Avoid Gaps in Construction Defect Coverage
July 10, 2012 — CDJ Staff
The language may be standardized, but the way different states’ courts interpret it is not. That’s the problem discussed by William F. Knowles and Brendan Winslow-Nason in an article in Business Insurance. One of the major issue through the country is whether a construction defect claim and the resultant damage are an occurrence. Additionally, there are questions whether certain exclusions apply, such as “your work” or “your product” exclusions. They note that many courts “ agree that they are intended to exclude defective construction itself, while providing coverage for unintended consequences.” They further note that these are not the only insurance issues, “making it difficult for construction companies operating across state lines to ensure adequate coverage.”
Their recommendations to contractors are that they pay careful attention to where they’ve done business and “if the states have issued decisions or if there is legislation in place address the scope of coverage under additional insured endorsements.” Additionally, they suggest determining whether a contractor can negotiate a choice of law provision in their policy. The conclude that “construction companies can take proactive steps to protect themselves by identifying the applicable states’ laws, determining whether insurance is adequate under those laws, and then taking steps to resolve any gaps in their coverage.”
Read the full story…
Fifth Circuit Asks Texas Supreme Court to Clarify Construction Defect Decision
November 7, 2012 — CDJ Staff
The Fifth Circuit Court has withdrawn its decision in Ewing Construction Company v. Amerisure Insurance Company, pending clarification from the Texas Supreme Court of its decision in Gilbert Texas Construction, L.P. v. Underwriters at Lloyd’s London. The Fifth Circuit had applied the Gilbert case in determining that a contractual liability exclusion barred coverage for faulty workmanship. The Insurance Journal reports that this decision was both applauded and criticized, with a concern noted that “an insurer would now have its pick of either the ‘your work’ exclusion or the contractual liability exclusion without the exception for subcontracted work.”
The Fifth Circuit is now asking the Texas Supreme Court two questions to clarify Gilbert, which Brian S. Martin and Suzanne M. Patrick see as a sign that the Court has realized that it overly expanded the scope of the earlier ruling. A response is expected from the Texas Supreme Court by spring 2013.
Read the full story…
California Assembly Bill Proposes an End to Ten Year Statute of Repose
May 9, 2011 — May 9, 2011 Beverley BevenFlorez - Construction Defect Journal
California Assemblyman Furutani has introduced a bill that if passed would eliminate the ten year statute of repose in certain construction defect cases. The statute of repose would not apply when “an action in tort to recover damages for damage to real or personal property, or for personal injury or wrongful death from exposure to hazardous or toxic materials, pollution, hazardous waste, or associates environmental remediation activities,” according to the latest amended version of AB 1207.
When Furutani first introduced the bill, it was aimed at small businesses only. However, the description of the bill, which read, “An act to amend Section 14010 of the Corporations Code, relating to small businesses” has been stricken from the bill, and it has been amended to read, “An act to amend Section 337.15 of the Code of Civil Procedure, relating to civil actions.”
The change in the bill’s intent has caused some outcry among attorneys in the blogosphere. For instance, Sean Sherlock of Snell & Wilmer stated that “the proposed amendment is unnecessary, and would upset nearly 50 years of deliberative legislation and judicial precedent on construction defects liability and the 10–year statute — all apparently motivated by a decision in a single, isolated Superior Court lawsuit that has not yet been reviewed by the court of appeal.” Sherlock is referring to Acosta v. Shell Oil Company, in which the Superior Court agreed to dismiss the plaintiffs’ claims against the developer based in part on the ten year statute of repose. AB 1207 was amended five days after the ruling in Acosta v. Shell Oil Company.
California AB 1207 has been re-referred to the Judiciary Committee.
Read the full story…
Home Sales Still Low, But Enough to Spur Homebuilders
August 16, 2012 — CDJ Staff
Although new home sales are still fifty percent below the average over the last forty years, the housing rebound has sent stock of homebuilders up 53 percent this year, during the same period, the S&P 500 rose only 12 percent. The San Francisco Chronicle reports that from 2005 through 2011, homebuilder stocks trailed the S&P 500.
The growth isn’t limited to homebuilders alone. Building suppliers are also seeing a growth in sales, with profits for companies that make gypsum wallboard, cabinetry, plumbing products, and other items used in home building.
Homebuilders have also been able to raise prices. Standard Pacific Corp of Irvine, California has raised prices and cut incentives. Nevertheless, the buyers still come. PulteGroup and D.R. Horton are also raising prices.
Read the full story…
Ohio Court of Appeals Affirms Judgment in Landis v. Fannin Builders
April 20, 2011 — April 20, 2011 Beverley BevenFlorez - Construction Defect Journal
The Ohio Court of Appeals affirmed the judgment in Landis v. William Fannin Builders. Landis contracted Fannin Builders to build their home. The case involved staining problems on the T1-11 siding chosen by the plaintiffs.
After a year and a half of discussion on how to resolve the problem of uneven staining on the siding, Landis filed suit “against Fannin Builders, alleging claims for breach of contract, breach of the express limited warranty, and violation of the Ohio Consumer Sales Practices Act (“OCSPA”). Fannin Builders, in turn, filed a third-party complaint against 84 Lumber, alleging claims for breach of contract and indemnification. With the trial court’s leave, Fannin Builders also later amended its answer to add a counterclaim against appellees for breach of contract and unjust enrichment. In the counterclaim, Fannin Builders alleged that appellees still owed it $3,908.98 for the construction of appellees’ home.”
“In its decision, the trial court found in appellees’ favor on their breach of contract claim and against appellees on their claims for breach of the express limited warranty and violation of the OCSPA. Additionally, the trial court found in Fannin Builders’ favor on its counterclaim for breach of contract and against Fannin Builders on its third-party claims for breach of contract and indemnity. The trial court determined that appellees’ damages amounted to $66,906.24, and after setting off the $3,908.98 that appellees owed Fannin Builders under the construction contract, the trial court awarded appellees $62,997.26. The trial court reduced its decision to judgment on May 18, 2010.”
Fannin Builders appealed this judgment and assigned the following errors:
[1.] The Trial Court Erred as a Matter of Law by Concluding that Appellant Breached its Contract with Appellees when it provided a Semi-Transparent Oil-Based Stain that Simply did not Meet their Approval.
[a.] The Contract does not Contain a Satisfaction Clause.
[b.] Even if the Court Implies a Satisfaction Clause, the Court Should Apply an Objective Standard.
[2.] The Trial Court Erred as a Matter of Law by Failing to Consider Appellant’s Right to Cure.
[3.] The Trial Court committed Reversible Error by not Assessing Damages Using “Diminished Value Standard,” and by Creating a Remedy that Constitutes Economic Waste.
[4.] The Trial Court Erred as a Matter of Law by Concluding that Appellant is Barred from Seeking Indemnification When 84 [Lumber] Never Fulfilled its Obligations Pursuant to the Settlement Agreement Entered on August 2, 2005.
In response to the first assigned error, the Court of Appeals stated: “Because the failure to provide siding of a uniform color, not appellees’ displeasure, breached the contract, we reject Fannin Builders’ contention that the trial court implied a satisfaction clause into the contract and found a breach of that clause. Accordingly, we overrule Fannin Builders’ first assignment of error.”
The Court of Appeals overruled the second assignment of error and provided the following reasoning: “Although Fannin Builders depends upon a term of the limited warranty for its right to cure, the trial court concluded that no breach of the limited warranty occurred. Fannin Builders breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIA’s Quality Standards. Consequently, the limited warranty does not apply to this case, and thus, it does not prevent appellees’ recovery of damages.”
The Appeals Court found “the trial court’s award of damages” was “both reasonable and supported by competent, credible evidence,” and therefore concluded “that the trial court did not err in setting appellees’ damages at $62,997.26.” The Fannin Builders third assignment of error was overruled.
The fourth and final assignment of error was also overruled by the Court of Appeals. “While Fannin Builders correctly asserts that 84 Lumber never installed the replacement siding, it ignores the fact that it ordered 84 Lumber to remove the replacement siding from appellees’ property. Thus, Fannin Builders precluded 84 Lumber from completely performing under the August 2, 2005 letter agreement. […] Consequently, Fannin Builders cannot now claim that the letter agreement is unenforceable or that it is entitled to indemnification from 84 Lumber. Because Fannin Builders assumed all liability for the defective siding in the letter agreement, it is responsible for appellees’ damages.”
James A. Zitesman, Columbus, Ohio Business Attorney, compared the case to Jones v. Centex (Ohio App. 2010), which had a different verdict:
“The common thread is the implied warranty of good workmanship. In the Jones case, the Court found that the buyers had in fact waived all implied warranties, including the implied warranty of good workmanship. In the contract between Jones and Centex, the builder stated that it “…would not sell the property to Purchasers without this waiver.” Probably should have been a sign to the buyers.
In the Landis case, the Court stated, “Contracts for the future construction of a residence include a duty, implied by law, that the builder must perform its work in a workmanlike manner.” The Court gave significant weight to the concept of the implied warranty of good workmanship. The builder relied upon the BIA Warranty which limits builders’ liability and exposure to legal issues. The trial court concluded there was no breach of the limited warranty, rather the builder “breached the duty of workmanlike conduct implicit in the construction contract, not the limited warranty requiring it to satisfy the BIAs Quality Standards.”
The Supreme Court of Ohio has accepted the Jones v. Centex Homes case for review.
Read the full story...
Is There a Conflict of Interest When a CD Defense Attorney Becomes Coverage Counsel Post-Litigation?
September 1, 2011 — Chad Johnson of Higgins, Hopkins, McLain & Roswell, LLC
In Weitz Co., LLC v. Ohio Cas. Ins. Co., the U.S. District Court for the District of Colorado was asked to rule on a motion to disqualify counsel in an insurance coverage action. 11-CV-00694-REB-BNB, 2011 WL 2535040 (D. Colo. June 27, 2011). Motions to disqualify counsel are viewed with suspicion, as courts “must guard against the possibility that disqualification is sought to ‘secure a tactical advantage in the proceedings.’” Id. at *2 (citing Religious Technology Center v. F.A.C.T. Net, Inc., 945 F. Supp. 1470, 1473 (D. Colo. 1996).
Weitz Company, LLC (“Weitz”) is a general contractor and defendant in an underlying construction defect suit which had concluded before the action bringing rise to this order. In the underlying action, Weitz made third-party claims against subcontractors, including NPW Contracting (“NPW”). Weitz was listed as an additional insured under NPW’s policies with both Ohio Casualty Insurance Company and Mountain States Mutual Casualty Company (collectively “the Carriers”). The Carriers accepted Weitz’s tender of defense under a reservation of rights. However, neither insurance carrier actually contributed to Weitz’s defense costs in the underlying action. At the conclusion of the construction defect action, the parties unsuccessfully attempted to apportion the attorney’s fees and costs. Eventually, Weitz brought suit against the recalcitrant carriers. The Lottner firm, which had previously represented Weitz in the underlying construction defect action, continued to represent Weitz in this coverage action.
Read the full story…
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. Johnson can be contacted at johnson@hhmrlaw.com
Recent Case Brings Clarity and Questions to Statute of Repose Application
August 16, 2012 — Douglas Reiser, Builders Counsel
I have often chatted about the Washington Statute of Repose on this blog. The Statute of Repose prevents construction claims, for the most part, from being raised 6 years from the date of substantial completion or termination. Well, a recent Court of Appeals case dove deep into the specific determinative factors that tell us when to start the clock. It certainly raises questions about how long we really have to file suit.
The Statute of Repose has been a frequent topic here, so I will simply direct you to my prior post for further information on how this law works. A recent post was published about a lawsuit that might raise some questions about when and how the clock begins to roll, and claim periods begin to diminish.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Is Construction Heading Off the Fiscal Cliff?
December 20, 2012 — CDJ Staff
After a period of growth, the construction industry lost 20,000 jobs in November, based on the federal jobs data. Damon Scott of New Mexico Business Weekly suggests that contractors may have laid off employees in anticipation of the “fiscal cliff.” Ken Simpson, the chief economist of the National Association of Home Builders said in a press release that “it is discouraging that construction employment is still struggling after three years of expansion in the overall economy.”
Read the full story…
Allowing The Use Of a General Verdict Form in a Construction Defect Case Could Subject Your Client to Prejudgment Interest
August 16, 2012 — Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC
A recent opinion from the Colorado Court of Appeals is a cautionary tale concerning the calculation of pre-judgment interest. See Hendricks v. Allied Waste Transportation, Inc., 2012 WL 1881004 (Colo. App. 2012). The Hendricks sued Allied after one of its drivers backed into the corner of their home with an Allied garbage truck. At trial, a jury awarded the Hendricks $160,100 in damages. Although the jury was instructed on the cost of repairs, diminution in value, and non-economic damages, the parties agreed to a general verdict form that did not ask the jury to specify the types of damages awarded. Id. at *1. The Hendricks sought to amend the judgment to include prejudgment interest and costs, which the trial court granted.
Allied appealed, arguing that the trial court erred by awarding the Hendricks prejudgment interest from the date their property was damaged. Id. at *7. The Colorado Court of Appeals found no error, and affirmed.
Read the full story…5
Reprinted courtesy of Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Anderson can be contacted at anderson@hhmrlaw.com
Will They Blow It Up?
March 28, 2012 — CDJ Staff
The issues concerning the Harmon Towers building in Las Vegas continue to make their way through the courts. As we noted in a previous piece, Cook County building officials stated that the building could be a hazard if Las Vegas were struck by an earthquake. The question of whether the building will continue to stand is just one of the issues in front of a judge.
MGM Resorts International argued at a March 13 hearing for permission to implode the Harmon hotel building. They claim that more than 1,700 defects have been discovered in the building and that the building is a public safety hazard. Arguing against demolition, Perini Building Company, the general contractor for the hotel, and its subcontractors are claiming that imploding the building would destroy evidence and prejudice juries in the ongoing construction defect claims. They claim that MGM Resorts wishes to abandon the building due to the economic slowdown. Perini Corp, the contractor for the project, claims that the building can be fixed. Perini claims that MGM’s position in the construction trial would be improved if the building is demolished.
After Judge Elizabeth Gonzalez heard the four days of testimony on the Harmon Towers building and whether it should be demolished, she scheduled more testimony, with two days in April and an entire week in July. Judge Gonzalez will be deciding whether the building will be torn down, imploded, or left in place.
Read the full story…
Read the full story…
Going Green for Lower Permit Fees
October 23, 2012 — CDJ Staff
Clay County, Kansas is offering rebates on building permits for green homes. According to the Kansas City Star, building permits in the county are typically $2,500. The county will rebate anything from half to all of the permit fee, depending on how well the builder meets green standards. The county will monitor and inspect the process to make certain that builders adhere to their promises for green construction. The county hopes this will encourage green building by offsetting the cost.
Read the full story…
Limitations of Liability in Subcontractors’ Contracts May Not Be Enforceable in Colorado to Limit Claims by Construction Professionals.
October 23, 2012 — Heidi J. Gassman, Higgins, Hopkins, McLain & Roswell
The Colorado Homeowner Protection Act of 2007 (“HPA”), codified at C.R.S. § 13-20-806(7), specifically voids express waivers of, or limitations on, a residential property owner’s ability to enforce any rights, remedies, and damages provided by law in a construction defect case. Practically speaking, this means that limitation of liability provisions in contracts between construction professionals and residential homeowners are void and will not be enforced in Colorado. The HPA can extend even further, however, to subcontractors on residential projects, as seen in a recent District Court ruling.
The HPA was tested in Thacker v. Gallery Homes, et al., v. Terracon Consultants, Inc., et al., Larimer County District Court Case No. 2007CV1195. Gallery Homes hired Terracon to provide geotechnical and structural engineering services at the Colony Ridge subdivision in Loveland, Colorado. Terracon performed work for Gallery Homes under three separate contracts, each of which included a provision limiting Terracon’s total liability to Gallery Homes.
After the project was completed, two homeowners filed suit against Gallery Homes for alleged construction defects involving movement of their basement floor systems and foundations and damage to porches, patios, garages, and driveways. Gallery Homes sued Terracon as a third-party defendant, and Terracon sought to enforce its limitation of liability provisions via a partial summary judgment motion.
Read the full story…
Reprinted courtesy of Heidi J. Gassman, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Gassman can be contacted at gassman@hhmrlaw.com
Another Las Vegas Tower at the Center of Construction Defect Claims
November 7, 2012 — CDJ Staff
Accusations are coming from both sides over construction defects at a Las Vegas tower, only this time, it’s not the Harmon Towers, it’s Hilton Grand Vacations, which is part of the Planet Hollywood Resort. The project was originally dubbed PH Towers Westgate, and it was developed by Westgate Resorts, which is suing the contractor, Tutor-Saliba for $10 million over late completion and construction defects.
Among the defects Westgate is claiming are cracked floor tiles in the valet lobby and cracks and delamination of the pool deck. Tutor-Saliba argues that the failure of the valet lobby floor is due to Westgate specifying only 1/16th inch-wide grouting, instead of the specified ¬º inch, and Westgate’s refusal to allow expansion joints on the pool deck has lead to problems there. Westgate’s attorney, Robert Schumacher, attributes the problems to “shoddy construction practices.”
According to the article in the Las Vegas Review Journal, plans were only 60 percent complete when construction began, leading to “thousands of change orders.” Despite not meeting an August completion deadline, Tutor-Saliba is claiming it is owed a $1.5 million bonus nevertheless.
Read the full story…
California Posts Nation’s Largest Gain in Construction Jobs
March 28, 2012 — CDJ Staff
California added about 8,900 construction jobs in January, 2012, as compared to December, 2011, leading the nation in the number of added construction jobs. Thirty-four other states also saw added construction jobs. A year prior, only twenty-eight states added construction jobs. The Associated General Contractors of America analyzed the monthly report from the Labor Department. Ken Simonson, the chief economist for the Associated General Contractors of America noted that “the gains this January partly reflect very mild weather this winter and exceptionally cold and snowy conditions a year before.”
Read the full story…
California Construction Bill Dies in Committee
July 21, 2011 — CDJ Staff
AB 20, which its sponsor, Linda Halderman (R-Fresno), stated would discourage class action lawsuits against builders and protect jobs in the construction industry, has died in committee. Although the Business Journal reported in June that Haldeman was promoting the bill during a talk in her district and the bill is still on her web site, the California Assembly reports that the bill failed in committee on March 15, 2011. It is possible that the bill could be reconsidered, but the Assembly Committee on Judiciary sees the bill as responding to issues quieted by SB 800 which gives builders the right to repair alleged defects before any suit can be filed.
Read the full story…
Court Rules on a Long List of Motions in Illinois National Insurance Co v Nordic PCL
May 10, 2012 — CDJ Staff
The case Illinois National Insurance Co. v Nordic PCL, et al. “involves a dispute about whether insurance benefits are available to a general contractor who built structures that allegedly have construction defects. Plaintiffs Illinois National Insurance Company (‘Illinois National’) and National Union Fire Insurance Company of Pittsburgh, PA (‘National Union’) (collectively, the ‘Insurers’), commenced this action for declaratory relief against Defendant Nordic PCL Construction, Inc., f/k/a Nordic Construction, Ltd. ("Nordic"), on August 23, 2011.”
The court was asked to rule on a long list of motions: “Counterclaim Defendants’ Request for Judicial Notice in Support of Their (1) Motion to Dismiss the Counterclaim and (2) Motion to Strike Portions of the Counterclaim, ECF No. 16 (‘Request for Judicial Notice’); Counterclaim Defendants’ Motion to Dismiss Counterclaim Filed October 24, 2011, ECF No. 14 (‘Motion to Dismiss Counterclaim’); Counterclaim Defendants’ Motion to Strike Portions of the Counterclaim Filed October 24, 2011, ECF No. 15 (‘Motion to Strike’); Third-Party Defendant Marsh USA, Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 33 (‘Marsh’s Motion To Dismiss Or Stay’); Defendant and Third-Party Plaintiff Nordic PCL Construction, Inc., f/k/a Nordic Construction Ltd.’s Substantive Joinder to Third-Party Defendant Marsh USA Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 36 (‘Nordic’s Joinder’); and Third-Party Defendant Marsh USA, Inc.’s Motion for Judgment on the Pleadings on Counts V and VI of Defendant/Third-Party Plaintiff Nordic PCL Construction, Inc.’s Third-Party Complaint, ECF No. 29 (‘Marsh’s Motion for Judgment on the Pleadings’).”
In result, the court reached the following decisions: “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice to the extent it covers matters relevant to these motions; GRANTS IN PART the Insurers’ Motion to Dismiss Counterclaim, but gives Nordic leave to amend the Counterclaim in certain respects; DENIES the Insurers’ Motion to Strike; DENIES Marsh’s Motion To Dismiss Or Stay and Nordic’s Joinder; and GRANTS Marsh’s Motion for Judgment on the Pleadings.”
The court provides a bit of background on the case: “This action arises out of alleged construction defects involving two projects on which Nordic acted as the general contractor. Nordic is a defendant in a pending state court action with respect to one of the projects and says it spent more than $400,000 on repairs with respect to the other project. Nordic tendered the defense of the pending state court action to the Insurers and sought reimbursement of the cost of repairs already performed. The Insurers responded by filing this action to determine their rights under the insurance policies issued to Nordic.”
Furthermore, the court presented a brief procedural history: “The Insurers commenced this declaratory action in this court on August 23, 2011. The Complaint asserts two claims, one seeking a declaration that the Insurers have no duty to provide a defense or indemnification regarding the Safeway Action, the other seeking such a declaration regarding the Moanalua Claims. Along with its Answer, Nordic filed a Counterclaim against the Insurers. The Counterclaim asserts breach of contract, breach of the covenant of good faith and fair dealing, misrepresentations and omissions of material fact, and bad faith, and seeks declaratory relief against the Insurers.”
The procedural history continues: “Nordic also filed a Third-Party Complaint against Marsh, the broker that had procured the Policies from the Insurers for Nordic. Nordic alleges that it reasonably believed that the Policies would provide completed operations insurance coverage for the types of construction defects alleged in the Safeway Action and Moanalua Claims. The Third-Party Complaint asserts breach of contract, negligence, promissory estoppel, breach of fiduciary duties, implied indemnity, and contribution and equitable subrogation.”
In conclusion, “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice. With regard to the Insurers’ Motion to Dismiss Counterclaim, the court GRANTS the motion as to Count I (breach of contract), Count II (duty of good faith and fair dealing), Count III (fraudulent and negligent misrepresentation), the portion of Count IV (bad faith) premised on fraud, and Count IV (declaratory relief). The court DENIES the motion as to Count IV (bad faith) that is not premised on fraud. Except with respect to the "occurrence" issue, which the court disposes of here on the merits, and Count V, which concerns only a form of relief, Nordic is given leave to amend its Counterclaim within three weeks of the date of this order. The court DENIES the Insurers’ Motion to Strike, DENIES Marsh’s Motion to Dismiss or Stay and Nordic’s Joinder, and GRANTS Marsh’s Motion for Judgment on the Pleadings with respect to Counts V and VI of the Third-Party Complaint.”
Read the court’s decision…
Negligent Misrepresentation in Sale of Building Altered without Permits
September 30, 2011 — CDJ Staff
The Supreme Court of New Hampshire has ruled in the case Wyle v. Lees. The Leeses owned a two-unit apartment building in North Conway, New Hampshire. They hired a contractor to add a third, larger apartment, including a two-car garage. The Leeses and their contractor submitted a building permit application. They were informed that site plan review was required. After receiving approval on the site plan, construction started. At no point did they obtain a building permit and the construction was never inspected. The Leeses subsequently added more space to the unit, reducing parking spaces below the minimum required. Again, they did not obtain a building permit.
In 2007, three years after all these changes were complete, the Leeses sold their building to Mr. Wyle. To the question “are you aware of any modifications or repairs made without the necessary permits?” they answered “no.” About six weeks after closing, Wyle “received a letter from the town code enforcement officer regarding the legality of the removal of a garage door from the new unit.” A subsequent inspection revealed “numerous building and life safety code violations.”
Mr. Wyle brought a claim against the Leeses for negligent misrepresentation. The defendants filed a motion “seeking to preclude economic loss damages.” At a two-day bench trial, Mr. Wyle won. The Leeses appealed.
The appeals court found that “the defendants negligently misrepresented that the premises were licensed for immediate occupancy and that the defendants had obtained all necessary permits,” and thus upheld the lower court’s finding of negligent misrepresentation. The appeals court also rejected the Leeses’ argument that damages must be apportioned on all parties, including “the plaintiff himself, the plaintiff’s building inspector, and the defendant’s contractor,” finding a lack of “adequate evidence.”
The Leeses further argued that they were unaware that modifications and repairs were accomplished without the required permits. The appeals court noted that “the trial court found that both the conditional approval and final approval for the site plan stated that a building permit and a certificate of occupancy were required prior to any use.” The court concluded that the Leeses “knew or should have known of the falsity of their representation.”
The appeals affirmed the findings of the trial court.
Read the court’s decision…
All Risk Policy Only Covers Repair to Portion of Dock That Sustains Damage
January 6, 2012 — Tred Eyerly, Insurance Law Hawaii
A portion of a dock on Lack Michigan operated by the Ports of Indiana suffered visible damage. See Ports of Indiana v. Lexington Ins. Co., 2011 U.S. Dist. LEXIS 130979 (S.D. Ind. Nov. 14, 2011). Lexington Insurance Company insured the port. Lexington agreed that a portion of the dock was damaged and paid $1.2 million for repairs. A dispute arose, however, over whether additional sections of the dock were damaged and whether the damage was the result of more than one "occurrence."
An expert report opined that a significant drop creating record lows in the water level of Lake Michigan in 2007 caused damage to the dock. Lexington maintained that only 128 feet of the dock was damaged; other portions of the dock did not sustain "direct physical loss or damage."
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com