Late Filing Contractor Barred from Involving Subcontractors in Construction Defect Claim
March 1, 2012 — CDJ Staff
The Colorado Court of Appeals looked at that state’s Construction Defect Action Reform Act in determining if a general contractor could add subcontractors as third-party defendants to a construction defect lawsuit. Shaw Construction, LLC was the general contraction of the Roslyn Court condominium complex, and was sued by the homeowners’ association in a construction defect case. United Builder Services was the drywall subcontractor on the project. MB Roofing had installed roofs, gutters, and downspouts. The certificate of occupancy for the last building was issued on March 10, 2004. The project architect certified completion of all known remaining architectural items in June, 2004.
The HOA filed a claim against the developers of the property on January, 21, 2009. A week later, the HOA amended its complaint to add Shaw, the general contractor. Shaw did not file its answer and third-party complaint until March 29, 2010, sending its notice of claim under the CDARA on March 30.
The subcontractors claimed that the six-year statute of limitations had ended twenty days prior. Shaw claimed that the statute of limitations ran until six years after the architect’s certification, or that the HOA’s suit had tolled all claims.
The trial court granted summary judgment to the subcontractors, determining that “substantial completion occurs ‘when an improvement to real property achieves a degree of completion at which the owner can conveniently utilize the improvement of the purpose it was intended.’”
The appeals court noted that “Shaw correctly points out that the CDARA does not define ‘substantial completion.’” The court argued that Shaw’s interpretation went against the history and intent of the measure. “Historically, a construction professional who received a complaint responded by ‘cross-nam[ing] or add[ing] everybody and anybody who had a part to play in the construction chain.’” The court concluded that the intent of the act was to prevent unnamed subcontractors from being tolled.
The court further rejected Shaw’s reliance on the date of the architect’s certification as the time of “substantial completion,” instead agreeing with the trial court that “the architect’s letter on which Shaw relies certified total completion.”
The appeals court upheld the trial court’s determination that the statute of limitation began to run no later than March 10, 2004 and that Shaw’s complaint of March 29, 2010 was therefore barred. The summary judgment was upheld.
Read the court’s decision…
Court Grants Summary Judgment to Insurer in HVAC Defect Case
August 4, 2011 — CDJ Staff
The US District Court in Colorado has determined in the case of RK Mechanical, Inc. v. Travelers Property Casualty Company of America that Travelers did not breach its insurance contract when it refused to cover RK Mechanical.
RK Mechanical performed an HVAC installation for a residential project for which J.E. Dunn Rocky Mountain was the general contractor. As part of the work, RK “installed approximately one hundred seventy-one CPVC flanges, which were manufactured by Charlotte Pipe and Foundry Company.” Two of these flanges failed in June, 2009 leading to water damage. RK replaced the cracked flanges and engaged in water remediation. “Travelers paid Dunn and RK for the costs associated with the water damage associated with the Flange Failure.” The court notes that Travelers did not pay for the cracked flanges, however.
Subsequently, RK examined the remaining flanges, finding many cracked ones. These were replaced with new ones. Later, all the Charlotte flanges were replaced with ones from another manufacturer. RK applied for coverage.
All sides brought in their experts: “Microbac Laboratories, Inc. prepared a report on behalf of RK concluding that the Flange Failure was due, in part, to an assembly or workmanship defect in addition to manufacturing defects in the flanges. Higgins & Associates prepared a report on behalf of Travelers concluding that the flanges failed due to improper installation. Plastic Failure Labs prepared a report on behalf of the flange manufacturer concluding that the flanges failed due to improper installation by RK.”
At this point, Travelers denied coverage. RK sued alleging that the coverage for flange failure and water damage implicitly includes mitigation costs. The court rejected this claim, noting it would do so even if Travelers had paid for the replacement of the first two flanges. Nor did the court find that replacement of the faulty flanges is not "a covered cause of loss." RK also argued that as it was required to mitigate, Travelers was obligated to cover costs. However, the court found that “the mitigation costs expended by RK were not incurred in an effort to avoid damages from a potential breach of contract by Travelers.” The court additionally noted that despite RK’s claims, the Colorado courts have not found a common law duty to mitigate. Finally, the court found that the exclusions in the policy were not in violation of public policy.
Read the court’s decision…
Recent Case Brings Clarity and Questions to Statute of Repose Application
August 16, 2012 — Douglas Reiser, Builders Counsel
I have often chatted about the Washington Statute of Repose on this blog. The Statute of Repose prevents construction claims, for the most part, from being raised 6 years from the date of substantial completion or termination. Well, a recent Court of Appeals case dove deep into the specific determinative factors that tell us when to start the clock. It certainly raises questions about how long we really have to file suit.
The Statute of Repose has been a frequent topic here, so I will simply direct you to my prior post for further information on how this law works. A recent post was published about a lawsuit that might raise some questions about when and how the clock begins to roll, and claim periods begin to diminish.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
JDi Data Introduces Mobile App for Litigation Cost Allocation
October 23, 2012 — CDJ Staff
JDi Data of Fort Lauderdale, Florida has announced that they are about to release a mobile app for their Vendor Cost Control service. Their mobile app is a web app, and so can be used by customers on the iOS, Android, or Blackberry platforms. It provides a secure link to their database with no risk of releasing proprietary information. JDi Data notes that their product will allow users to “track their full subscribed case listings,” give them “easy access to carrier allocations, payments, and outstanding balances reports,” and to “call or email case managers directly from their mobile application.
James DeRosa, the founder of JDi Data says that “pushing the boundaries of technology has enabled us to further our goal of providing credible reporting and cost allocation expertise to insured, carriers and the legal community.”
Read the full story…
Court Orders House to be Demolished or Relocated
April 26, 2011 — April 26, 2011 Beverley BevenFlorez - Construction Defect Journal
Decision Affirmed in Central Arkansas Foundation Homes, LLC v. Rebecca Choate
The Arkansas Court of Appeals affirmed the decision by the trial court in Central Arkansas Foundation Homes, LLC v. Rebecca Choate. In the trial case, Central Arkansas Foundation Homes (CAFH) sought payment for a home built for Choate, while Choate alleged that the builders committed multiple construction defects including using the wrong foundation materials and positioning the house in the wrong direction.
After the house was built, CAFH contacted Choate regarding payment, however, Choate alleged that the finished product did not match the contract. “ After CAFH completed construction, it obtained permanent home financing for Choate and tried to contact her to close the transaction. Choate did not respond until October 2005, when she sent CAFH a list of alleged construction defects, including that the house was facing in the wrong direction; that it was not built on a slab; and that the fireplace, garbage disposal, driveway, and storage area were missing. CAFH replied to Choate in writing, telling her that she had until January 6, 2006, to close on the house or CAFH would sell it. The correspondence enclosed worksheets showing that the amount Choate would owe at closing exceeded $94,000, which included interest that had accrued on the as-yet unpaid construction loan.”
Initially, the court found in favor of CAFH. “On April 18, 2007, Choate’s attorney withdrew from representing her. Soon thereafter, CAFH’s attorney asked the court to set a final hearing on the case. The attorney purportedly sent Choate a letter by regular mail on May 15, 2007, advising her that the case was set for trial on July 9, 2007. Choate, however, did not appear. CAFH did appear, and its general manager, John Oldner, testified to events leading up to the case and the amount of damages claimed. According to Oldner, the interest on the construction loan had accrued to the point that CAFH now sought $104,965.88 from Choate. The court found in favor of CAFH and entered judgment for that amount, plus attorney fees, on July 18, 2007. The court ruled that CAFH could sell the house and either remit any excess to Choate or look to Choate for the deficiency if the sales price did not cover the judgment.”
However, Choate successfully argued that she did not receive notice of the trial. A new trial was ordered, and the outcome was quite different. “On June 6, 2008, the circuit court entered judgment for Choate, ruling that the house was not in substantial compliance with the parties’ contract and that the contract should be rescinded. The court found that the house suffered from numerous construction defects, that the contract contemplated a slab rather than a concrete-pier foundation, and that CAFH ignored Choate’s complaints that the house was facing the wrong way. The judgment directed CAFH to hold Choate harmless on the construction loan, to deed Choate’s two acres back to her, and to remove the house from Choate’s property.”
The Court of Appeals “found that Choate would be unjustly enriched by retaining the benefit of the septic systems and utility lines that CAFH installed on her land. The court therefore awarded $5340 to CAFH as a quantum-meruit recovery for the value of that work. CAFH contends that the award is not sufficient, but we see no clear error.” In the end, the Court of Appeals provided this reason for declining to reverse the trial court’s decision: “The court in this case apparently concluded that the house constructed by CAFH was so fundamentally at odds with Choate’s contractual expectations that she was not unjustly enriched and should simply be, as nearly as possible, returned to the status quo ante. Accordingly, the court ordered the house removed from her property and permitted CAFH to either relocate the house or salvage the house’s materials and unused appliances. We decline to reverse the court’s weighing of the equities in this manner.”
Read the court’s decision…
Bound by Group Builders, Federal District Court Finds No Occurrence
August 11, 2011 — Tred Eyerly, Insurance Law Hawaii
The homeowners sued their contractor, alleging the contractor had defectively constructed and failed to complete their home.  State Farm Fire and Casualty Co. v. Vogelgesang, 2011 U.S. Dist. LEXIS 72618 (D. Haw. July 6, 2011). The homeowners' complaint pled, among other things, damage caused by breach of contract and negligence. State Farm agreed to defend under a reservation of rights.
State Farm filed suit in federal court for declaratory relief. Judge Mollway granted State Farm's motion for summary judgment. Relying on the Hawaii Intermediate Court of Appeal's decision in Group Builders, Inc. v. Admiral Ins. Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010), Judge Mollway determined that the claims asserted in the underlying litigation arose from the contractor's alleged breach of contract.  Group Builders held that breach of contract claims based on allegations of shoddy performance were not covered under CGL policies.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Hilton Grand Vacations Defect Trial Delayed
October 23, 2012 — CDJ Staff
A settlement agreement between Conti Electric and Westgate Resorts has lead to a delay in starting the trial over construction defect claims and billing disputes over Hilton Grand Vacations a time share tower in Las Vegas. According to the Las Vegas Review-Journal, the dispute includes claims of $23.3 million owed to the general contractor against which the developer has placed $30 million in construction defect claims.
Read the full story…
Ensuing Loss Provision Does Not Salvage Coverage
December 9, 2011 — Tred R. Eyerly, Insurance Law Hawaii
Water intrusion caused by a construction defect was not covered under the all risk policy’s ensuing loss provision. See Friedberg v. Chubb & Son, Inc., 2011 U.S. Dist. LEXIS 123582 (D. Minn. Oct. 25, 2011).
Extensive water damage was discovered in the insureds’ home when a small hole in the exterior wall was being repaired. Chubb’s adjuster and an expert found water intrusion causing rot, mold, and damage to the home’s wood framing and insulation. Chubb denied coverage because water intruded through the roof and wall, resulting in gradual deterioration. The insureds filed suit.
The policy excluded coverage for construction defects, but insured "ensuing covered loss unless another exclusion applies."
The court agreed there was a prima facie case for coverage because the home suffered a physical loss.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Utah Construction Defect Claims Dependant on Contracts
July 10, 2012 — CDJ Staff
An owner who wants to sue a subcontractor directly may find limited ability to do so under Utah court decisions. Writing on the JDSupra site, Stewart O. Peay and Mark O. Morris of Snell & Wilmer discuss the distinction the Utah courts make between contractor (with whom an owner has direct contracts) and subcontractors (with whom an owner does not). In the Utah courts, construction defect claims must be based on contract, rather than tort. With no contract, there is no way to pursue claims against a subcontractor alone.
They note that the Utah couts do not “accept negligence and negligent misrepresentation claims that many other jurisdictions embrace.” They recommend that in setting up contracts for a construction project, owners should ensure that they are provided with “third-party beneficiary rights to purse claims against subs.” They suggest that “the owner may require his generals to include language in the various subcontracts that incorporates some or all of the terms of the prime contract into the subcontracts.” Additionally they suggest that the owner “require the general to include ‘flow down’ provisions in the various subcontracts.”
Read the full story…
Renovation Contractors: Be Careful How You Disclose Your Projects
December 9, 2011 — Derek J. Lindenschmidt, Colorado Construction Litigation
In Palu and Beyer v. Toney, 2011 WL 2560249 (Bankr. D. Colo.), the United States Bankruptcy Court for the District of Colorado determined that a Colorado District Court order granting summary judgment in favor of plaintiff home buyers was binding on the Bankruptcy Court in the defendant contractor’s bankruptcy proceeding based on issue preclusion.
Pertinent to this column is the subject matter of the summary judgment motion: Colorado’s Seller’s Property Disclosure (Form LC-18-5-04). In the underlying state court action, the plaintiff home buyers filed a motion for summary judgment contending that the defendant contractor represented to them, through the Seller’s Property Disclosure, that there were no present or past conditions involving moisture or water problems, roof problems or leaks, skylight problems, or gutter downspout problems.
In granting plaintiffs’ motion, the state court determined that the defendant contractor made these representations on her Seller’s Property Disclosure despite witnessing water leaking from the skylight onto the floor and being aware of repairs to the roof, skylight, and interior drywall prior to the sale of the property.
Read the full story…
Reprinted courtesy of Derek J. Lindenschmidt of Higgins, Hopkins, McClain & Roswell, LLP. Mr. Lindenschmidt can be contacted at lindenschmidt@hhmrlaw.com
CC&Rs Not the Place for Arbitration Agreement, Court Rules
May 24, 2011 — CDJ Staff
In January, the California Court of Appeals ruled that an arbitration clause inserted in a development’s CC&Rs by the developer could not be enforced. The case, Villa Vicenza Homeowners Association v. Noble Court Development, involved a case in which, according to the opinion, “following the first sale Nobel controlled the board of directors of the Association and because the initial condominium buyers noticed defects in common areas and common facilities and did not believe Nobel had provided a reserve fund sufficient to repair the defects, the condominium owners brought a derivative action on behalf of the Association against Nobel.”
The court concluded, “The use of CC&R's as a means of providing contractual rights to parties with no interest in or responsibility for a common interest development is also problematic from the standpoint of determining what if any consideration would support such third-party agreements. By their terms the CC&R's bind all successors, even those with whom a third party such as Nobel has never had any contractual relationship and to whom Nobel has not provided any consideration.” The court determined that “the trial court did not err in denying Nobel's motion to compel arbitration.”
Read the court’s decision