Yellow Brass Fittings Play a Crucial Role in Baker v Castle & Cooke Homes
May 10, 2012 — CDJ Staff
Baker v Castle & Cooke Homes Hawaii, et al. is a “class action filed by homeowners who allege that their homes have a construction defect. They allege that their plumbing systems include brass fittings susceptible to corrosion and likely to cause leaks. They bring this action against the developer of their homes and the manufacturers of the brass fittings.”
Zurn, the manufacturer of the allegedly defective brass fittings, sought a dismissal, or if that could not be achieved, then “a more definite statement, of five of the six claims.” Zurn moved for summary judgment on the sixth claim, or alternately sought “summary judgment on one of the five claims it” sought to dismiss.” The court granted in part the motion, and denied the motion for summary judgment.
The developer, Castle & Cooke, sought dismissal of the First Amended Complaint stating “that Plaintiffs have not complied with Hawaii’s Contractor Repair Act, chapter 672E of Hawaii Revised Statutes, which requires, among other things, a plaintiff to give a contractor the results of any testing done before filing an action against that contractor.” The court couldn’t determine “certain facts essential to ruling” on Castle & Cooke’s motion, and therefore denied the motion, but ordered Plaintiffs to submit requested material by the stated deadline.
The Baker v Castle & Cooke case began with the Plaintiffs claim that the use of yellow brass fittings can lead to construction defects. They allege that “yellow brass is particularly susceptible to dezincification, a corrosion process in which zinc leaches into potable water that comes into contact with the brass. According to Plaintiffs, as the brass corrodes, it becomes porous and mechanically weak. Plaintiffs further allege that the PEX systems in the putative class members’ homes have begun to, or are about to, leak water into the walls, ceilings, and floors of their homes. Plaintiffs allege that the leakage will cause water damage and mold growth, exposing the occupants to toxins.”
In response to the plaintiffs’ claims, Zurn argued “because their yellow brass fittings have not failed to date, Plaintiffs fail to allege, and have no evidence showing, that they have suffered any actual injury.” Plaintiffs replied, “even if the fittings have not failed as of today, failure in the future is inevitable.”
However, the court stated, “whether Plaintiffs have suffered any injury, or whether Plaintiffs are attempting to proceed based solely on future injury, implicates Plaintiffs’ standing to bring this action, as well as whether this case is ripe for adjudication.” The court has requested the parties to submit “supplemental briefing on whether this case should be dismissed pursuant to Rule 12(b)(1). In supplemental briefs, Zurn argues that dismissal is appropriate because Plaintiffs lack standing, and Castle & Cooke argues that dismissal is appropriate because Plaintiffs’ claims are not ripe.”
The court continues to discuss the problem of standing: “To establish standing, a plaintiff must demonstrate three things. First, the plaintiff must suffer an "injury-in-fact," which means that there must be a concrete and particularized "invasion of a legally protected interest" and the invasion is actual or imminent. Lujan v. Defenders of Wildlife, 504 U.S. 555, 560 (1992). Second, the injury must be fairly traceable to the challenged action. Third, a favorable decision must be likely to redress the injury. Id. It is the first element (injury-in-fact) that is in issue here.”
The court found that the plaintiffs do have standing: “Even if the court could not rely on the allegations that the pipes will soon leak, the court would conclude that, for standing purposes, Plaintiffs have a sufficient injury-in-fact in the form of their alleged economic loss.” In a hearing, Plaintiffs argued that their homes had decreased in value.
The court also denied Castle & Cooke’s motion to dismiss based on a lack of ripeness, stating “the same reasons Plaintiffs satisfy the injury-in-fact requirement for standing purposes, they satisfy the constitutional ripeness requirement.”
Plaintiffs asserted six counts against Zurn. Zurn, in response, made a motion to dismiss counts VIII, IX, X, XII, and XIII. The court granted Zurn’s motion for Counts VIII, IX, and X only: “Counts VIII (product liability), IX (negligence), and X (strict liability) sound in tort. Zurn argues that, because Plaintiffs allege no injury other than to the PEX systems and the yellow brass fittings themselves, the economic loss rule bars their tort claims. The court agrees.”
The court disagreed with Zurn’s motion regarding Count XII: “Count XII asserts that Zurn has breached the implied warranty of merchantability. Zurn argues that Count XII is barred by the applicable statute of limitations and that Plaintiffs do not sufficiently allege an injury. The court disagrees.”
Zurn’s motion regarding Count XIII was also denied: “Count XIII asserts that Zurn violated section 480-2 of Hawaii Revised Statutes.” Furthermore, “Plaintiffs allege that Zurn ‘engaged in unfair and deceptive acts or practices when [it] designed, manufactured and sold Yellow Brass Fittings.’ Zurn argues that Plaintiffs fail to state a claim under section 480-2(a) because their claims are barred by the statute of limitations and they do not adequately allege reliance or a cognizable injury. The court disagrees.”
The court denied the motion for summary judgment with respect to Counts XI and XII.
Castle & Cooke sought to dismiss “Plaintiffs’ claims against it under section 672E-2 of Hawaii Revised Statutes, which provides for dismissal when claimants fail to comply with chapter 672E.” There was some discussion regarding the test results. Apparently, the plaintiffs had failed to provide a written notice of claim at least 90 days before filing the action. However, it is unclear if the Plaintiffs have since complied with the requirements of the chapter. “The court has received no supplemental information from either party about whether any test results from another case have been turned over or whether those materials are subject to a confidentiality agreement. The record at this point does not establish noncompliance with the requirement in chapter 672E to provide such information. The court therefore denies the motion to dismiss.”
In summary, “Zurn’s motion to dismiss is granted as to Count VIII, Count IX, and Count X. Zurn’s motion to dismiss is denied with respect to Plaintiffs’ other claims. Zurn’s request for a more definite statement and its summary judgment motion are denied. Plaintiffs are given leave to file an amended Complaint no later than May 21, 2012.” Furthermore, “the court denies Castle & Cooke’s motion, but directs Plaintiffs to file, within two weeks, either a certificate of compliance with section 672E-3(c), or an explanation as to why they have not complied. Castle & Cooke may submit a response within two weeks of Plaintiffs’ submission. Each party’s submission is limited to 1000 words.”
Read the court’s decision…
Joinder vs. Misjoinder in Colorado Construction Claims: Roche Constructors v. One Beacon
July 10, 2012 — David McLain, Higgins, Hopkins, McLain & Roswell, LLC
Often, those practicing in the construction defect field have faced questions concerning the joinder of a party. Recently, the U.S. District Court for the District of Colorado weighed in on the requirements for joinder under the Colorado Rules of Civil Procedure. See Roche Constructors, Inc. v. One Beacon America Ins. Co., 2012 WL 1060000 (D. Colo. 2012). Roche secured a construction contract to build a detention facility for the Lincoln County Sheriff’s Office in Lincoln County, Nebraska. In turn, Roche entered into a subcontract with Dobberstein Roofing Company, Inc. in October 2009 to install the roofing system and other related work at the detention facility. The subcontract agreement required Dobberstein to maintain adequate commercial general liability insurance and to add Roche as an additional insured under the policy. Roche maintained a builder’s risk policy issued by OneBeacon America Insurance Company and Dobberstein secured a certificate of liability insurance underwritten by Transportation Insurance Company (“TIC”). Id. at *1.
Roche alleged that Dobberstein constructed the roofing system in a negligent manner in violation of the subcontract. Roche claims it incurred additional costs to repair structural damage to the roofing system as a result of Dobberstein’s negligent work. In order to cover said damage, Roche tendered insurance claims to OneBeacon and TIC.
Read the full story…
Reprinted courtesy of David McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com
Insurer Unable to Declare its Coverage Excess In Construction Defect Case
January 6, 2012 — CDJ Staff
The Ninth Circuit Court of Appeals has upheld a summary judgment in the case of American Family Mutual Insurance Co. v. National Fire & Marine Insurance Co. Several other insurance companies were party to this case. In the earlier case, the US District Court of Appeals for Arizona had granted a summary judgment to Ohio Casualty Group and National Fire & Marine Insurance Company. At the heart of it, is a dispute over construction defect coverage.
The general contractor for Astragal Luxury Villas, GFTDC, contracted with American Family to provide it with a commercial liability policy. Coverage was issued to various subcontractors by Ohio Casualty and National Fire. These policies included blanket additional insured endorsements that provided coverage to GFTDC. The subcontractor policies had provisions making their coverage excess over other policies available to GFTDC.
The need for insurance was triggered when the Astragal Condominium Unit Owners Association filed a construction defect claim in the Arizona Superior Court. CFTDC filed a third-party claim against several subcontractors. The case was settled with American Family paying the settlement, after which it filed seeking reimbursement from the subcontractor’s insurers. The court instead granted summary judgment in favor of Ohio Casualty and National Fire.
American Family appealed to the Ninth Circuit for a review of the summary judgment, arguing that the “other insurance” clauses were “mutually repugnant and unenforceable.” The Ninth Circuit cited a case from the Arizona Court of Appeals that held that “where two policies cover the same occurrence and both contain ‘other insurance’ clauses, the excess insurance provisions are mutually repugnant and must be disregarded. Each insurer is then liable for a pro rate share of the settlement or judgment.”
The court noted that unlike other “other insurance” cases, the American Family policy “states that it provides primary CGL coverage for CFTDC and is rendered excess only if there is ‘any other primary insurance’ available to GFTDC as an additional insured.” They note that “the American Family policy purports to convert from primary to excess coverage only if CFTDC has access to other primary insurance as an additional insured.”
In comparison, the court noted that “the ‘other insurance’ language in Ohio Casualty’s additional insured endorsement cannot reasonably be read to contradict, or otherwise be inconsistent with, the ‘other primary insurance’ provision in the American Family policy.” They find other reasons why National Fire’s coverage did not supersede American Family’s. In this case, the policy is “written explicitly to apply in excess.”
Finally, the Astragal settlement did not exhaust American Family’s coverage, so they were obligated to pay out the full amount. The court upheld the summary dismissal of American Family’s claims.
Read the court’s decision…
Fire Reveals Defects, Appeals Court Affirms Judgment against Builder
July 10, 2012 — CDJ Staff
The Arizona Court of Appeals has ruled in the case of Simms v. Nance Construction. After a fire damaged his home, Jerry Simms discovered some construction defects in the work of the builder, Nance Construction. Nance Construction completed the home in 2000 and it was damaged by fire in 2001. In the course of Simms’ suit against his neighbor, “defense experts opined both that Dusty Creek had negligently repaired the damage to Simms’ residence and that many defects found in the houses were the result of defects in the original construction.” Nance offered to make roof repairs. Simms responded with a list of “numerous construction defects,” stating this was “not a comprehensive and final list of items.” Nance offered to repair some while disputing others. Simms entered a lawsuit against Nance and other parties.
Nance first sought a summary judgment, “asserting that Simms had failed to adequately disclose the repairs for which he sought to hold Nance responsible.” The court denied this. It also would not allow Nance to introduce evidence that Simms had been denied a license by the Arizona Department of Gaming over “questionable business practices, illegal activities, and financial transactions with a person purportedly involved in organized crime.”
During the suit, Simms contracted with Advanced Repair Technologies “for repairs that included a complete remodel of the roof and the exterior stucco system.” Nance later claimed that the cost of ART’s repair was unreasonable, claiming that it should have cost about $600,000 instead of the $1.5 million for which Simms contracted. The jury found against Nance, with a judgment of $870,200 of which half was due to the roofing subcontractor.
After the verdict, Nash moved for a new trial, stating that the jury should have heard expert testimony on whether the contract price was reasonable. Nance also “argued that the trial court had erred in refusing to allow Nance to impeach Simms’ credibility with his purported prior acts of dishonesty.” These motions were denied and Nance appealed.
The appeals court upheld the trial court on all counts. The court found that, despite the contention made by Nance, the jury had sufficient information to determine if the cost of the repairs were reasonable. The court also found that Simms had given Nance an opportunity to propose repairs. The law, however, “does not require the Plaintiff to accept an offer for repairs,” adding that “the record makes clear that the parties were far apart in their belief of the nature of repairs necessary.” Nor did the court find that Nance should have been allowed to introduce evidence to impeach Simms’ credibility.
Although judgment of the lower court was affirmed, the court took the discretion to decline to award attorneys’ fees to Simms, although he was awarded costs.
Read the court’s decision…
The Flood Insurance Reform Act May be Extended to 2016
April 7, 2011 — April 7, 2011 Beverley BevenFlorez - Construction Defect Journal
The Flood Insurance Reform Act of 2011 (H. R. 1309) has been referred to the House Committee on Financial Services—the first step in the legislative process. The bill, if passed, would extend the program to September 30, 2016. It is currently slated to be terminated September 30 of this year. The bill also contains changes to premium rates, mapping protocols, and privatization initiatives.
H. R. 1309 has garnered the support of several Insurance organizations. Leigh Ann Pusey, president and CEO of the American Insurance Association (AIA), sent a letter of support to the Chair and Ranking member of the House Financial Services Subcommittee. “AIA has advocated for a long term reauthorization of the NFIP to protect consumers and help increase stability for real estate transactions and policyholders,” Pusey said. “AIA believes the five-year extension contained in HR 1309, will provide certainty in the flood program thereby increasing consumer and business confidence in the NFIP.”
Jimi Grande, senior vice president of federal and political affairs for the National Association of Mutual Insurance Companies (NAMIC) spoke out in support of the bill. “For the NFIP to survive, the prices for flood insurance must reflect the actual costs of flood risk for a property,” Grande said. “HR 1309 will provide that transparency. In addition, the Technical Mapping Advisory Council will give communities a voice in the flood mapping process, fostering a better understanding of what flood maps represent and how they are made.”
Read H. R. 1309...
Read the American Insurance Association statement...
Read the NAMIC Press Release...
Arbitration Clause Found Ambiguous in Construction Defect Case
October 28, 2011 — CDJ Staff
The California Court of Appeals ruled on September 28 in the case of Burch v. Premier Homes. Ms. Burch bought a home after negotiating various addendums to the contract. The contract was a standard California Association of Realtors contract to which both the buyer and seller made additions. At issue in this case was paragraph 17 of the contract which included that “Buyer and Seller agree that any dispute or claim in Law or equity arising between them out of this Agreement or resulting transaction, which is not settled through mediation, shall be decided by neutral, binding arbitration.”
The seller/defendant’s Addendum 2 “included provisions relating to the arbitration of disputes that may arise.” Ms. Burch’s realtor, Lisa Morrin, told Burch that “she had never seen a proposed contractual provision that would require a home buyer to agree to arbitrate with a builder over construction defects.” Ms. Burch told Morrin that she did not want to buy the property if she would have to give up her rights under California law.
As part of Addendum 2, the buyer had to buy a warranty from the Home Buyers Warranty Corporation. The sale was held up for a while, as Ms. Burch waited for a copy of the warranty. When she received it, she took further exception to Addendum 2. Scott Warren of Premier Homes said he could not sell the property without Addendum 2. Ms. Burch told her realtor that despite the claims made by Mr. Warren that this was for her benefit, she felt it was more to the benefit of Premier Homes. Don Aberbrook of HBW agreed to the clause, contained in the final sentence of Addendum 2, being struck.
Subsequent to buying the home, Burch submitted a claim concerning construction defects. HBW denied the claim and Burch began an action against the defendants. Premier filed a motion to compel arbitration which Burch opposed.
The trial court ruled that the striking out of the arbitration clause at the end of Addendum 2 “created a conflict with respect to the parties’ intent as to the scope of arbitration.” The trial court found that “the parties’ intention was to preserve Burch’s right to make state law claims including her right to a jury trial for any non-warranty claims against the builder.”
The appeals court in their ruling looked at the standard of review and concluded that the purchase agreement was ambiguous and that extrinsic evidence was required to resolve that ambiguity. As the contract contained contradictory provisions as to whether or not arbitration was required, it was necessary for the trial court to examine these claims. The appeals court found that the evidence supported the conclusions of the trial court.
Finally, the appeals court found that “there was no valid agreement to arbitrate disputes.” The court noted that arbitration can only happen by mutual consent and “it is clear that Burch did not enter into an agreement to arbitrate any construction defect disputes she might have.”
Read the court’s decision…
Ohio Adopts Energy-Efficient Building Code
June 19, 2012 — CDJ Staff
In a compromise between environmental groups, who were looking for stricter standards, and homebuilders, who were trying to contain building costs, the state of Ohio has adopted buildings codes that will increase the energy efficiency of new homes. The estimated costs are about $1,100 with estimated annual savings of $230. According to Corey Roblee of the International Code Council, “It’s something needed in the state of Ohio.”
The Ohio Home Builders Association opposed a proposal to adopt the guidelines of the International Code Council. Builders will be able to either follow the ICC guidelines or they can use the Ohio guidelines to meet the same energy efficiency. Vincent Squillace, the executive vice president of the OHBA, said, “We came up with an equivalent code that’s more strict but is about $2,000 cheaper per home to implement than the original code.”
The new code will require that at least 75% of lighting must be high efficiency, increases the degree of insulation, and specifies more efficient windows, among other changes.
Read the full story…
Broker Not Liable for Failure to Reveal Insurer's Insolvency After Policy Issued
March 28, 2012 — Tred Eyerly, Insurance Law Hawaii
Faced with an issue of first impression in California, the Court of Appeals held that a broker was not liable for failing to reveal the insurer's insolvency occurring after issuance of the policy. Pacific Rim Mechanical Contractors, Inc. v. Aon Risk Ins. Serv. West, Inc., 2012 Cal. App. LEXIS 232 (Cal. Ct. App. Feb. 28, 2012).
The developer for a construction project in downtown San Diego retained Aon as its broker to secure coverage. Aon procured a general liability policy for the project with Legion Indemnity Company. Legion was solvent when it issued the policy.
The developer hired Pacific Rim (“PacRim”) as one of several subcontractors on the project. The parties entered into a contract in which the developer agreed to provide PacRim with liability insurance through an Owner Controlled Insurance Program (“OCIP”). Aon was not a party to the contract and PacRim was never its client. PacRim, however, enrolled in the OCIP by contacting Aon and providing all necessary paperwork.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Geometrically Defined Drainage Cavities in EIFS as a Guard Against Defects
July 10, 2012 — CDJ Staff
The blog Stucco & Insulation Contractor writes up some details on a “relatively new modification to modern Exterior Insulation Finish Systems,” known as “geometrically defined insulation boards.” They note that the insulation has grooves cut in the back to provide a route for water to drain, instead of getting trapped. They note that when EIFS is installed by a skilled applicator, this is unnecessary. However, with less experienced (and cheaper) installers, problems are more likely.
By cutting these channels, the application of EIFS is rendered “idiot proof,” as they note. Their preference would be that EIFS installers take the time to do the job right, but call this “a step in the right direction.”
Read the full story…
Flooded Courtroom May be Due to Construction Defect
September 1, 2011 — CDJ Staff
The General Services Administration wouldn’t pin it on a construction defect, but a spokesperson said that a pipe that was misaligned during installation was the likely cause of a flood in the Thomas F. Eagleton US Courthouse on August 23. According to the St. Louis Dispatch, the burst pipe caused a 17-story waterfall in the courthouse, soaking ceilings and floors, and drenching the building’s contents.
The building was dedicated eleven years ago. During the nearly ten years before the building was complete, there were construction disputes and soil contamination issues.
Read the full story…
Ohio Court Finds No Coverage for Construction Defect Claims
March 28, 2012 — Tred Eyerly, Construction Law Hawaii
Charles and Valerie Myers hired Perry Miller to build their home. Myers v. United Ohio Ins. Co., 2012 Ohio App. LEXIS 287 (Ohio Ct. App. Jan. 26, 2012). After completion of the home, Miller was again hired to construct an addition which included a full basement, staircases, bathroom, bedroom, hallway and garage.
After the addition was completed, one of the basement walls began to crack and bow. Miller began to make repairs, but eventually stopped working on the project. Other contractors were hired to make repairs, but further problems developed. A second basement wall began to bow and crack, allowing water into the basement. The wall eventually had to be replaced. Subsequently, the roof over the addition began to leak in five or six places before the drywall could be painted. The leaks caused water stains on the drywall and caused it to separate and tear. It was discovered the roof needed to be replaced.
The Myers sued Miller and his insurer, United Ohio Insurance Company. The trial court ruled that the policy did not provide coverage for faulty workmanship, but did provide coverage for consequential damages caused by repeated exposure to the elements. United Ohio conceded liability in the amount of $2,000 to repair water damage to the drywall. United Ohio was also found liable for $51,576, which included $31,000 to repair the roof and ceiling and $18,576 to replace the basement wall.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Retaining Wall Contractor Not Responsible for Building Damage
July 20, 2011 — CDJ Staff
The Court of Appeals of Indiana ruled on July 8 in the case of Rollander Enterprises, Inc. v. H.C. Nutting Co. Judge Baily wrote the opinion affirming the decision of the trial court.
The case involved an unfinished condominium complex, the Slopes of Greendale, in Greendale, Indiana. Rollander is a real estate development company incorporated in Ohio. One of the issues in the case was whether the case should be settled in the Indiana courts or be tried in Ohio. The project was owned by a special purpose entity limited liability corporation incorporated in Indiana.
Rollander hired Nutting to determine the geological composition of the site. Nutting’s report described the site as “a medium plastic clay containing pieces of shale and limestone.” The court summarized this as corresponding with “slope instability and landslides.” Rollander then hired Nutting to design the retaining walls, which were constructed by Scherziner Drilling.
After cracking was discovered on State Route 1, the walls were discovered to be inadequate. More dirt was brought in and a system of tie-backs was designed to anchor the walls. Not only were the tie-backs unsightly, local officials would not approve the complex for occupancy. Further, the failure of the wall below one building lead to damage of that building.
The court concluded that since almost all events occurred in Indiana, they rejected Rollander’s contention that the case should be tried in Ohio. Further, the court notes “the last event making Nutting potentially liable on both claims was an injury that occurred in Indiana and consequently, under the lex loci delicti analysis, Indiana law applies.”
Nor did the court find that Nutting was responsible for the damage to the rest of the project, citing an Indiana Supreme Court ruling, that “there is no liability in tort to the owner of a major construction project for pure economic loss caused unintentionally by contractors, subcontractors, engineers, design professionals, or others engaged in the project with whom the project owner, whether or not technically in privity of contract, is connected through a network or chain of contracts.”
The court concluded:
Because Rollander was in contractual privity with Nutting, and Indy was connected to Nutting through a chain of contracts and no exception applies, the economic loss rule precludes their recovery in tort. Damage to Building B was not damage to "other property," and the negligent misrepresentation exception to the economic loss rule is inapplicable on these facts. The trial court therefore did not abuse its discretion by entering judgment on the evidence in favor of Nutting on the Appellants' negligence and negligent misrepresentation claims.
Read the court’s decision…
Allowing the Use of a General Verdict Form in a Construction Defect Case Could Subject Your Client to Prejudgment Interest
August 2, 2012 — Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC
A recent opinion from the Colorado Court of Appeals is a cautionary tale concerning the calculation of pre-judgment interest. See Hendricks v. Allied Waste Transportation, Inc., 2012 WL 1881004 (Colo. App. 2012). The Hendricks sued Allied after one of its drivers backed into the corner of their home with an Allied garbage truck. At trial, a jury awarded the Hendricks $160,100 in damages. Although the jury was instructed on the cost of repairs, diminution in value, and non-economic damages, the parties agreed to a general verdict form that did not ask the jury to specify the types of damages awarded. The Hendricks sought to amend the judgment to include prejudgment interest and costs, which the trial court granted.
Allied appealed, arguing that the trial court erred by awarding the Hendricks prejudgment interest from the date their property was damaged. Id. at *7. The Colorado Court of Appeals found no error, and affirmed.
Read the full story…
Reprinted courtesy of Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Anderson can be contacted at anderson@hhmrlaw.com
Ohio Court Finds No Coverage for Construction Defect Claims
March 1, 2012 — Tred Eyerly, Insurance Law Hawaii
Charles and Valerie Myers hired Perry Miller to build their home. Myers v. United Ohio Ins. Co., 2012 Ohio App. LEXIS 287 (Ohio Ct. App. Jan. 26, 2012). After completion of the home, Miller was again hired to construct an addition which included a full basement, staircases, bathroom, bedroom, hallway and garage.
After the addition was completed, one of the basement walls began to crack and bow. Miller began to make repairs, but eventually stopped working on the project. Other contractors were hired to make repairs, but further problems developed. A second basement wall began to bow and crack, allowing water into the basement. The wall eventually had to be replaced. Subsequently, the roof over the addition began to leak in five or six places before the drywall could be painted. The leaks caused water stains on the drywall and cause it to separate and tear. It was discovered the roof needed to be replaced.
The Myers sued Miller and his insurer, United Ohio Insurance Company. The trial court ruled that the policy did not provide coverage for faulty workmanship, but did provide coverage for consequential damages caused by repeated exposure to the elements. United Ohio conceded liability in the amount of $2,000 to repair water damage to the drywall. United Ohio was also found liable for $51,576, which included $31,000 to repair the roof and ceiling and $18,576 to replace the basement wall.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Construction Defect Case Not Over, Despite Summary Judgment
November 7, 2012 — CDJ Staff
The Supreme Court of Oregon has concluded in an en banc decision that a motion to reconsider a summary judgment is not a motion for a new trial. In coming to their conclusion the court overturned an earlier Oregon Supreme Court case, Carter v. U.S. National Bank. Although the decision does not bear on construction defects, the underlying case did. Due to the decision, these claims can now be evaluated in a trial.
The case, Association of Unit Owners of Timbercrest Condominiums v. Warren, came about after an apartment complex was converted into condominium units. The developers hired Big Al’s Construction for some of the remodeling work. The condominium association later sued the developer and the contractor over claims of construction defects. The defendants filed a motion for summary judgment, which the court granted.
But that wasn’t the end of things. The plaintiff soon filed a “motion to reconsider,” noting that the summary judgment seemed to be in conflict with both law and other recent rulings, and additionally, the grounds for the decision were not in the order. The judge then notified the parties that the court had “pulled the trigger too quickly” and had seven questions for the parties to answer.
The court dismissed all claims against the defendants. The defendants filed their responses, objecting that that “‘there is no such thing’ as a motion for reconsideration.” Further, while “the rules do allow for post-judgment review of pre-judgment rulings through a motion for a new trial,” the plaintiffs had not filed for a new trial. But did they need one? They did file an appeal.
The judge in the case admitted that there was no such thing as a motion to reconsider, and felt bad about prematurely signing the judgment. The case was sent to the Court of Appeals to determine if the motion to reconsider was a request for a new trial. The Court of Appeals concurred.
In reviewing the decision, the Oregon Supreme Court concluded that there were a maximum of three questions to address. Was the motion for reconsideration a motion for a new trial? If so, was the later notice of appeal premature? And if so, was the plaintiff required to file a new appeal? The court determined that the answer to the first question was no.
Prior decisions pointed to the conclusion “that a motion for reconsideration of a summary judgment amounts to a motion for a new trial,” but here the court concluded that “our prior cases erred,” and turned to the summary judgment rule for clarification. The court noted that “the rule contemplates that summary judgment and trial are separate and distinct events.” With this conclusion, the Oregon Supreme Court remanded the case to the Court of Appeals for further proceedings.
Read the court’s decision…
Tucson Officials to Discuss Construction Defect Claim
July 10, 2012 — CDJ Staff
The mayor of Tucson, Arizona and the city council scheduled a meeting on June 26, 2012 in order to consult with the city’s attorneys concerning possible construction defect litigation involving the Martin Luther King, Jr. apartment building in that city. The memorandum was authored by Richard Miranda, the Tucson city manager.
Read the full story…
Tenth Circuit Finds Insurer Must Defend Unintentional Faulty Workmanship
December 9, 2011 — Tred R. Eyerly, Insurance Law Hawaii
Applying Colorado law, the Tenth Circuit found a duty to defend construction defect claims where the faulty workmanship was unintentional. Greystone Const. Inc. v. National Fire & Marine Ins. Co., 2011 U.S. App. LEXIS 22053 (10th Cir. Nov. 1, 2011). A prior post [here] discussed the Tenth Circuit’s certified question to the Colorado Supreme Court in this matter, a request that was rejected by the Colorado court.
In two underlying cases, Greystone was sued by the homeowner for damage caused to the foundation by soil expansion. In both cases, the actual construction was performed by subcontractors. Further, in neither case was the damage intended or anticipated. Nevertheless, National Union refused to defend, contending property damage resulting from faulty construction was not an occurrence.
Relying on a Colorado Court of Appeals case, General Security Indemn. Co. of Arizona v. Mountain States Mut. Cas. Co., 205 P.3d 529 (Colo. App. 2009), the district court granted summary judgment to National Union.
On appeal, the Tenth Circuit first considered whether Colorado legislation enacted to overturn General Security could be applied retroactively. The statute, section 13-20-808, provided courts "shall presume that the work of a construction professional that results in property damage, including damage to the work itself or other work, is an accident unless the property damage is intended and expected by the insured."
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Are Construction Defects Covered by Your General Liability Policy?
July 10, 2012 — CDJ Staff
Construction firms are finding that their insurers are denying construction defect claims and the courts are siding with the insurers, according to Kelly M. Gindele, writing in the Martindale-Hubble Legal Library. Ms. Gindele notes that when construction defect claims are not covered, firms can end up with “multi-million dollar claims” that it has to pay “out of its own pocket.” She notes that in Kentucky and Ohio, if “the insured’s work causes an unforeseen and unintended event to occur?Ķthere is not occurrence under the policy.” Further, if there is an occurrence, the court will “look for an exception to coverage.”
She also notes that contractors may not hold sufficient coverage, either by limiting the amounts or the time. She notes that while “insurers generally try to limit coverage for defect claims to one year,” that “construction defects may not be found in a year’s time.”
Ms. Ginele recommends that contractors “hire an insurance company with extensive experience in this field” and “independent legal counsel with insurance knowledge,” to avoid finding themselves “with limited or even no coverage when it needs it most.”
Read the full story…