Orange County Home Builder Dead at 93
April 25, 2012 — CDJ Staff
Randall E. Presley was a homebuilder in Southern California for more than thirty years, acting as head of Presley Development Company from 1956 until selling the firm to Lyon Homes in 1987. The two companies merged in 1991 as the Presley Cos. Mr. Presley saw the need in the 1950s to provide people in Southern California with low- to medium-priced quality homes.
His firm built more than 160 communities and was among the ten largest homebuilding firms in the country, expanding beyond California. Mr. Presley was 93 when he succumbed to pneumonia. He is survived by a wife, three children, seven grandchildren, and 11 great-grandchildren.
Read the full story…
In Oregon Construction Defect Claims, “Contract Is (Still) King”
April 25, 2012 — CDJ Staff
Writing in Oregon’s Daily Journal of Commerce, David Anderson looks at the aftermath of the case Abraham v. T. Henry Construction, Inc. In that case, Anderson notes that “the homeowners hired a contractor to build their house, and subsequently discovered extensive water damage” “after expiration of the time to sue for breach of contract.” The homeowners claimed negligence. Oregon’s Supreme Court concluded that “homeowners only had to prove that the contractor negligently caused reasonably foreseeable harm to the homeowner’s property.”
Anderson views this decision as leading to two risks for contractors. “First, contractors can be held liable in tort for breaching building code standards; second, they can be held liable for violating the often-difficult-to-define ‘reasonable care’ standard.” But here, “contract can be king.” The Oregon Supreme Court noted that the contractor “could have avoided exposure to the general ‘reasonable care’ standard by more carefully defining its obligations in the original construction contract.”
He notes that contractors who fail to define their obligations or use generic definitions “may be exposing themselves to a more vague scope of liability.”
Read the full story…
Judge Concludes Drywall Manufacturer Sold in Florida
September 13, 2012 — CDJ Staff
A Florida judge has concluded that the Chinese drywall manufacturer Taishan actively sought to sell its products in Florida and cannot now claim that it was not involved. Judge Joseph Farnia also noted that the main distributor of the drywall was, as noted in the Miami Herald, an arm of the company. Lennar Hones has sued the firm after installing drywall manufactured by the company in hundreds of homes.
Taishan’s activities in Florida included not only distributing samples, but also hosting tours of their plants in China for construction executives, and even making customized runs. According to other reports, has lost past cases over defects in their drywall.
Read the full story…
Condominium Communities Must Complete Construction Defect Repairs, Says FHA
July 10, 2012 — CDJ Staff
Laura K. Sanchez of HindmanSanchez writes that the FHA “will not approve or recertify” any condominium community “where there are any pending or incomplete repairs within the community which are a result of a construction defect claim, regardless of whether the litigation has been resolved and regardless of whether there are funds in the bank paid by the developer to pay for the repairs.” The FHA notes that failure to complete or fund repairs could “put FHA insured loans at risk.” Communities must disclose all maintenance and repair issues to the FHA. Sanchez notes that the FHA has stated that incomplete repairs could put FHA-insured loans at risk.
Read the full story…
A Lien Might Just Save Your Small Construction Business
April 4, 2011 — Douglas Reiser in the Builders Counsel Blog
Many owners incorrectly believe that payment to the general contractor gets the owner off the hook for payment to subcontractors and suppliers. This assumption sometimes fosters the irresponsible owner, who fails to ensure that everyone is getting paid. Fortunately for those contractors further down the contracting chain, this assumption is incorrect.
Suppliers and subcontractors can file a lien to secure payment for their labor and materials. A filing party must offer proper notice (if applicable) and file an adequate and timely lien in the County where the work is performed. You can read our earlier posts on these topics by following this link.
A lien notice and a lien put an owner on notice that your business has provided labor and/or materials for the improvement of the owner’s property (See RCW 60.04.031 for more info). If the owner fails to take care to ensure that your business is paid the law mandates that the owner may have to pay twice.
Read the full story...
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Denver Court Rules that Condo Owners Must Follow Arbitration Agreement
November 7, 2012 — CDJ Staff
Prior to initiating a construction defect lawsuit, the Glass House Residential Association voted to invalidate the arbitration agreement that had been written into its declaration and bylaws by the developer and general contractor. After the association started their construction defect claims, the developer and general contractor argued that the case must go to arbitration, as the arbitration clause contained a provision that it could not be altered without the agreement of the developer and general contractor.
The Denver District Court has ruled against that association, determining that the res triction was not in violation of Colorado condominium law. And, as a post from Polsinelli Shughart PC on JDSupra notes, the Colorado Common Interest Ownership Act encourages the use of arbitration procedures to settle disputes. The CCIOA does prohibit “certain restrictions on the homeowners association’s ability to amend the condominium declarations,” however, preserving an arbitration agreement is not one of them.
Read the full story…
Judge Okays Harmon Tower Demolition, Also Calls for More Testing
August 2, 2012 — CDJ Staff
Vegas.Inc reports that Clark County District Court Judge Elizabeth Gonzalez has permitted the demolition the tower, which MGM Resorts has claimed is a safety hazard. Perini Building Co. claims that the building does not need to be demolished. CityCenter claims that repairing the building would take nearly a year longer than a demolition and cost about $200 million. Further, CityCenter assumes that the building’s reputation would cost it another $30 million.
Subsequently, Judge Gonzalez ruled that the pattern of destructive testing would not support a claim that there were an estimated 1,400 defective items in the building. An attorney for CityCenter, Steve Morris, has suggested that they may seek more testing, impossible to do once the building is demolished. CityCenter issued a statement that “nearly every time CityCenter has chipped away concrete to review structural work at the Harmon, we have found defects.” They describe the building as “unusable.”
Tutor Perini contends that it “remains confident that it will prevail when the issues of safety, reparability and responsibility for the issues facing the Harmon tower are considered.
Read the full story…
New Buildings in California Soon Must Be Greener
June 19, 2012 — CDJ Staff
The California Energy Commission has approved new energy efficiency standards for new homes and commercial buildings. The 2013 Building Energy Efficiency Standards are set to go into effect on January 1, 2014, and will require 30% more energy efficiency for non-residential construction and 25% more for homes. The standards do not affect hospitals, nursing homes, or prisons.
Buildings covered under the standard will have to have roofs that ready for the installation of solar panels. Additionally, non-residential buildings will require high-performance windows, advanced lighting controls, and cool-roof technologies. Residential requirements include insulated hot-water pipes, whole house fans, and more efficient windows.
The new standards are expected to add 3,500 new building industry jobs. One thing these construction workers won’t be building are power plants, since over the next thirty years, the standards are expected to save as much as six power plants.
Read the full story…
North Carolina Exclusion j(6) “That Particular Part”
February 10, 2012 — CDCoverage.com
In Alliance Mutual Insurance Co. v. Dove, 714 S.E.2d 782 (N.C. Ct. App. 2011), claimant Murphy-Brown hired insured Dove to repair a broken elevator belt in a grain elevator in Murphy-Brown’s feed mill. The elevator was inside a metal duct and, to access the broken belt, Dove had to cut out a section of the duct. After replacing the belt, Dove welded the metal section back to the duct. Immediately after Dove completed the welding, dust inside the duct ignited, causing an explosion in the elevator, resulting in property damage to the elevator and other property. Murphy-Brown sued Dove for negligence seeking damages for the repair and replacement of the elevator, repair and replacement of the other property, increased grain handling costs during the repairs, and loss of use.
Read the full story…
Reprinted courtesy of CDCoverage.com
Will They Blow It Up?
March 28, 2012 — CDJ Staff
The issues concerning the Harmon Towers building in Las Vegas continue to make their way through the courts. As we noted in a previous piece, Cook County building officials stated that the building could be a hazard if Las Vegas were struck by an earthquake. The question of whether the building will continue to stand is just one of the issues in front of a judge.
MGM Resorts International argued at a March 13 hearing for permission to implode the Harmon hotel building. They claim that more than 1,700 defects have been discovered in the building and that the building is a public safety hazard. Arguing against demolition, Perini Building Company, the general contractor for the hotel, and its subcontractors are claiming that imploding the building would destroy evidence and prejudice juries in the ongoing construction defect claims. They claim that MGM Resorts wishes to abandon the building due to the economic slowdown. Perini Corp, the contractor for the project, claims that the building can be fixed. Perini claims that MGM’s position in the construction trial would be improved if the building is demolished.
After Judge Elizabeth Gonzalez heard the four days of testimony on the Harmon Towers building and whether it should be demolished, she scheduled more testimony, with two days in April and an entire week in July. Judge Gonzalez will be deciding whether the building will be torn down, imploded, or left in place.
Read the full story…
Read the full story…
Couple Sues Attorney over Construction Defect Case, Loses
June 10, 2011 — CDJ Staff
The California Court of Appeals has ruled against a couple who sued their lawyer, after they were unhappy with the results of a construction defect case. Craig and Jeanne Petrik sued Mahaffey and Associates for legal malpractice and breach of contract. Their lawyer, Douglas L. Mahaffey, had settled their case for $400,000. The Petricks claimed Mahaffey did not have the authority make an offer to compromise.
In the original case, Mahaffey held back the $400,000 awarded in the settlement until he and the Petricks came to terms on how much of that was owed to Mahaffey. The lower court concluded that the Petricks were due $146,323,18. The jury did not agree with the Petrik’s claim that conditions had been met in which Mahaffey would not be charging them costs.
Judges O’Leary and Ikola wrote the opinion, with the third judge on the panel, Judge Bedworth offering a dissent only on their view of the cost waiver clause.
Read the court’s opinion
Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)
August 11, 2011 — Melissa Brumback
For today’s law note, I’m addressing a comment that came to me last week from Dave O’Hern of Miller O’Hern Construction. Dave writes:
I am a general contractor doing a fuel tank replacement project for our county. In the specifications there is a spec for a UL 142 tank, on the plans the spec references UL 2085 ? a much more expensive tank. My subcontractor bid the UL 142 tank. The specifications state that the specs and plans are on the same level of precedence.
The county wants me to furnish the more expensive tank without compensation citing the clause that states the plans and specs are complementary and what is called for by one is binding as if called by all and the most stringent requirement will apply.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Washington Court Limits Lien Rights of Construction Managers
August 17, 2011 — Douglas Reiser, Builders Counsel
A newly filed, yet unpublished, court opinion opines that a construction manager cannot file a construction lien in Washington state. So, how far reaching is this opinion?
In the case of Blue Diamond Group Inc. v. KB Seattle 1, Inc., et al, a New York construction manager filed a lien against the Westfield Southcenter Mall in Tukwila, Washington. The lien was filed after the owner of a coffee stand failed to pay Blue Diamond for consulting services used in the construction of a kiosk.
Blue Diamond served as the owner’s agent, assisting with managing subcontractors, vendors and other tasks. The manager’s tasks also included paying invoices, managing deliveries, setting schedules and other site managerial tasks. Blue Diamond was not registered as a contractor under Washington’s RCW 18.27.
Read the full story…
Read the court’s decision…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Differing Rulings On Construction Defect Claims Leave Unanswered Questions For Builders, and Construction Practice Groups. Impact to CGL Carriers, General Contractors, Builders Remains Unclear
March 7, 2011 — March 7, 2011 Construction Defect Journal Staff
In the past year a number of state and federal courts have rendered a number of conflicting decisions that promise to alter or perhaps shift entirely the paradigm, of how builders manage risk.
According to a report today by Dave Lenckus in Property Casualty 360 “Nine state and federal courts and one state legislature over the past year have addressed whether a construction defect a defective product or faulty workmanship is fortuitous and therefore an occurrence under the commercial general liability insurance policy. Four jurisdictions determined it is; three said no; two ruled that a construction defect that causes consequential damage to property other than the work product is an occurrence; and one federal court contributed its conflicting case law that has developed in Oregon since its high court ruled in 2000 that a construction defect is not an occurrence”.
The article strongly suggests that in the absence of a clear consensus over what the recent rulings mean for builders and contractors coverage disputes will intensify and continue to proliferate.
Doing this on a state-by-state basis has caused a lot of confusion among buyers and sellers, said Jeffrey A. Segall, a Tampa-based senior vice president and the Florida Construction Practice leader at Willis of Florida, a unit of Willis Group Holdings.
Read Full Story...
California Assembly Bill Proposes an End to Ten Year Statute of Repose
May 9, 2011 — May 9, 2011 Beverley BevenFlorez - Construction Defect Journal
California Assemblyman Furutani has introduced a bill that if passed would eliminate the ten year statute of repose in certain construction defect cases. The statute of repose would not apply when “an action in tort to recover damages for damage to real or personal property, or for personal injury or wrongful death from exposure to hazardous or toxic materials, pollution, hazardous waste, or associates environmental remediation activities,” according to the latest amended version of AB 1207.
When Furutani first introduced the bill, it was aimed at small businesses only. However, the description of the bill, which read, “An act to amend Section 14010 of the Corporations Code, relating to small businesses” has been stricken from the bill, and it has been amended to read, “An act to amend Section 337.15 of the Code of Civil Procedure, relating to civil actions.”
The change in the bill’s intent has caused some outcry among attorneys in the blogosphere. For instance, Sean Sherlock of Snell & Wilmer stated that “the proposed amendment is unnecessary, and would upset nearly 50 years of deliberative legislation and judicial precedent on construction defects liability and the 10–year statute — all apparently motivated by a decision in a single, isolated Superior Court lawsuit that has not yet been reviewed by the court of appeal.” Sherlock is referring to Acosta v. Shell Oil Company, in which the Superior Court agreed to dismiss the plaintiffs’ claims against the developer based in part on the ten year statute of repose. AB 1207 was amended five days after the ruling in Acosta v. Shell Oil Company.
California AB 1207 has been re-referred to the Judiciary Committee.
Read the full story…
Homeowners Sue Over Sinkholes, Use Cash for Other Things
January 6, 2012 — CDJ Staff
Quoting one homeowner as saying that his house “can fall in the ground for all I care, I made my money,” the Tampa Bay Times looks at the issue of sinkhole claims in Florida. Homeowners “have paid off mortgages, put in pools, replaced roofs, or otherwise used money from sinkhole claims to do something besides fix sinkhole damage.
It’s been tough for insurance companies. Citizens Property Insurance took in $32 million in premiums for sinkhole coverage in 2010, but paid out $245 million in sinkhole claims. The Tampa Bay Times notes that some of those claims come from settling problems caused by their repairs, including one settlement of $350,000 for repairs to a house worth $39,000.
One couple, after receiving $217,000 from Citizens, sold the house to a company that bought unrepaired sinkhole homes for $190,000. The home has been sold since and remains unrepaired.
Sometimes the preferred solution by the insurance company isn’t the cheapest either. One couple was informed that Citizens was going to spend $150,000 to have the hole filled with grout. After they settled with the insurance company, they fixed the problem by installing steel piers, at a cost of about $45,000.
Read the full story…
Manhattan Developer Breaks Ground on $520 Million Project
November 18, 2011 — CDJ Staff
Rebuilding an area of Midtown West that has been condemned for decades, the Gotham Organization has broken ground on a 1,200-unit project that will include housing for a variety of household incomes and a school. One unit of the project will be affordable housing for families of annual incomes up to $40,000. Another will be for middle-income households. Additionally, there will be a 31-story tower with 550 luxury units.
The site CityBiz quotes Mayor Michael Bloomberg, as saying that the project “will grow our economy by creating 2,900 construction-related jobs.” The president of the Gotham Organization, David L. Picket notes that it will “create hundreds of new jobs, generate millions of dollars in revenue for the construction industry, contribute towards the building of a new primary, and provide homes to thousands of New Yorkers.”
Read the full story…
Product Exclusion: The Big Reason Behind The Delay of LEED 2012
July 10, 2012 — Douglas Reiser, Builders Counsel
By now, you have probably heard that the USGBC has decided to delay implementation of its previously named “LEED 2012” rating system. What you might not know is exactly why this is happening. Rest assured that the decision was not made willy nilly ?Äì LEED 2012 had many industrial groups running for the hills.
I have spent the past few weeks reading a number of articles on the backlash. LEED 2012 was intended to create a seismic shift; it was not a mere update. A strict focus on reduction of chemicals, created mass panic that a large number of material providers’ products would essentially be banned from green projects ?Äì meaning most local, state and federal projects.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com