Insurer’s Discovery Requests Ruled to be Overbroad in Construction Defect Suit
October 28, 2011 — CDJ Staff
The US District Court has ruled in the case of D.R. Horton Los Angeles Holding Co. Inc. v. American Safety Indemnity, Co. D.R. Horton was involved in a real estate development project. Its subcontractor, Ebensteiner Co., was insured by ASIC and named D.R. Horton as an additional insured and third-party beneficiary. D.R. Horton, in response to legal complaints and cross-complaints, filed for coverage from ASIC under the Ebensteiner policy. This was refused by ASIC. ASIC claimed that “there is no potential coverage for Ebensteiner as a Named Insurer and/or D.R. Horton as an Additional Insured.” They stated that “the requirements for coverage are not satisfied.”
The case same to trial with the deadline for discovery set at March 1, 2011. ASIC stated they were seeking the developer’s “job file” for the Canyon Gate project. D.R. Horton claimed that ASIC’s discovery request was overbroad and that it would be “unduly burdensome for it to produce all documents responsive to the overbroad requests.”
D.R. Horton did agree to produce several categories of documents, which included:
“(1) final building inspection sign-offs for the homes that are the subject of the underlying litigation;(2) an updated homeowner matrix for the underlying actions; (3) the concrete subcontractor files; (4) the daily field logs for D.R. Horton’s on-site employee during Ebensteiner’s work; (5) documents relating to concrete work, including documents for concrete suppliers; (6) documents relating to compacting testing; (7) documents relating to grading; and (8) D.R. Horton’s request for proposal for grading”
The court found that the requests from ASIC were overbroad, noting that the language of the ASIC Request for Production of Documents (RFP) 3-5 would include “subcontractor files for plumbing, electric, flooring, etc. - none of these being at issue in the case.” The court denied the ASIC’s motion to compel further documents.
The court also found fault with ASIC’s RFPs 6 and 7. Here, D.R. Horton claimed the language was written so broadly it would require the production of sales information and, again, subcontractors not relevant to the case.
Further, the court found that RFPs 8, 10, 11, and 13 were also overbroad. RFP 8 covered all subcontractors. D.R. Horton replied that they had earlier complied with the documents covered in RFPs 10 and 11. The court concurred. RFP 13 was denied as it went beyond the scope of admissible evidence, even including attorney-client communication.
The court denied all of ASIC’s attempts to compel further discovery.
Read the court’s decision…
Colorado Senate Bill 12-181: 2012’s Version of a Prompt Pay Bill
May 10, 2012 — W. Berkeley Mann, Jr., Higgins, Hopkins, McLain & Roswell, LLC
A potentially important legislative bill has been introduced in waning days of the 2012 legislative session, which would change many of the commercial practices that prevail in the construction industry. Senate Bill 12-181 applies to all building and construction contracts and would prohibit any contract provision that requires a contractor, subcontractor, or supplier to waive their lien in advance of payment. It also would ban any “choice of law” provisions that make a Colorado-based construction contract subject to enforcement only in another state, or under the laws of another state.
The bill also seeks to change many existing commercial practices between contractors, subcontractors, and suppliers. It is presently unclear whether the bill allows parties to contract around these payment procedure provisions, or whether these requirements are simply “gap filling” provisions that pertain if there are no written contract terms specified on these issues. The proposed statute would mandate payment to subcontractors and material suppliers due within seven days in the absence of a dispute about the work or materials being billed. After this seven day period, the bill would require the payment of interest at the rate of 1.5% monthly (18% annually). In any later suit for payment, the creditor would also be able to collect reasonable attorneys’ fees. Additionally, non-payment to a subcontractor or supplier who is later found to be entitled to prompt payment would excuse the subcontractor or supplier, and its surety bond provider, from any further performance under the contract.
It is presently unclear whether the bill allows parties to contract around these payment procedure provisions. However, it is clear that the bill provides some leeway for change orders, as long as there is (1) negotiation in good faith between the parties concerning the changed scope of work, and (2) a 50% payment of a subcontractor’s costs by the changing party within 30 days of the change order work being done. Additionally, the bill provides for retainage, but in an amount of no more than 5%.
The bill is presently set for hearing before the Colorado Senate Committee on Business, Labor, and Technology Committee on May 2, 2012 at 1:30 p.m.
Read the full story…
Reprinted courtesy of W. Berkeley Mann, Jr. of Higgins, Hopkins, McLain & Roswell, LLC. Mr. Mann can be contacted at mann@hhmrlaw.com.
Five Years of Great Legal Blogging at Insurance Law Hawaii
December 9, 2011 — CDJ Staff
Our congratulations to Tred Eyerly who has been blogging at Insurance Law Hawaii for five years now. Over the years, he has posted more than five hundred posts and has provided us all with fascinating insights into the laws on insurance coverage. He describes his blog as “a commentary on insurance coverage issues in Hawaii and beyond.” We are grateful that the “beyond” has just in the last few weeks included Colorado, Illinois, Washington, Minnesota, and Rhode Island (about as far from the island of Hawaii as you can get).
You can read his blog at Insurance Law Hawaii.
Summary Judgment in Construction Defect Case Cannot Be Overturned While Facts Are Still in Contention in Related Cases
September 9, 2011 — CDJ Staff
The Alabama Court of Civil Appeals has dismissed an appeal of a summary judgment in the case Bella Investments, Inc. v. Multi Family Services, Inc. MFS was hired by Bella to be the general contractor for a hotel in Gardendale, Alabama. MFS hired various subcontractors, including the architect for the project. After completion of the hotel in April, 2006, Bella made requests for MFS to repair cracked floor tiles.
In August, 2008, Bella sued MFS, the architect, and various fictitiously named defendants. Subsequently, Bella amended its complaint, naming some of the fictitiously named defendants.
MFS in turn claimed that Bella’s claims were void under the statute of limitations and that Bella was in beach of contact by failing to pay MFS the full amount owed. MFS moved for summary judgment under the statute of limitations, which was granted by the court.
Bella requested that the court “alter, amend, or vacate its summary judgment order.” When this was denied, Bella appealed to the Alabama Supreme Court, which transferred the appeal to the Court of Civil Appeals. The Court of Appeals refused to vacate the summary judgment as claims that form part of the case against MFS are also part of Bella’s claims against the other defendants. For this reason, the court upheld the summary judgment.
Read the court’s decision…
Ohio Adopts Energy-Efficient Building Code
June 19, 2012 — CDJ Staff
In a compromise between environmental groups, who were looking for stricter standards, and homebuilders, who were trying to contain building costs, the state of Ohio has adopted buildings codes that will increase the energy efficiency of new homes. The estimated costs are about $1,100 with estimated annual savings of $230. According to Corey Roblee of the International Code Council, “It’s something needed in the state of Ohio.”
The Ohio Home Builders Association opposed a proposal to adopt the guidelines of the International Code Council. Builders will be able to either follow the ICC guidelines or they can use the Ohio guidelines to meet the same energy efficiency. Vincent Squillace, the executive vice president of the OHBA, said, “We came up with an equivalent code that’s more strict but is about $2,000 cheaper per home to implement than the original code.”
The new code will require that at least 75% of lighting must be high efficiency, increases the degree of insulation, and specifies more efficient windows, among other changes.
Read the full story…
Webinar on Insurance Disputes in Construction Defects
July 10, 2012 — CDJ Staff
Seth Lamden, of the firm Neal Gerber Eisenberg will be presenting a webinar on “Insurance Coverage Disputes in Construction Defects” on July 17, 2012 at 1 p.m. EDT. Mr. Lamden’s presentation will focus on “handling both the construction and insurance components of construction defect claims.” He will be discussing recent case law and new insurance products. The presentation will present information on evaluating various types of insurance policies, explaining common issues, contract requirement, and the economic loss doctrine. Mr. Lamden will advise attendees on how to avoid getting into a construction defect case. He will conclude his presentation with a brief question-and-answer session.
Read the full story…
Residential Construction Down in San Diego
September 13, 2012 — CDJ Staff
While new home construction is on the rise in some parts of the country, San Diego has seen a fall, comparing the first seven months of 2012 with the first seven months of 2011, dropping nine percent, according to an article in the San Diego Business Journal. The news isn’t all bad, since although July residential construction dropped sharply, nonresidential construction increased thirty-six percent.
Read the full story…
Construction Defect Case Not Over, Despite Summary Judgment
November 7, 2012 — CDJ Staff
The Supreme Court of Oregon has concluded in an en banc decision that a motion to reconsider a summary judgment is not a motion for a new trial. In coming to their conclusion the court overturned an earlier Oregon Supreme Court case, Carter v. U.S. National Bank. Although the decision does not bear on construction defects, the underlying case did. Due to the decision, these claims can now be evaluated in a trial.
The case, Association of Unit Owners of Timbercrest Condominiums v. Warren, came about after an apartment complex was converted into condominium units. The developers hired Big Al’s Construction for some of the remodeling work. The condominium association later sued the developer and the contractor over claims of construction defects. The defendants filed a motion for summary judgment, which the court granted.
But that wasn’t the end of things. The plaintiff soon filed a “motion to reconsider,” noting that the summary judgment seemed to be in conflict with both law and other recent rulings, and additionally, the grounds for the decision were not in the order. The judge then notified the parties that the court had “pulled the trigger too quickly” and had seven questions for the parties to answer.
The court dismissed all claims against the defendants. The defendants filed their responses, objecting that that “‘there is no such thing’ as a motion for reconsideration.” Further, while “the rules do allow for post-judgment review of pre-judgment rulings through a motion for a new trial,” the plaintiffs had not filed for a new trial. But did they need one? They did file an appeal.
The judge in the case admitted that there was no such thing as a motion to reconsider, and felt bad about prematurely signing the judgment. The case was sent to the Court of Appeals to determine if the motion to reconsider was a request for a new trial. The Court of Appeals concurred.
In reviewing the decision, the Oregon Supreme Court concluded that there were a maximum of three questions to address. Was the motion for reconsideration a motion for a new trial? If so, was the later notice of appeal premature? And if so, was the plaintiff required to file a new appeal? The court determined that the answer to the first question was no.
Prior decisions pointed to the conclusion “that a motion for reconsideration of a summary judgment amounts to a motion for a new trial,” but here the court concluded that “our prior cases erred,” and turned to the summary judgment rule for clarification. The court noted that “the rule contemplates that summary judgment and trial are separate and distinct events.” With this conclusion, the Oregon Supreme Court remanded the case to the Court of Appeals for further proceedings.
Read the court’s decision…
Builder Waits too Long to Dispute Contract in Construction Defect Claim
May 10, 2012 — CDJ Staff
The Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.
The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.
The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.
In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.
The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.
A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”
Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.
Read the court’s decision…
Steps to Defending against Construction Defect Lawsuits
July 21, 2011 — CDJ Staff
Writing in Claims Journal, Bryan Rendzio notes that the decline in construction has not been matched by a decline in construction defect lawsuits over condominiums. He reviews the ways in which lawyers representing developers can help protect their clients. He identifies four important considerations in defending developers from claims of construction defects.
He advocates a careful review of the contract. “Under a breach of contract claim, the insured’s duties to the party who brought the claim against the insured flow from the contract. Commonly, construction contracts limit the scope of recoverable damages, such as by waiving consequential damages.’
The next step, according to Rendzio is to check of a settlement agreement is already in place, noting that these are “a familiar occurrence in the construction industry, regardless of any lawsuits having been filed.”
He considers the statute of repose “the single-most decisive weapon an insured possesses in its arsenal during a condo defect lawsuit.” He notes that no lawsuits can be brought for construction defects after the end specified by the statute of repose, and if a lawsuit is brought beforehand, no additional parties can be named once the statute has taken effect.
Finally, he warns adjusters to be suspicious when a condo association requests contractual indemnification. He notes that the pitfall in this is that developers and the subsequent condominium association often have similar names, given the theoretical example of a condo project built by “Fake Lakes LLC” and later run by the “Fake Lakes Condominium Association.” Writing in regards to Florida law, he notes that condominium associations do not have successor interest in contracts developers made with contractors.
Read the full story…
LEED Certified Courthouse Square Negotiating With Insurers, Mulling Over Demolition
June 6, 2011 — Douglas Reiser in the Builders Counsel Blog
Apparently, Courthouse Square is still unresolved. The County hasnow hired an attorney to handle its insurance claim against Affiliated FM. Is there a lawsuit coming?
Right now, no lawsuit is expected. According to officials, the insurer has been acting in good faith. But, its been quite a while since Salem officials learned that the Courthouse Square building had significant concrete issues that would result in probable demolition of the LEED certified building.
If you have yet to hear about Courthouse Square, let me fill you in briefly. The Salem building was substantially completed in 2000 and LEED certified by the US Green Building Council in 2002. The project cost more than $30 Million to complete and the building was revered for its innovation as a crowning achievement for city leaders.
But, structural problems in the building’s core were discovered as early as 2002, writes Chris Cheatham of Green Building Law Update. Final tests earlier in the year, determined that the building had to be vacated. The building has been clear since July 2010.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Sometimes It’s Okay to Destroy Evidence
August 17, 2011 — CDJ Staff
The Minnesota Supreme Court has ruled in the case of Miller v. Lankow that Mr. Miller was within his rights to remediate his home, even though doing so destroyed the evidence of water intrusion.
Linda Lankow built a home in 1992. In 2001 or 2002, Lankow discovered a stucco problem at the garage which she attributed to moisture intrusion. She asked the original contractor to fix the wall. In 2003, Lankow attempted to sell her home, but the home inspection revealed fungal growth in the basement. Lankow made further repairs, including alterations to the landscaping.
In 2004, Lankow put her house on the market once again and entered into an agreement with David Miller. Miller declined to have an independent inspection, as the home had been repaired by professional contractors.
In 2005, Miller put the house on the market. A prospective buyer requested a moisture inspection. The inspection firm, Private Eye, Inc. found “significant moisture intrusion problems.”
Miller hired an attorney who sent letters to the contractors and to Lankow and her husband. Lankow’s husband, Jim Betz, an attorney, represented his wife and sent a letter to Miller’s attorney that Miller had declined an opportunity to inspect the home.
In 2007, Miller’s new attorney sent letters to all parties that Miller had decided to begin remediation work on the house. All stucco was removed. Miller then filed a lawsuit against the prior owners, the builders, and the realtors.
Two of the contractors and the prior owners moved for summary judgment on the grounds that Miller had spoliated evidence by removing the stucco. They requested that Miller’s expert reports be excluded. The district court found for the defendants and imposed sanctions on Miller.
The Minnesota Supreme court found that “a custodial party’s duty to preserve evidence is not boundless,” stating that “it may be particularly import to allow remediation in cases such as the one before us.” Their reasoning was that “remediation of the moisture intrusion problem in the home may be necessary, even essential, to address immediate health concerns.”
Given that Miller needed to remediate the problem in order to continue living there, and that he had given the other parties a “full and fair opportunity to inspect,” the court found that he was within his rights. The court reversed the judgment of the lower court and remanded it to them for review.
Read the court’s decision…
Massachusetts Couple Seek to Recuse Judge in Construction Defect Case
September 30, 2011 — CDJ Staff
After seeing their $1 million jury award overturned on appeal by a judge who called the award “against the weight of evidence and likely due to misapprehension, confusion or passion,” Kathryn and Christian Culley are seeking to have him removed from the case. The Massachusetts Supreme Judicial Court has rejected their claim.
The Culleys claim that Judge Thomas R. Murtagh’s decision was influence by him membership in the Andover Country Club which is represented by the opposing counsel in their construction defect case. Justice Margot G. Botsford had denied the Culley’s request, ruling that they had other remedies available to them.
The SJC noted in their ruling that if the Culleys are alleging judicial misconduct a request must be made to the Commission on Judicial Conduct. Their lawyer plans to file a new motion for recusal with the SJC.
Read the full story…
Largest Per Unit Settlement Ever in California Construction Defect Case?
October 28, 2011 — CDJ Staff
BusinessWire reports that the Chelsea Court Homeowners Association has settled their construction defect case for $5.4 million. That works out to $169,000 per unit, which BusinessWire describes as “California’s largest per-unit recovery known to be on record to date.”
Most of the money in the settlement is coming from insurance companies for the builder and thirteen subcontractors. Issues included roof and window leaks, deck failures, and unsafe walkways.
Read the full story...
Las Vegas Home Builder Still in Bankruptcy
October 23, 2012 — CDJ Staff
American West Development attempted to exit Chapter 11 bankruptcy on September 27, but their plan was turned down by U.S. Bankruptcy Court Judge Mike Nakagawa. According to the Las Vegas Review-Journal, Judge Nakagawa rejected the plan over a trust fund for construction defects. America West’s attorney said they were hoping to complete the process by the end of the year.
Under approved portions of the plan, America West’s owner, Lawrence Canarelli, will retain control of the corporation, although he must contribute $10 million into the firm and an additional $1.5 million into the fund for construction defects. America West faces charges for construction defects reported in the broad range of “less than $20 million” to “as much as $80 million.”
Read the full story…
FHA Lists Bridges and Overpasses that May Have Defective Grout
September 13, 2012 — CDJ Staff
The Federal Highway Administration has released a list of bridges and overpasses that may be prone to corrosion problems due to grout that was in chlorides when it was supposed to be completely free of them. Currently, the FHA is working with state departments of transportation to determine if the defective grout was indeed used on additional bridges and overpasses. The initial FHA list of structures determined to have been built with the defective grout lists thirty-four sites, of which four are in Ohio, the largest number for any state.
California contains only one such site, the intersection of the 55 and 405 freeways, one of the few items on the list not designated as a bridge.
Read the full story…
Couple Sues Attorney over Construction Defect Case, Loses
June 10, 2011 — CDJ Staff
The California Court of Appeals has ruled against a couple who sued their lawyer, after they were unhappy with the results of a construction defect case. Craig and Jeanne Petrik sued Mahaffey and Associates for legal malpractice and breach of contract. Their lawyer, Douglas L. Mahaffey, had settled their case for $400,000. The Petricks claimed Mahaffey did not have the authority make an offer to compromise.
In the original case, Mahaffey held back the $400,000 awarded in the settlement until he and the Petricks came to terms on how much of that was owed to Mahaffey. The lower court concluded that the Petricks were due $146,323,18. The jury did not agree with the Petrik’s claim that conditions had been met in which Mahaffey would not be charging them costs.
Judges O’Leary and Ikola wrote the opinion, with the third judge on the panel, Judge Bedworth offering a dissent only on their view of the cost waiver clause.
Read the court’s opinion
Water Is the Enemy
August 16, 2012 — CDJ Staff
So says Melissa Mitchell, writing in the blog of Community Association Consultants. She cites the nightmare scenario of “an unseen presence lurking behind the walls.” Not a horror movie, but water intrusion, which she notes can cause hundreds of thousands of dollars in damage. Eric Hoff, of Western Architectural, is quoted that “it only takes a hole one-eighth inch diameter in a building’s exterior to allow the intrusion of 35 gallons of water over twelve months.” Destructive testing on a building in in the Pacific Northwest revealed that water intrusion had lead to structural failure of the building. The wet wood had made a home for carpenter ants. Repairs exceeded $100,000.
Mitchell notes that “deferred maintenance can be costly” and cites the importance of preventative maintenance or the development of a maintenance plan. She concludes that “if you own or are responsible for maintaining a condominium complex, apartment building or commercial structure, it’s simply good business sense to have a building envelope assessment conducted by experts in the field.”
Read the full story…