of the common elements, if he refused to go along with the suit, and there was ultimately a finding in favor of the HOA which was in any way limited by his refusal to participate, he would be personally liable for 1/58th of the HOA’s total damages. In another instance, a different plaintiffs’ attorney sent a letter to a homeowner who wanted the builder to perform warranty repairs, informing the owner that if he let the builder perform any repairs, the attorney would bill the HOA according to the fee agreement entered by the HOA board (without knowledge or consent of non-board members) and that the HOA would assess the homeowner for that expense. These are just two examples of conflicts which may arise between the HOA board and individual homeowners when the HOA pursues CD cases.
Another example of a conflict which will arise as a result of CD litigation occurs post-settlement. When an HOA settles for less than 100% of the amount necessary to fund all repairs outlined by its experts, plus attorneys’ fees and litigation costs, there will obviously be a shortfall in the amount necessary to fix the development. The HOA board must then choose to impose a special assessment to cover the shortfall or to make some, but not all, of the repairs outlined by its experts. In choosing the latter, the conflict arises with respect to which homes get fixed and which do not. In this situation, the HOA board has acted as the attorney-in-fact for the individual owners by bringing claims on their behalf, and has compromised those claims without their knowledge or consent.
Read the full story…
Reprinted courtesy of David M. McLain of Higgins, Hopkins, McClain & Roswell, LLC. Mr. McClain can be contacted at mclain@hhmrlaw.com.
Allowing the Use of a General Verdict Form in a Construction Defect Case Could Subject Your Client to Prejudgment Interest
August 2, 2012 — Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC
A recent opinion from the Colorado Court of Appeals is a cautionary tale concerning the calculation of pre-judgment interest. See Hendricks v. Allied Waste Transportation, Inc., 2012 WL 1881004 (Colo. App. 2012). The Hendricks sued Allied after one of its drivers backed into the corner of their home with an Allied garbage truck. At trial, a jury awarded the Hendricks $160,100 in damages. Although the jury was instructed on the cost of repairs, diminution in value, and non-economic damages, the parties agreed to a general verdict form that did not ask the jury to specify the types of damages awarded. The Hendricks sought to amend the judgment to include prejudgment interest and costs, which the trial court granted.
Allied appealed, arguing that the trial court erred by awarding the Hendricks prejudgment interest from the date their property was damaged. Id. at *7. The Colorado Court of Appeals found no error, and affirmed.
Read the full story…
Reprinted courtesy of Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Anderson can be contacted at anderson@hhmrlaw.com
Save A Legal Fee? Sometimes You Better Talk With Your Construction Attorney
May 10, 2012 — Douglas Reiser, Builders Counsel
I love writing this column, because I think it’s refreshing for contractors to hear that they don’t always need an attorney. Today’s post is the “Un-Save a Legal Fee” because I want to point out a specific illustration of when you definitely need your attorney. Using a construction contract template can be fine, but you always need to consider its application to each project ? or it could bite you in the rear.
Seattle attorney Paul Cressman published a prime depiction of bad contract management, last week. A Florida appellate court struck down a general contractor’s “pay if paid” clause when it became ambiguous because of some incorporated language from its prime contract. Specifically, a clause in the prime contract required the general contractor to pay all subcontractors before receiving payment from the owner, while the general contractor’s “pay if paid” clause required its subcontractors to wait for payment until it arrived from the owner.
Read the full story…
Seven Tips to Manage Construction Defect Risk
July 10, 2012 — CDJ Staff
Jody T. Wright looks at “seven strategies being used around the country to identify, manage and mitigate your exposures” in a piece in Business Insurance. Wright, Senior VP, Construction Department Manager for Lockton Companies in Denver, gives seven simple steps from the perspective of a insurer.
His first step is to match your project to your insurance. He suggests keeping the riskier projects separate, noting that from an insurer’s point-of-view, “any project that creates a homeowners association carries a higher potential threat of future litigation.” This leads to his second point: you need to “determine what makes your liability insurer nervous.” In other words, talk with your insurer.
His third point suggests that builders look back and see if there is a pattern of problems that have lead to payouts from your insurer. Keep your insurer happier by making sure these areas don’t continue to be problems. Nor should you look for new problems. He suggests against leading in new technologies.
Three more points deal with being careful about with whom you associate. He tells builders to negotiate their contracts, avoiding clauses that would obligate a builder to “indemnify the owner for the negligent work of others that they did not control.” Avoid subcontractors “with loss patterns that might affect your project and reputation.” Builders should identify “owners with a pattern of suing contractors” adding that risk to the cost of the job. They should also identify “the most effective attorneys and expert witnesses” and get them involved before the litigation starts.
Read the full story…
Insurer Not Entitled to Summary Judgment on Construction Defect Claims
February 10, 2012 — Tred Eyerly, Insurance Law Hawaii
The insurer unsuccessfully moved for summary judgment, contending it had no obligation to defend two related underlying construction defect cases. Amerisure Ins. Co. v. R.L.Lantana Boatyard, Ltd., 2012 U.S. Dist. LEXIS 2466 (S.D. Fla. Jan. 9, 2012).
An engineering report noted design construction defects and deficiencies in visible, physical improvements at The Moorings at Lantana Condominium. In two lawsuits, The Moorings sued the developer, R.L. Lantana Boatyard ("RLLB"), and the contractor, Current Builders of Florida.
Current Builders was insured by Amerisure. RLLB was named as an additional insured under the Amerisure policy.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Preparing for Trial on a Cause of Action for Violation of Civil Code section 895, et seq.
May 10, 2012 — Samir R. Patel, Esq., Lorber, Greenfield, & Polito, LLP
In 2002, the California Legislature enacted the Right to Repair Act (hereinafter “SB-800”), as codified in Title VII of the Civil Code. As set forth in Civil Code section 895, et seq., SB-800 established a set of standards for residential construction, and provides a statutory protocol to address alleged violations of those standards. SB-800 applies to all new single family homes sold after January 1, 2003, and it created its own cause of action governed completely by its own terms, in that in order to state a cause of action under SB-800, a plaintiff may only allege a violation of the Act. (Civ. Code, § 938.) Under Civil Code sections 896, 897, 943, and 944, the Legislature made it clear that it intended to create a single cause of action for construction defects in homes that fall under the purview of SB-800. By passing SB-800, the Legislature eliminated multiple and often redundant or conflicting causes of action, burdens of proof, statutes of limitations, and types of damages that were common in construction defect actions prior to the enactment of the same.
Civil Code section 895, et seq. has significantly changed the landscape of construction defect lawsuits. Yet, for years, the only attention given to the statutes focused solely on the codified pre-litigation process that requires plaintiffs and builders to meet and confer regarding defects and attempt a process to repair the alleged defects before litigation is pursued. A major impediment to the implementation of the pre-litigation procedures has often been that the statutes specifically state that the information obtained during the pre-litigation process is admissible at trial. Hence, through use of the pre-litigation process, plaintiffs’ counsel can engage in a builder funded fishing expedition and later use the information obtained to advance their litigation goals. As such, many builders have chosen to opt out of codified pre-litigation process altogether, an option which the builder can elect within their Purchase and Sale Agreements.
Recently, counsel for builders throughout California have turned their attention to the “exclusive remedy” aspect of SB-800 by seeking, often successfully, to limit plaintiffs to a single cause of action for violation of SB-800. Civil Code section 943 makes clear that a cause of action for violation of SB-800 performance standards is a plaintiff’s sole remedy for a residential construction defect action. Civil Code section 943 states:
Except as provided in this title, no other cause of action for a claim covered by this title or for damages recoverable under 944 is allowed. (Civ. Code, § 943.) Â
The question remains: what is the benefit of requiring plaintiffs to trim down their complaint and eliminate their tried and true common law causes of action, and requiring them to pursue only a single cause of action for violation of SB800?
The construction standards enumerated within SB-800 include fifty-plus functionality standards. On their face, any benefit to pursuing a construction defect action under a single cause of action for violation of SB-800 initially appears trivial at best, in light of the fact that a jury may be very confused with the complexity of the functionality standards set forth within the Civil Code. Nevertheless, Title VII of the Civil Code actually contains numerous provisions that builders can utilize to their benefit throughout the process of construction defect litigation, including during preparation for trial.
First and foremost, counsel for builders can assert numerous affirmative defenses that will be beneficial if the matter proceeds to trial. These affirmative defenses, as codified in Civil Code section 945.5, include mitigation, in whole or in part, for damages caused by: an unforeseen act of nature; a homeowner’s failure to allow reasonable and timely access for inspections and repair under the pre-litigation procedures; the homeowner’s failure to follow the builder’s recommendations and commonly accepted homeowner maintenance obligations; ordinary wear and tear; misuse; abuse; or neglect. Builders should include these affirmative defenses within their responsive pleadings and as trial approaches, prepare appropriate motions in limine and request special jury instructions regarding the same. As frustrated builders and their attorneys are well aware, many construction defect suits result from a homeowner’s failure to properly maintain their property in a manner that is consistent with normal maintenance procedures and guidelines. Furthermore, within the ten year statute of limitations for most defects, ordinary wear and tear is often attributable to numerous deficiencies alleged by plaintiffs. The affirmative defense for a homeowner’s failure to allow inspections and repairs is also vital, as plaintiffs’ counsel may encourage a homeowner to forego the repair and seek monetary damages, allowing plaintiffs’ counsel to ultimately obtain their share of attorney’s fees. Therefore, the SB-800 statutes provide the builder with recourse and distinctive mitigation defenses that were previously and confusingly mixed into tort and contract related defenses. These affirmative defenses can also be utilized by counsel during the cross-examination of plaintiff homeowners and expert witnesses. Defense counsel should fully grasp these defenses and utilize them as defense themes throughout litigation.
As a plaintiff is limited to a single cause of action for violation of SB-800, if defense counsel has failed to properly eliminate excessive tort and contract causes of action prior to trial, a motion for summary adjudication, or at the very least, a motion for judgment on the pleadings should be brought to limit the introduction of evidence outside of a single cause of action for violation of SB-800. Practical judges are always looking for ways to streamline and expedite trials, and they are currently ruling that SB-800 is the exclusive remedy available to plaintiffs. In fact, plaintiffs’ firms in SB-800 matters are now voluntarily limiting their complaints to this one cause of action.
Special jury instructions can also be crafted to limit a jury’s computation of damages pursuant to Civil Codesection 944, which provides the method for computing damages within a construction defect action, as follows:
If a claim for damages is made under this title, the homeowner is only entitled to damages for the reasonable value of repairing any violation of the standards set forth in this title, the reasonable cost of repairing any damages caused by the repair efforts, the reasonable cost of repairing and rectifying any damages resulting from the failure of the home to meet the standards, the reasonable cost of removing and replacing any improper repair by the builder, reasonable relocation and storage expenses, lost business income if the home was used as a principal place of a business licensed to be operated from the home, reasonable investigative costs for each established violation, and all other costs or fees recoverable by contract or statute. (Civ. Code, § 944.) [Emphasis added.]
Civil Code section 944 specifically prohibits recovery for damages outside the scope of its explicit language as it states “the homeowner is only entitled to ... damages for the reasonable value of repairing any violation of the standards set forth in this title....” [Emphasis added.] The statute ultimately provides a “reasonableness” standard for the computation of damages that did not exist when computing damages on traditional common law tort and contract claims. Therefore, defense counsel should prepare special jury instructions to limit evidence of damages introduced at trial to the reasonable value of repairing any violation of the standards, and to exclude any evidence of damages beyond the reasonableness standard. Defense counsel should seize the opportunity to utilize the theme of “reasonableness” when attacking plaintiffs’ allegations and plaintiffs’ proposed repair methodology throughout the discovery process and at trial.
Defense counsel may also prepare a motion in limine or special jury instruction regarding the limitation of evidence regarding defects that did not cause resultant damage. Civil Code section 897 states:
Intent of Standards
The standards set forth in this chapter are intended to address every function or component of a structure. To the extent that a function or component of a structure is not addressed by these standards, it shall be actionable if it causes damage. (Civ. Code, § 897.) [Emphasis added.]
Defense counsel can argue that the introduction of any evidence supporting a claim for construction-related deficiencies that are not enumerated within Civil Code section 896, or for deficiencies where no damage has occurred is prohibited and must be excluded at trial. This requirement of resultant damages is familiar as the general rule was previously established in Aas v. Superior Court (2000) 24 Cal.4th 627, in which the California Supreme Court held that there is no tort recovery for construction defects that have not actually caused property damage. The legislature effectively codified this rule within Civil Code section 897.
A motion in limine can also be crafted to limit expert testimony to the standards enumerated in Civil Code section 896, and to deficiencies that caused damage pursuant to Civil Code 897. The motion in limine can be based upon Civil Code section 943 and the fact that claims for defects in homes which were sold after January 1, 2003 may only be pursued under a single cause of action for violation of SB-800. As such, expert testimony should be controlled by the standards set forth in Civil Code section 896. Furthermore, throughout a construction defect matter, defense counsel should ensure that their experts are well versed with the standards and that they can provide testimony that utilizes the same. Defense counsel’s knowledge of the standards will also be helpful during the cross-examination of plaintiffs’ expert witnesses.
If, despite the efforts of defense counsel, the complaint still has numerous causes of action, or if only some homes fall under the purview of SB-800 while others do not, defense counsel can utilize a motion to bifurcate trial. The motion’s basis is that a cause of action for violation of SB-800 will require the introduction of evidence regarding the violations of the fifty-plus standards, and the tort and contract-based claims would also require the introduction of a wide range of evidence to prove each cause of action. For example, in order to prove the tort causes of action, plaintiffs must prove elements such as: duty, breach, proximate and actual causation, and that the builder placed the homes into the stream of commerce. (See Richards v. Stanley (1954) 43 Cal.2d 60, 63; Kriegler v. Eichler Homes, Inc. (1969) 269 Cal.App.2d 224, 227.) On the contract causes of action, plaintiffs must prove the existence of a valid written contract for the sale of the home, including proof regarding the existence of basic contractual elements such as offer, acceptance, and consideration. (Civ. Code, § 1624 subd. (a); Roth v. Malson (1997) 67 Cal.App.4th 552, 557.) Defense counsel can argue that exposing the jury to elements that may or may not be applicable to all of the homes in the action will complicate and confuse the jury. Thus, concurrently exposing the jury to the SB-800 claims and the non-SB-800 claims will necessitate undue consumption of time, and create the substantial danger of undue prejudice of confusing the issues or misleading the jury.
One of the most important and relevant features of the SB-800 statutes is that they include shortened statutes of limitation as to certain enumerated defects. The codified statutes of limitations apply from the date of “close of escrow,” and are much more definitive than statutes of limitations regarding tort and contract claims. Therefore, they can be utilized within a motion for summary adjudication in cases where only one or a few defects are alleged. For example, under Civil Code section 896, et seq., there is a five year limitation on paint (Civ. Code, § 896, subd. (g)(1)); a four year limitation on plumbing fixtures (Civ. Code, § 896, subd. (e)); a three year limitation on landscaping (Civ. Code § 896, subd. (g)(12)); and a one year limitation on irrigation systems and drainage (Civ. Code, § 896, subd. (g)(7)). The non-SB-800 claims are subject to a four year statute of limitation for patent defects and a ten year statute of limitation for latent defects. (See Code of Civ. Proc., §§ 337.1, 337.15.) The contrast between the statute of limitations for the SB-800 claims and non-SB-800 claims can complicate a matter at trial, further establishing the necessity to limit plaintiffs to a single cause of action for violation of SB-800. Hence, defense counsel should also utilize a motion to bifurcate the statute of limitations issues from the issue of liability if a question of fact exists. If successful on the motion to bifurcate, plaintiff’s counsel will be barred from the introducing evidence at trial regarding a defect where the statute of limitations has run.
Defense counsel should also seek to simplify the construction standards for the jury. Ultimately, by drafting jury instructions and a special verdict form that is easy to navigate, counsel can promote an easy interpretation of the standards enumerated within the Civil Code. The best route for drafting a special verdict form is to draft it as a check-list, similar to a traditional real estate walk-through check-list. By incorporating the shortened statutes of limitations into the special verdict form, defense counsel can effectively frame the case for the jury. The special verdict form should also allow the jury to easily eliminate any claim for damages that is mitigated, in whole or in part, through the codified affirmative defenses. Defense counsel should also consider drafting a trial brief that effectively and simplistically provides the trial court judge with an understanding of the specific defects before the court, and simultaneously notes which Civil Code standards are implicated and the scope of the same. If the trial judge is not well versed in construction defect litigation, defense counsel should be all the more careful in breaking down the parameters and limitations codified within SB-800 for the court.
The strategies outlined within this article are only a few tactics that can be utilized to defend a construction defect suit. Depending on the defect allegations within any particular case, defense counsel should become intimately familiar with Title VII of the Civil Code and use all aspects of the same to their advantage. If not, plaintiffs’ counsel will have the advantage during “court-house step” settlement discussions and at trial.
Printed courtesy of Samir R. Patel, Esq. of Lorber, Greenfield, & Polito, LLP. Mr. Patel can be contacted at spatel@lorberlaw.com.
Court Consolidates Cases and Fees in Soil Construction Defect Case
August 16, 2012 — CDJ Staff
The California Court of Appeals has ruled in Burrow v. JTL Development. JTL Development had appealed a judgement in a construction defect case in which JTL Development and Highland Development were found liable for damage due to homes built on unstable and improperly compacted soil. The two companies were sued by the two sets of homeowners, the Burrows and the Balls, and their cases were consolidated at trial. Each family was awarded $700,000 in damages. This judgement had also been appealed and affirmed by the appeals court. In the current case, an additional $235,800 in cost-of-proof sanctions had been awarded to the two families.
Before the trial, Dale Burrows, Charles Ball, and Laurie Ball “asked JTL and Highland to admit that they ‘approved grading plans’ for the Burrows’ and Balls’ properties; ‘had knowledge that the [properties] contained improperly compacted fill’; ‘had knowledge that the [properties were’ not properly prepared for structures’; and ‘did not provide Plaintiffs with a complete soils report’ prepared by Gorian & Associates.” These were requests 14, 19, 20, and 22. JTL and Highland denied all of these.
At trial, the Burrows and Balls proved that all these were true. JTL and Highland’s geotechnical subcontractor, Gorian & Associates, had “recommended that Highland remove and re-compact the entire tract to a depth of 25 feet.” JTL and Highland did not follow this recommendation, “in order to avoid expense.”
After judgment, the Burrows and Balls moved for $582,587.45 for “attorneys’ fees and costs incurred proving the truth of requests for admission.” JTL and Highland claimed that only Dale Burrows could recover fees, but that also the fees were not recoverable. Joe Lynch of Highland “declared that he always believed the soils under the Burrows and Balls homes were properly compacted.” The Burrows and Balls responded with six identical sets of requests for admissions and the court awarded each of them twenty-five percent of $235,800, with JTL and Highland each responsible for fifty percent.
The appeals court noted that JTL and Highland filed a timely appeal and goes on to notes the four circumstances under which a responding party does not have to pay costs and fees. The court concluded that none of these were met. Instead of waiving the request, JTL and Highland denied the request, stating “without in any manner waiving the foregoing objection, responding party denies the request for admission.”
Nor was the admission “of no substantial importance,” instead the court said that the matters were of “substantial importance,” and the “trial would have been shortened by their admission. Highland and JTL “relied on Gorian when it denied the request,” but the trial court “discredited Lynch’s assertions,” finding that “Highland knew the soil was improperly compacted.”
As all plaintiffs had identical discovery requests, the court rejected the claim that only Dale Burrows was entitled to an award.
Read the court’s decision…
New Web Site Tracks Settled Construction Defect Claims
June 19, 2012 — CDJ Staff
Peter Lissner, a former Nevada homebuilder, has created a new site to help track homes that have been involved in construction defect litigation. His site, housefaxreview.com, collections documentation about homes where claims of construction defects have been made. He told The Builders Magazine concerns about “the number of homes that have been served notices, received compensation, yet the homes weren’t repaired.” On the site, the creator is identified as “a family owned builder.” According to the site, “the builder had no claims until the neighborhood reached the statutory claims limit 10 years.”
Lissner also claims that in many cases, after settling construction defect lawsuits, the homeowners sell to subsequent buyers without disclosing the lawsuit or their failure to repair. “Who is going to let the new homeowner know about the issue?” he asks.
Documents on the site are priced according to their relevance. Lissner notes that those who provide documents to the site will receive free access.
Read the full story…
Florida Appeals Court Rules in Favor of Homeowners Unaware of Construction Defects and Lack of Permits
December 9, 2011 — CDJ Staff
The Florida Court of Appeals has ruled that a homeowner is not liable for defects in unpermitted alterations, reversing a lower court’s decision in Jensen v. Bailey. The Jensens sold their house to the Baileys. During the sale, the Jensens filled out a property disclosure statement, checking “no” to a question about “any improvement or additions to the property, whether by your or by others that have been constructed in violation of building codes or without necessary permits.”
After moving in, the Baileys discovered several problems with the home. One involved a defective sewer connection leading to repeated backups. The Baileys also found problems with remodeling the Jensens had done in the kitchen, master bath, and bedroom. The remodeling work was not done with required permits nor was it up to code.
The court noted that an earlier case, Johnson v. Davis, established four criteria: “the seller of a home must have knowledge of a defect in the property; the defect must materially affect the value of the property; the defect must not be readily observable and must be unknown to the buyer; and the buyer must establish that the seller failed to disclose the defect to the buyer.” The court found that the first of these criteria was crucial to determining the case.
In the Johnson ruling, the then Chief Justice dissented, fearing that the courts “would ultimately construe Johnson’s requirement of actual knowledge to permit a finding of liability based on constructive knowledge,” quoting Justice Boyd, “a rule of constructive knowledge will develop based on the reasoning that if the seller did not know of the defect, he should have known about it before attempting to sell the property.” The Appeals Court concluded that the lower court hit this point in ruling on Jensen v. Bailey.
Citing other Florida cases, the court noted that the Johnson rule does require “proof of the seller’s actual knowledge of the defect.” The court cited a case in which it was concluded that the seller “should have known” that there was circumstantial evidence was that the seller did know about the defects, as the seller had been involved in the construction of the home.
In the case of the Jensens, the lower court concluded that they did not know that the work was defective, nor did they know that they were obligated to obtain permits for it. The Appeals Court found this one fact sufficient to reverse the decision and remand the case to the lower court for a final judgment in favor of the Jensens.
Read the court’s decision…
Policing Those Subcontractors: It Might Take Extra Effort To Be An Additional Insured
June 14, 2011 — Douglas Reiser, Builders Council Blog
I just came across a case that I think truly paints the insurance dilemma for contractors. Thanks to this recent Illinois case, I don’t have to make up any factual scenarios—so kudos to Attorney Robert Boylan for posting it.
In reading over my RSS feeds this weekend, I noticed a great writeup on long-time blogger Josh Glazov’s Construction Law Today. Attorney Robert Boylan’s post describes a recent Illinois case where a general contractor was denied its additional insured status on a second-tier subcontractor’s insurance. The reason for the denial: the general contractor failed to procure an agreement in writing with the second-tier subcontractor, requiring it to be listed as an additional insured.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Geometrically Defined Drainage Cavities in EIFS as a Guard Against Defects
July 10, 2012 — CDJ Staff
The blog Stucco & Insulation Contractor writes up some details on a “relatively new modification to modern Exterior Insulation Finish Systems,” known as “geometrically defined insulation boards.” They note that the insulation has grooves cut in the back to provide a route for water to drain, instead of getting trapped. They note that when EIFS is installed by a skilled applicator, this is unnecessary. However, with less experienced (and cheaper) installers, problems are more likely.
By cutting these channels, the application of EIFS is rendered “idiot proof,” as they note. Their preference would be that EIFS installers take the time to do the job right, but call this “a step in the right direction.”
Read the full story…
Building Boom Leads to Construction Defect Cases
August 2, 2012 — CDJ Staff
Professor Evan McKenzie of the University of Illinois at Chicago says that rise of construction defect litigation in the Las Vegas area followed the same pattern it did in other places, according to an article in the Las Vegas Review Journal. “Step one,” according to Professor McKenzie, “there was this enormous growth in construction. Then these attorneys began to swarm in from all over, especially Southern California.” McKenzie noted that during a building boom, construction “outpaces the ability of building inspectors to do their job.”
But, despite his contention that “rapid growth in housing stock” leads to “shoddy construction,” another problem of growth was that “eventually there were too many lawyers chasing too many condominium complexes and subdivisions.” What came next was that “attorneys start coming up with cases that really aren’t good cases.” It’s in the interest of these attorneys that HOA boards sue.
Read the full story…
Good Signs for Housing Market in 2013
December 20, 2012 — CDJ Staff
Dan Green, a loan officer at Waterstone Mortgage, is optimistic about the construction market in 2013. He notes that the rise in building permit, housing starts, and housing completions are all good signs. Mortgage rates are still low, making these new homes attractive to buyers.
Read the full story…