BERT HOWE
  • Nationwide: (800) 482-1822    
    parking structure Marshall County Minnesota office building Marshall County Minnesota Subterranean parking Marshall County Minnesota industrial building Marshall County Minnesota high-rise construction Marshall County Minnesota tract home Marshall County Minnesota mid-rise construction Marshall County Minnesota landscaping construction Marshall County Minnesota multi family housing Marshall County Minnesota casino resort Marshall County Minnesota custom homes Marshall County Minnesota townhome construction Marshall County Minnesota structural steel construction Marshall County Minnesota retail construction Marshall County Minnesota custom home Marshall County Minnesota institutional building Marshall County Minnesota concrete tilt-up Marshall County Minnesota condominium Marshall County Minnesota low-income housing Marshall County Minnesota production housing Marshall County Minnesota condominiums Marshall County Minnesota Medical building Marshall County Minnesota
    Arrange No Cost Consultation
    Construction Expert Witness Builders Information
    Marshall County, Minnesota

    Minnesota Builders Right To Repair Current Law Summary:

    Current Law Summary: Statutory warranties for one-year, two-year and ten-year periods limits types of construction defects actionable under warranty law; This statute (Chapter 327A) limits liability and excludes normal wear and tear, normal shrinkage caused by drying of the dwelling, loss due to insufficient ventilation, loss or damage from negligence, improper maintenance, or alteration to dwelling, loss or damage from failure to maintain or failure to mitigate


    Construction Expert Witness Contractors Licensing
    Guidelines Marshall County Minnesota

    Residential contractors need to be licensed. If you work in two or more trades, certain trades will require a license. Call the state for details.


    Construction Expert Witness Contractors Building Industry
    Association Directory
    Headwaters Builders Association
    Local # 2480
    PO Box 402
    Bemidji, MN 56619
    http://www.headwatersbuilders.org

    Northern MN Builders Association
    Local # 2417
    802 S Pokegama Ave Ste A
    Grand Rapids, MN 55744
    http://www.nmbuilders.com

    Lake Region Builders Association
    Local # 2470
    1114 Hwy. 59 South Ste 2
    Detroit Lakes, MN 56501
    http://www.lakeregionbuilders.com

    Arrowhead Builders Association
    Local # 2415
    5255 Maple Grove Road
    HERMANTOWN, MN 55811
    http://www.abamn.org

    Home Builders Association of Mid-Minnesota
    Local # 2450
    17068 Commercial Park Road
    Brainerd, MN 56401
    http://www.midmnba.org

    Vikingland Builders Assoc
    Local # 2495
    509 22ND AVE E Ste 200
    Alexandria, MN 56308
    http://www.vikinglandbuilders.com

    Central Minnesota Builders Association
    Local # 2410
    1124 W Saint Germain St
    Saint Cloud, MN 56301
    http://www.cmbaonline.org


    Construction Expert Witness News and Information
    For Marshall County Minnesota

    Allowing the Use of a General Verdict Form in a Construction Defect Case Could Subject Your Client to Prejudgment Interest

    Former New York Governor to Head Construction Monitoring Firm

    One World Trade Center Due to Be America’s Tallest and World’s Priciest

    Hospital Construction Firm Settles Defect Claim for $1.1 Million

    Insurance Company Prevails in “Chinese Drywall” Case

    Subcontractor Not Liable for Defending Contractor in Construction Defect Case

    The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?

    California Bill Would Notify Homeowners on Construction Defect Options

    Micropiles for bad soil: a Tarheel victory

    Claims Under Colorado Defect Action Reform Act Count as Suits

    OSHA Extends Temporary Fall Protection Rules

    New Washington Law Nixes Unfair Indemnification in Construction Contracts

    Ghost Employees Steal Jobs from Legit Construction Firms

    Ensuing Losses From Faulty Workmanship Must be Covered

    Insurer Must Defend Claims for Diminution in Value of Damaged Property

    No Coverage For Construction Defects When Complaint Alleges Contractual Damages

    Texas res judicata and co-insurer defense costs contribution

    Statute of Limitations Upheld in Construction Defect Case

    Orange County Home Builder Dead at 93

    Increased Expenditure on Injuries for New York City School Construction

    Are Construction Defects Covered by Your General Liability Policy?

    Seven Tips to Manage Construction Defect Risk

    Tucson Officials to Discuss Construction Defect Claim

    Pipes May Be Defective, But Owners Lack Standing

    Washington Court of Appeals Upholds Standard of Repose in Fruit Warehouse Case

    Condominium Communities Must Complete Construction Defect Repairs, Says FHA

    Construction Firm Sues City and Engineers over Reservoir Project

    Product Exclusion: The Big Reason Behind The Delay of LEED 2012

    Nevada Supreme Court Reverses Decision against Grader in Drainage Case

    Bad Faith and a Partial Summary Judgment in Seattle Construction Defect Case

    Cogently Written Opinion Finds Coverage for Loss Caused By Defective Concrete

    Southern California Lost $8 Billion in Construction Wages

    Another Colorado District Court Refuses to Apply HB 10-1394 Retroactively

    Nevada Court Adopts Efficient Proximate Cause Doctrine

    Environment Decision May Expand Construction Defect Claims

    Ohio Court of Appeals Affirms Judgment in Landis v. Fannin Builders

    Damron Agreement Questioned in Colorado Casualty Insurance v Safety Control Company, et al.

    Home Builder Doesn’t See Long Impact from Hurricane

    Texas covered versus uncovered allocation and “legally obligated to pay.”

    Williams v. Athletic Field: Hugely Important Lien Case Argued Before Supreme Court

    California Construction Bill Dies in Committee

    MGM Seeks to Demolish Harmon Towers

    New OSHA Fall Rules to Start Early in Minnesota

    Court Rejects Anti-SLAPP Motion in Construction Defect Suit

    Another Guilty Plea In Nevada Construction Defect Fraud Case

    Arbitration Clause Found Ambiguous in Construction Defect Case

    Save A Legal Fee? Sometimes You Better Talk With Your Construction Attorney

    Celebrities Lose Case in Construction Defect Arbitration

    California Appeals Court Remands Fine in Late Completion Case

    Time to Repair Nevada’s Construction Defect Laws?

    Godfather Charged with Insurance Fraud

    Toxic Drywall Not Covered Under Homeowner’s Policy

    Court Orders House to be Demolished or Relocated

    BHA Expands Construction Experts Group

    Recent Case Brings Clarity and Questions to Statute of Repose Application

    Contractors Admit Involvement in Kickbacks

    Anti-Assignment Provision Unenforceable in Kentucky

    Pennsylvania Court Extends Construction Defect Protections to Subsequent Buyers

    Five Years of Great Legal Blogging at Insurance Law Hawaii

    Preventing Costly Litigation Through Your Construction Contract

    Construction Law: Unexpected, Fascinating, Bizarre

    Conspirators Bilked Homeowners in Nevada Construction Defect Claims

    Building Boom Leads to Construction Defect Cases

    Washington Supreme Court Sides with Lien Claimants in Williams v. Athletic Field

    Arbitration Clause Not Binding on Association in Construction Defect Claim

    Texas Construction Firm Files for Bankruptcy

    After Construction Defect Case, Repairs to Austin Building

    After Breaching its Duty to Defend, Insurer Must Indemnify

    Supreme Court of Oregon Affirms Decision in Abraham v. T. Henry Construction, et al.

    SB800 Cases Approach the Courts

    Discovery Ordered in Nevada Construction Defect Lawsuit

    Destruction of Construction Defect Evidence Leads to Sanctions against Plaintiff

    Contractor Burns Down Home, Insurer Refuses Coverage

    Federal Court Denies Summary Judgment in Leaky Condo Conversion

    $5 Million Construction Defect Lawsuit over Oregon Townhomes

    Illinois Court Determines Insurer Must Defend Negligent Misrepresentation Claim

    Homeowner Has No Grounds to Avoid Mechanics Lien

    School District Settles Construction Lawsuit

    Dust Infiltration Due to Construction Defect Excluded from Policy

    General Contractors Must Plan to Limit Liability for Subcontractor Injury

    Anti-Concurrent Causation Clause Bars Coverage for Landslide and Water Leak

    Does the New Jersey Right-To-Repair Law Omit Too Many Construction Defects?

    Michigan Supreme Court Concludes No Statute of Repose on Breach of Contract

    CC&Rs Not the Place for Arbitration Agreement, Court Rules

    Construction Bright Spot in Indianapolis

    In Colorado, Primary Insurers are Necessary Parties in Declaratory Judgment Actions

    Going Green for Lower Permit Fees

    Construction Defect Not Occurrences, Says Hawaii Court

    Insurance Firm Defends against $22 Million Claim

    Boston’s Tunnel Project Plagued by Water
    Corporate Profile

    MARSHALL COUNTY MINNESOTA CONSTRUCTION EXPERT WITNESS
    DIRECTORY AND CAPABILITIES

    Leveraging from more than 5500 construction defect and claims related expert witness designations, the Marshall County, Minnesota Construction Expert Witness Group provides a wide range of trial support and consulting services to Marshall County's most acknowledged construction practice groups, CGL carriers, builders, owners, and public agencies. Drawing from a diverse pool of construction and design professionals, BHA is able to simultaneously analyze complex claims from the perspective of design, engineering, cost, or standard of care.

    Marshall County Minnesota general contracting construction expert witnessesMarshall County Minnesota general contracting OSHA expert witness constructionMarshall County Minnesota general contracting engineering consultantMarshall County Minnesota general contracting expert witness concrete failureMarshall County Minnesota general contracting structural engineering expert witnessesMarshall County Minnesota general contracting testifying construction expert witnessMarshall County Minnesota general contracting roofing construction expertMarshall County Minnesota general contracting roofing and waterproofing expert witnessMarshall County Minnesota general contracting consulting engineers
    Construction Expert Witness News & Info
    Marshall County, Minnesota

    Policing Those Subcontractors: It Might Take Extra Effort To Be An Additional Insured

    June 14, 2011 — Douglas Reiser, Builders Council Blog

    I just came across a case that I think truly paints the insurance dilemma for contractors. Thanks to this recent Illinois case, I don’t have to make up any factual scenarios—so kudos to Attorney Robert Boylan for posting it.

    In reading over my RSS feeds this weekend, I noticed a great writeup on long-time blogger Josh Glazov’s Construction Law Today. Attorney Robert Boylan’s post describes a recent Illinois case where a general contractor was denied its additional insured status on a second-tier subcontractor’s insurance. The reason for the denial: the general contractor failed to procure an agreement in writing with the second-tier subcontractor, requiring it to be listed as an additional insured.

    Read the full story…

    Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com


    Construction Defect Notice in the Mailbox? Respond Appropriately

    August 4, 2011 — Douglas Reiser, Builders Counsel

    Recently, I have seen a rash of ignored construction defect notices. What is a construction defect notice? It’s a statutorily required notice, sent from a homeowner to a contractor, listing a number of defects found at their property. If you get one, don’t ignore it.

    The Revised Code of Washington includes a number of provisions intended for residential construction disputes. Among them is the “Notice to Customer” requirement in RCW 18.27.114, which can preempt a contractor’s lien rights, and the “Notice of Construction Defects” found in RCW 64.50.020.

    The Notice of Construction Defects is a standard notice mandated by RCW 64.50, a chapter in the Revised Code of Washington, intended to provide a pre-litigation resolution process for contractors and consumers. The chapter applies only to those losses “caused by a defect in the construction of a residence or in the substantial remodel of a residence.”(See “Action” RCW 64.50.010).

    Unfortunately, many contractors will simply ignore these notices or tell the homeowner to make a warranty claim. But, the notice actually provides a contractor with a forty-five (45) day window to alleviate the dispute.

    Read the full story…

    Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com


    Another Las Vegas Tower at the Center of Construction Defect Claims

    November 7, 2012 — CDJ Staff

    Accusations are coming from both sides over construction defects at a Las Vegas tower, only this time, it’s not the Harmon Towers, it’s Hilton Grand Vacations, which is part of the Planet Hollywood Resort. The project was originally dubbed PH Towers Westgate, and it was developed by Westgate Resorts, which is suing the contractor, Tutor-Saliba for $10 million over late completion and construction defects.

    Among the defects Westgate is claiming are cracked floor tiles in the valet lobby and cracks and delamination of the pool deck. Tutor-Saliba argues that the failure of the valet lobby floor is due to Westgate specifying only 1/16th inch-wide grouting, instead of the specified ¬º inch, and Westgate’s refusal to allow expansion joints on the pool deck has lead to problems there. Westgate’s attorney, Robert Schumacher, attributes the problems to “shoddy construction practices.”

    According to the article in the Las Vegas Review Journal, plans were only 60 percent complete when construction began, leading to “thousands of change orders.” Despite not meeting an August completion deadline, Tutor-Saliba is claiming it is owed a $1.5 million bonus nevertheless.

    Read the full story…


    General Contractor/Developer May Not Rely on the Homeowner Protection Act to Avoid a Waiver of Consequential Damages in an AIA Contract

    August 4, 2011 — Higgins, Hopkins, McLain & Roswell, LLC

    Recently, in Caribou Ridge Homes, LLC v. Zero Energy, LLC, et al., Case No. 10CV1094, Boulder County District Court Judge Ingrid S. Bakke entered a ruling and order on the Plaintiff’s Motion for Determination of Question of Law Pursuant to C.R.C.P. 56(h) on Issue of Damages. The Order found that the Plaintiff was not a homeowner intended to be protected by the Homeowner Protection Act (the “HPA”) and thus could not pursue its claims for consequential damages against Defendant.

    By way of background, on June 18, 2008, Plaintiff Caribou Ridge Homes, LLC (“Caribou”) entered into a Standard Form Agreement Between Owner and Contractor AIA Document A114-2001 (the “Contract”) with Defendant Zero Energy, LLC (“Zero Energy”). Plaintiff hired Zero Energy to serve as a general contractor for the construction of a single-family home in the Caribou Ridge subdivision in Nederland, Colorado. A provision in the contract contained a mutual waiver of consequential damages (“Waiver”).

    Read the full story…

    Reprinted courtesy Higgins, Hopkins, McLain & Roswell, LLC


    Insurance Company Prevails in “Chinese Drywall” Case

    June 17, 2011 — CDJ Staff

    The Louisiana Court of Appeals rejected an appeal to reverse a summary judgment granted to Louisiana Citizens Property Insurance Company. Terrence and Rhonda Ross contracted for a remodel of their home in which Chinese-made drywall was used. When the drywall emitted harmful gasses, the Rosses filed a claim under their insurance policy. This claim was rejected under four exclusions: for faulty materials, latent defect, loss by corrosion, and loss by pollution. After the claim was denied, the Rosses sued Louisiana Citizens.

    In April 2010, the lower court granted a summary judgment, followed by a May, 2010 order dismissing the Rosses’ claims against Louisiana Citizens. The Rosses appealed this decision. In the court’s review, they agreed with Louisiana Citizens and the lower court on all counts. Although the Rosses maintained that the drywall was not defective (as it still functioned as drywall), the court ruled that its emission of sulfuric gases was a defect. Further, as it was in place for two years before this became evident, it was also a latent defect. Damage to the Rosses’ home consisted of corrosion damage caused by the pollutants in the drywall.

    The Rosses made an additional claim that since their policy covered smoke damage, this should be covered, as the harm was done by sulfuric gases. The court noted that the contract specifies “fumes or vapors from a boiler, furnace, or related equipment,” none of which apply in this case.

    Read the court’s decision


    Colorado Statutes of Limitations and Repose, A First Step in Construction Defect Litigation

    December 20, 2012 — CDJ Staff

    Grund Dagner, a law firm operating in Denver and Boulder, Colorado notes on their blog that when defending a construction defect claim, one of their first steps is to determine if the claims are affected by the statutes of limitations or repose, and that they “have had much success raising these defenses with the court before trial.”

    Colorado has a two-year statute of limitations, starting from when the homeowner discovers the defect. Further, Colorado’s statute of repose precludes lawsuits beginning “more than six years after the substantial completion of the improvement to the real property.”

    Grund Dagner notes that they “recently obtained dismissal of claims related to eight of 22 buildings in a condominium project, where the homeowners in those building observed the defects more than two years before the HOA initiated its claims against our client.”

    Read the full story…


    Nevada Supreme Court Reverses Decision against Grader in Drainage Case

    June 30, 2011 — CDJ Staff

    The Nevada Supreme Court has issued an opinion in the case of Rayburn Lawn & Landscape Designers v. Plaster Development Corporation, reversing the decision of the lower court and remanding the case for a new trial.

    The case originated in a construction defect suit in which Plaster Development Corporation was sued by homeowners. Plaster filed a third-party complaint against its subcontractor, Reyburn. The testimony of Reyburn’s owner was considered to be admission of liability and so the court limited the scope of Reyburn’s closing argument and did not allow the jury to determine the extent of Reyburn’s liability. Reyburn appealed.

    Plaster, in their case, cited California’s Crawford v. Weather Sheild MFG, Inc. The court held the application of these standards, but noted that the “an indemnitor’s duty to defend an indemnitee is limited to those claims directly attributed to the indemnitor’s scope of work and does not include defending against claims arising from the negligence of other subcontractors and the indemnittee’s own negligence.”

    On the matter of law against Reyburn, the court concluded, “Given the conflicting evidence at trial as to whether Reyburn’s work was implicated in the defective retaining walls and sidewalls, and viewing the evidence and inferences in Reyburn’s favor, we conclude that a reasonable jury could have granted relief in favor of Reyburn.” The Nevada Supreme Court conduced that the district court should not have granted Plaster’s motion for judgement.

    Further, the Nevada Supreme Court found that the district court should have apportioned the fees and costs to those claims directly attributed to Reyburn’s scope of work, “if any,” and should not have assigned all attorney costs and court fees to Reyburn.

    Read the court’s decision…


    California Appeals Court Remands Fine in Late Completion Case

    November 18, 2011 — CDJ Staff

    The California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.

    The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”

    Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”

    Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”

    The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”

    The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.

    The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.

    Read the court’s decision…


    Wisconsin “property damage” caused by an “occurrence.”

    April 4, 2011 — April 4, 2011 in CDCoverage.com

    In American Family Mut. Ins. Co. v. American Girl, Inc., 673 N.W.2d 65 (Wis. 2004), the insured general contractor was hired by the owner to design and build a warehouse on the owner s property. The general contractor hired a soil engineer to do a soil analysis and make site preparation recommendations. The soil engineer determined that the soil conditions were poor and recommended a compression process which the general contractor followed. After the warehouse was completed and the owner took possession, excessive soil settlement caused the foundation to sink which in turn caused structural damage to the warehouse. The warehouse had to be torn down.

    Read the full story...

    Reprinted courtesy of CDCoverage.com


    Damron Agreement Questioned in Colorado Casualty Insurance v Safety Control Company, et al.

    February 10, 2012 — CDJ Staff

    Safety Control and EMC appealed the judgment in Colorado Casualty Insurance Company versus Safety Control Company, Inc., et al. (Ariz. App., 2012). The Superior Court in Maricopa County addressed “the validity and effect of a Damron agreement a contractor and its excess insurer entered into that assigned their rights to sue the primary insurer.” Judge Johnsen stated, “We hold the agreement is enforceable but remand for a determination of whether the stipulated judgment falls within the primary insurer’s policy.”

    The Opinion provides some facts and procedural history regarding the claim. “The Arizona Department of Transportation (“ADOT”) hired DBA Construction Company (“DBA”) to perform a road-improvement project on the Loop 101 freeway. Safety Control Company, Inc. was one of DBA’s subcontractors. As required by the subcontract, Safety Control purchased from Employer’s Mutual Casualty Company (“EMC”) a certificate of insurance identifying DBA as an additional insured on a policy providing primary coverage for liability arising out of Safety Control’s work.”

    A collision occurred on site, injuring Hugo Roman. Roman then sued ADT and DBA for damages. “Colorado Casualty tendered DBA’s defense to the subcontractors, including Safety Control. Safety Control and EMC rejected the tender. Roman eventually settled his claims against DBA and ADOT. DBA and ADOT stipulated with Roman for entry of judgment of $750,000; Roman received $75,000 from DBA (paid by Colorado Casualty) and $20,000 from ADOT, and agreed not to execute on the stipulated judgment. Finally, DBA, ADOT and Colorado Casualty assigned to Roman their rights against the subcontractors and other insurers.”

    Colorado Casualty attempted to recover what “it had paid to defend DBA and ADOT and settle with Roman. However, Roman intervened, and argued that “Colorado Casualty had assigned its subrogation rights to him as part of the settlement agreement.” The suit was not dismissed, but the Superior Court allowed Roman to intervene. “Roman then filed a counterclaim against Colorado Casualty and a cross-claim against the subcontractors.”

    All claims were settled against all of the defendants except Safety Control and EMC. “The superior court ruled on summary judgment that EMC breached a duty to defend DBA and that as a result, ‘DBA was entitled to settle with Roman without EMC’s consent as long as the settlement was not collusive or fraudulent.’ After more briefing, the court held the stipulated judgment was neither collusive nor procured by fraud and that EMC therefore was liable to Roman on the stipulated judgment and for his attorney’s fees. The court also held Safety Control breached its subcontract with DBA by failing to procure completed-operations insurance coverage and would be liable for damages to the extent that EMC did not satisfy what remained (after the other settlements) of the stipulated judgment and awards of attorney’s fees.” Safety Control and EMC appealed the judgment.

    Four reasons were given for the decision of the ruling. First, “the disagreement between Roman and Colorado Casualty does not preclude them from pursuing their claims against EMC and Safety Control.” Second, “the settlement agreement is not otherwise invalid.” Third, “issues of fact remain about whether the judgment falls within the EMC policy.” Finally, “Safety Control breached the subcontract by failing to procure ‘Completed Operations’ coverage for DBA.”

    In conclusion, the Superior Court affirmed in part, reversed in part, and remanded . “Although, as stated above, we have affirmed several rulings of the superior court, we reverse the judgment against EMC and remand for further proceedings consistent with this Opinion to determine whether the stipulated judgment was a liability that arose out of Safety Control’s operations. In addition, we affirm the superior court’s declaratory judgment against Safety Control but remand so that the court may clarify the circumstances under which Safety Control may be liable for damages and may conduct whatever further proceedings it deems appropriate to ascertain the amount of those damages. We decline all parties’ requests for attorney’s fees pursuant to A.R.S. § 12-341.01 without prejudice to a request for fees incurred in this appeal to be filed by the prevailing party on remand before the superior court.”

    Read the court’s decision…


    Construction Upturn in Silicon Valley

    August 17, 2011 — CDJ Staff

    Work resumed after nearly three years on an office tower in Santa Clara, according to the San Jose Mercury News. Work had stalled on the building due to the economy, but now the developer is planning a second five-story building on the site. Other dormant projects in the area are also getting restarted. Santa Clara County saw the addition of 1,800 construction jobs in June.

    A spokesperson for the Operating Engineers Local 3 in Alameda told the paper, “two years ago we had five thousand folks on the out-of-work list. It’s now down to about 1,700.”

    Read the full story…


    Insurer Able to Refuse Coverage for Failed Retaining Wall

    October 28, 2011 — CDJ Staff

    The Eleventh District of the US Court of Appeals has ruled in the case of Nix v. State Farm Fire & Casualty Company. In this case, the Nixes filed a claim after a portion of the retaining wall in their home collapsed and their basement flooded. State Farm denied the claim “on the ground that the policy excluded coverage for collapses caused by defects in construction and for damage caused by groundwater.”

    The court reviewed the Nixes’ policy and found that State Farm’s statement did specifically exclude both of these items. In reviewing the lower court’s ruling, the appeals court noted that State Farm’s expert witness, Mark Voll, determined that the retaining wall “lacked reinforcing steel, as required by a local building code, and could not withstand the pressure created by groundwater that had accumulated during a heavy rainfall.” Additionally, a french drain had been covered with clay soil and so had failed to disperse the groundwater.

    The Nixes argued that the flooding was due to a main line water pipe, but their opinions were those of Terry Nix and the contractor who made temporary repairs to the wall. “Those opinions were not admissible as lay testimony. Neither Nix nor the contractor witnessed the wall collapse or had personal knowledge about the construction of the Nixes’ home.”

    The lower court granted a summary judgment to State Farm which has been upheld by the appeals court.

    Read the court’s decision…


    Contractual Liability Exclusion Bars Coverage

    August 2, 2012 — Tred Eyerly, Insurance Law Hawaii

    The Fifth Circuit Court of Appeals considered whether coverage existed for a defectively built tennis court in light of a contractual liability exclusion. Ewing Construction Company, Inc. v. Amerisure Ins. Co., 2012 U.S. App. LEXIS 12154 (5th Cir. June 15, 2012).

    Ewing Construction Company entered a contract with the School District to construct tennis courts at a school. After completion, the School District complained that the courts were cracking and flaking, rendering them unfit for playing tennis. The School District filed suit, seeking damages for defective construction. It alleged that Ewing breached its contract and performed negligently.

    Ewing tendered the underlying lawsuit to Amerisure. Amerisure denied coverage and Ewing filed suit.

    Read the full story…

    Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com


    Are Construction Defects Covered by Your General Liability Policy?

    July 10, 2012 — CDJ Staff

    Construction firms are finding that their insurers are denying construction defect claims and the courts are siding with the insurers, according to Kelly M. Gindele, writing in the Martindale-Hubble Legal Library. Ms. Gindele notes that when construction defect claims are not covered, firms can end up with “multi-million dollar claims” that it has to pay “out of its own pocket.” She notes that in Kentucky and Ohio, if “the insured’s work causes an unforeseen and unintended event to occur?Ķthere is not occurrence under the policy.” Further, if there is an occurrence, the court will “look for an exception to coverage.”

    She also notes that contractors may not hold sufficient coverage, either by limiting the amounts or the time. She notes that while “insurers generally try to limit coverage for defect claims to one year,” that “construction defects may not be found in a year’s time.”

    Ms. Ginele recommends that contractors “hire an insurance company with extensive experience in this field” and “independent legal counsel with insurance knowledge,” to avoid finding themselves “with limited or even no coverage when it needs it most.”

    Read the full story…


    California Assembly Bill Proposes an End to Ten Year Statute of Repose

    May 9, 2011 — May 9, 2011 Beverley BevenFlorez - Construction Defect Journal

    California Assemblyman Furutani has introduced a bill that if passed would eliminate the ten year statute of repose in certain construction defect cases. The statute of repose would not apply when “an action in tort to recover damages for damage to real or personal property, or for personal injury or wrongful death from exposure to hazardous or toxic materials, pollution, hazardous waste, or associates environmental remediation activities,” according to the latest amended version of AB 1207.

    When Furutani first introduced the bill, it was aimed at small businesses only. However, the description of the bill, which read, “An act to amend Section 14010 of the Corporations Code, relating to small businesses” has been stricken from the bill, and it has been amended to read, “An act to amend Section 337.15 of the Code of Civil Procedure, relating to civil actions.”

    The change in the bill’s intent has caused some outcry among attorneys in the blogosphere. For instance, Sean Sherlock of Snell & Wilmer stated that “the proposed amendment is unnecessary, and would upset nearly 50 years of deliberative legislation and judicial precedent on construction defects liability and the 10–year statute — all apparently motivated by a decision in a single, isolated Superior Court lawsuit that has not yet been reviewed by the court of appeal.” Sherlock is referring to Acosta v. Shell Oil Company, in which the Superior Court agreed to dismiss the plaintiffs’ claims against the developer based in part on the ten year statute of repose. AB 1207 was amended five days after the ruling in Acosta v. Shell Oil Company.

    California AB 1207 has been re-referred to the Judiciary Committee.

    Read the full story…


    Arbitration Clause Not Binding on Association in Construction Defect Claim

    June 19, 2012 — CDJ Staff

    Determining that a community’s CC&Rs do not form an agreement to arbitrate, the California Court of Appeals has reversed the decision of the Superior Court inVerano Condo. Homeowners the Ass’n v. La Cima Dev., LLC (Cal. App., 2012). La Cima purchased an apartment complex in December 2004, which they converted into condominiums. In the process, La Cima created the CC&Rs, under which the Verano Condominium Homeowners Association came into being. One section of the CC&Rs included arbitration clauses. Additionally, the purchase agreements for individual condominium units also contained arbitration clauses. Subsequently, the owners became aware of construction defect both in units and in the common areas. The Association sued La Cima both in its own interest and on behalf of its members. La Cima moved to compel arbitration, which was denied by the trial court. La Cima appealed.

    The court concluded that “CC&Rs are insufficient to form an agreement to arbitrate between La Cima and the Association.” The court noted that “no evidence exists to show the Association consented to the terms of the CC&Rs, either explicitly or implicitly.”

    The court agreed with La Cima that the arbitration agreement applied to those owners who had purchased their units directly from La Cima. Moreover, as the conversion to condominiums involved interstate commerce, in part because a Delaware company was selling condominiums located in California, the court held that the Federal Arbitration Act (FAA) applied, and as such “even a state constitutional standard, such as the the jury waiver provision requirements of the California Constitution, cannot be used to circumvent the FAA in the face of an otherwise valid arbitration agreement.”

    However, the court also held that there was “no agreement in the CC&Rs between La Cima and owners who did not purchase units directly from La Cima,” adding that “no meeting of the minds between La Cima and these later purchasers and their successors occurred.” The court did not believe that “the Legislature intended that CC&Rs would be used to provide continuing and irrevocable contractual development or role as a representative of the owners of the development.”

    The purpose of the CC&Rs, according to the court are to “protect owners from one another and permit enforcement of its terms by the Association.” The court stated that “La Cima relinquished its interests in the land by selling its property and may not assert any rights under the CC&Rs following the transfer of its ownership interest.

    In its conclusion, the court determined that claims must be organized in three classes. The claims the association made against La Cima for defects in the common area “are not subject to any valid agreement to arbitrate.” The second category are those owners who did not purchase their units directly from La Cima. Here, also, the court found that the units “are similarly not subject to a valid arbitration agreement.”

    The third category, however, was “owners who purchased units directly from La Cima.” The court held that these arbitration agreements were valid, and if the claims were to be taken up by the association, the association could only submit these claims to arbitration. The lower court was instructed to separate these claims, as here La Cima’s motion could be granted.

    Read the court’s decision…


    Hawaii State Senate Requires CGL Carriers to Submit Premium Information To State Legislature

    March 20, 2011 — March 20, 2011 Construction Defect Journal Staff

    In light of the decision in Hawaii’s Intermediate Court of Appeals in Group Builders, Inc.,v. Admiral Insurance Company, 231 P.3d 67(2010), Hawaii’s state senate is requesting that "every domestic and foreign insurance company that has ever issued commercial general liability policies in the State is requested to submit information to the Legislature on the total premiums received for their commercial general liability policies during the past ten years"

    Read Full Text of Hawaii State Senate Resolution


    Statute of Limitations Upheld in Construction Defect Case

    September 30, 2011 — CDJ Staff

    The Missouri Court of Appeals has ruled in Ball v. Friese Construction Co., finding that Mr. Ball’s claims were barred by the statute of limitations.

    Mr. Ball hired Friese Construction Company to build a single-family home. The sale was completed on March 29, 2001. That December, Mr. Ball complained of cracks in the basement floor. SCI Engineering, n engineering firm, hired by Friese, determined that the home’s footing had settled and recommended that Mr. Ball hire a structural engineer to determine if the footings were properly designed and sized. In September 2002, the structural engineer, Strain Engineering, determined that the cracks were due to slab movement, caused in part by water beneath the slab, recommending measures to move water away from the foundation. In 2005, Mr. Ball sent Friese correspondence “detailing issues he was having with the home, including problems with the basement slab, chimney structure, drywall tape, and doors.” All of these were attributed to the foundation problems. In 2006, Friese stated that the slab movement was due to Ball’s failure to maintain the storm water drains.

    In 2009, Ball received a report from GeoTest “stating the house was resting on highly plastic clay soils.” He sued Friese in May, 2010. Friese was granted a summary judgment dismissing the suit, as the Missouri has a five-year statute of limitations. Ball appealed on the grounds that the extent of the damage could not be determined until after the third expert report. The appeals court rejected this claim, noting that a reasonable person would have concluded that after the conclusion of SCI and Strain Engineering that “injury and substantial damages may have occurred.”

    The court concluded that as there were not “continuing wrongs causing new and distinct damages,” he should have filed his lawsuit after the first two expert reports, not waiting seven years for a third expert to opine.

    Read the court’s decision…