Largest Per Unit Settlement Ever in California Construction Defect Case?
October 28, 2011 — CDJ Staff
BusinessWire reports that the Chelsea Court Homeowners Association has settled their construction defect case for $5.4 million. That works out to $169,000 per unit, which BusinessWire describes as “California’s largest per-unit recovery known to be on record to date.”
Most of the money in the settlement is coming from insurance companies for the builder and thirteen subcontractors. Issues included roof and window leaks, deck failures, and unsafe walkways.
Read the full story...
Manhattan Developer Breaks Ground on $520 Million Project
November 18, 2011 — CDJ Staff
Rebuilding an area of Midtown West that has been condemned for decades, the Gotham Organization has broken ground on a 1,200-unit project that will include housing for a variety of household incomes and a school. One unit of the project will be affordable housing for families of annual incomes up to $40,000. Another will be for middle-income households. Additionally, there will be a 31-story tower with 550 luxury units.
The site CityBiz quotes Mayor Michael Bloomberg, as saying that the project “will grow our economy by creating 2,900 construction-related jobs.” The president of the Gotham Organization, David L. Picket notes that it will “create hundreds of new jobs, generate millions of dollars in revenue for the construction industry, contribute towards the building of a new primary, and provide homes to thousands of New Yorkers.”
Read the full story…
Insurer Able to Refuse Coverage for Failed Retaining Wall
October 28, 2011 — CDJ Staff
The Eleventh District of the US Court of Appeals has ruled in the case of Nix v. State Farm Fire & Casualty Company. In this case, the Nixes filed a claim after a portion of the retaining wall in their home collapsed and their basement flooded. State Farm denied the claim “on the ground that the policy excluded coverage for collapses caused by defects in construction and for damage caused by groundwater.”
The court reviewed the Nixes’ policy and found that State Farm’s statement did specifically exclude both of these items. In reviewing the lower court’s ruling, the appeals court noted that State Farm’s expert witness, Mark Voll, determined that the retaining wall “lacked reinforcing steel, as required by a local building code, and could not withstand the pressure created by groundwater that had accumulated during a heavy rainfall.” Additionally, a french drain had been covered with clay soil and so had failed to disperse the groundwater.
The Nixes argued that the flooding was due to a main line water pipe, but their opinions were those of Terry Nix and the contractor who made temporary repairs to the wall. “Those opinions were not admissible as lay testimony. Neither Nix nor the contractor witnessed the wall collapse or had personal knowledge about the construction of the Nixes’ home.”
The lower court granted a summary judgment to State Farm which has been upheld by the appeals court.
Read the court’s decision…
Preparing For the Worst with Smart Books & Records
November 7, 2012 — Douglas Reiser, Builders Counsel
Contractors are often too caught up in keeping the wheel of business churning to recognize deficiencies in how their records are managed. Working hard and working often tend to leave little time for consideration of your documents. But all too often I see the unthinkable, a contractor gets into trouble and has to call on its surety for help. At that point, you might finally get your first dose of reality about your records ?Äì and it can cost you.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Granting Stay, Federal Court Reviews Construction Defect Coverage in Hawaii
January 6, 2012 — Tred Eyerly, Insurance Law Hawaii
The federal district court ultimately stayed a construction defect case, but offered comments on the current status of coverage disputes for such defects in Hawaii. See National Union Fire Ins. Co. of Pittsburgh, Pa. v. Simpson Mfg. Co., 2011 U.S. Dist. LEXIS 128481(D. Haw. Nov. 7, 2011).
National Union filed a complaint for declaratory relief to establish it had no duty to defend or to indemnify Simpson Manufacturing Company in four actions pending in the Hawaii state courts. The state court actions concerned allegedly defective hurricane strap tie hold downs that were manufactured and sold by Simpson. The hurricane ties allegedly began to prematurely corrode and rust, causing cracking, spalling and other damage to homes.
National Union contended the underlying allegations did not constitute "property damage" caused by an "occurrence," as defined in the policies.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Florida Contractor on Trial for Bribing School Official
October 28, 2011 — CDJ Staff
Lloyd Whann, an executive in M. M. Parrish Construction, a Gainesville, Florida firm, is going to trial over claims that he bribed a school district official with more than $50,000 in gifts. The trial has been pushed to March of 2012, in order for his defense to review documents.
Bob Williams, the former school official, plead guilty to conspiracy to commit bribery. He agreed to testify against Whann and M.M. Parrish Construction.
Read the full story...
Australian Group Seeks Stronger Codes to Combat Dangerous Defects
October 23, 2012 — CDJ Staff
The Owners Corporation Network, a group that represents condominium owners in Australia, has raised concerns about building defects in high-rise building that can lead to safety problems. The group prepared a statement which would strengthen the rights of owners, but the government official, Fair Trading Minister Anthony Roberts, declined to sign it. A spokesperson for the group cited a fatal fire at a Sydney high rise, noting that “there had been issues of certification which has been a concern of the Owners Corporation Network.” The Australian Broadcasting Network reports that the government will be reviewing the laws concerning high-rise apartment buildings.
Read the full story…
Insurer Beware: Failure to Defend Ends with Hefty Verdict
June 1, 2011 — Douglas Reiser in the Builders Counsel Blog
Served with a lawsuit that you turned over to your insurer? Insurer refusing to defend you? Well, find some hope in this news. Washington’s IFCA has the claws to ensure that insurers perform their duties.
Contractors heavily rely on the defense provisions of their Commercial General Liability (CGL) policies. In construction, a legal dispute can easily rear its head when you least expect it. Luckily, Washington registered contractors are required to maintain CGL insurance. That insurance often provides contractors with adequate legal defense in the event that they are sued.
But, what if your insurer turns down the defense request? They might be staring at massive damages. A current Reiser Legal client, Australia Unlimited, Inc., recently won a large verdict against Hartford Insurance, after the insurer unreasonably denied their claim. The firm who represented Australia Unlimited Inc. in that case, Hackett Beecher and Hart, were successful in procuring a $5.43 Million verdict
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Florida trigger
August 4, 2011 — CDCoverage.com
In Mid-Continent Casualty Co. v. Siena Home Corp., No. 5:08-CV-385-Oc-10GJK (M.D. Fla. July 8, 2011), insured residential real estate developer Siena was sued by homeowners seeking damages for moisture penetration property damage resulting from exterior wall construction defects. Siena’s CGL insurer Mid-Continent filed suit seeking a declaratory judgment of no duty to defend or indemnify in part on the basis that the alleged “property damage” did not manifest during the Mid-Continent policy period.
Read the full story…
Reprinted courtesy of CDCoverage.com
Was Jury Right in Negligent Construction Case?
September 30, 2011 — CDJ Staff
Yes, said the South Carolina Court of Appeals in Pope v. Heritage Communities, Inc. Heritage Communities developed Riverwalk, a community in South Carolina. During the earlier trial, HCI “conceded that construction defects existed at Riverwalk, and repairs needed to be made.” The trial court found that the construction was negligent, awarding the property owners association $4.25 million in actual damages and $250,000 in punitive damages, with the class of owners awarded $250,000 in actual damages and $750,000 in punitive damages. HCI appealed on nine issues. All were rejected by the appeals court.
The court rejected HCI’s claim that the judge’s instruction to the jury suggested to the jury that “the court had already determined that Appellants were willful, wanton, and reckless.” But here, the appeals court found “no reversible error.”
The general contractor for Riverwalk was BuildStar. Off-site management and sale were managed by Heritage Riverwalk, Inc., which also owned title to the property. Both these companies were owned by Heritage Communities, Inc. During the trial, an HCI employee testified that “the three corporations shared the same officers, directors, office, and telephone number.” The trial court found that the three entities were amalgamated. This was upheld by the appeals court.
Nor did the appeals agree with the HCI that the trial court had improperly certified a class. The owners were seen as properly constituting a class. Further, the court held that the property owners’ losses were properly included by the trial court. HCI objected at trial to the inclusion of evidence of subsequent remedial measures, however, as they did not object that it was inadmissible, the issue could not be addressed at appeal.
HCI argued on appeal that the trial court should not have allowed evidence of defects at other HCI developments. The appeals court noted that “the construction defects at the other HCI developments were substantially similar to those experienced by Riverwalk.”
The court additionally found that the negligence claims, the estimated damages (since full damage could not be determined until all defective wood was removed), and the award of punitive damages were all properly applied.
Read the court’s decision…
Joinder vs. Misjoinder in Colorado Construction Claims: Roche Constructors v. One Beacon
July 10, 2012 — David McLain, Higgins, Hopkins, McLain & Roswell, LLC
Often, those practicing in the construction defect field have faced questions concerning the joinder of a party. Recently, the U.S. District Court for the District of Colorado weighed in on the requirements for joinder under the Colorado Rules of Civil Procedure. See Roche Constructors, Inc. v. One Beacon America Ins. Co., 2012 WL 1060000 (D. Colo. 2012). Roche secured a construction contract to build a detention facility for the Lincoln County Sheriff’s Office in Lincoln County, Nebraska. In turn, Roche entered into a subcontract with Dobberstein Roofing Company, Inc. in October 2009 to install the roofing system and other related work at the detention facility. The subcontract agreement required Dobberstein to maintain adequate commercial general liability insurance and to add Roche as an additional insured under the policy. Roche maintained a builder’s risk policy issued by OneBeacon America Insurance Company and Dobberstein secured a certificate of liability insurance underwritten by Transportation Insurance Company (“TIC”). Id. at *1.
Roche alleged that Dobberstein constructed the roofing system in a negligent manner in violation of the subcontract. Roche claims it incurred additional costs to repair structural damage to the roofing system as a result of Dobberstein’s negligent work. In order to cover said damage, Roche tendered insurance claims to OneBeacon and TIC.
Read the full story…
Reprinted courtesy of David McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com
Home Builder Doesn’t See Long Impact from Hurricane
November 7, 2012 — CDJ Staff
No one needs to tell Toll Brothers about the impact of Hurricane Sandy. The Wall Street Journal reports that the home building company lost power as a result of the storm. Martin Connor, the company’s CFO, told the Journal that he did not expect the hurricane to have a big effect on sales. Luckily for the company, many of its large projects are either sufficiently completed to provide shelter or too early in the process to be affected by the storm. “This type of weather event has limited impact on the market. It may move settlements later, and may defer people a weekend or two until they go out shopping. But it doesn’t have a long impact.”
Read the full story…
Las Vegas Home Builder Still in Bankruptcy
October 23, 2012 — CDJ Staff
American West Development attempted to exit Chapter 11 bankruptcy on September 27, but their plan was turned down by U.S. Bankruptcy Court Judge Mike Nakagawa. According to the Las Vegas Review-Journal, Judge Nakagawa rejected the plan over a trust fund for construction defects. America West’s attorney said they were hoping to complete the process by the end of the year.
Under approved portions of the plan, America West’s owner, Lawrence Canarelli, will retain control of the corporation, although he must contribute $10 million into the firm and an additional $1.5 million into the fund for construction defects. America West faces charges for construction defects reported in the broad range of “less than $20 million” to “as much as $80 million.”
Read the full story…
CC&Rs Not the Place for Arbitration Agreement, Court Rules
May 24, 2011 — CDJ Staff
In January, the California Court of Appeals ruled that an arbitration clause inserted in a development’s CC&Rs by the developer could not be enforced. The case, Villa Vicenza Homeowners Association v. Noble Court Development, involved a case in which, according to the opinion, “following the first sale Nobel controlled the board of directors of the Association and because the initial condominium buyers noticed defects in common areas and common facilities and did not believe Nobel had provided a reserve fund sufficient to repair the defects, the condominium owners brought a derivative action on behalf of the Association against Nobel.”
The court concluded, “The use of CC&R's as a means of providing contractual rights to parties with no interest in or responsibility for a common interest development is also problematic from the standpoint of determining what if any consideration would support such third-party agreements. By their terms the CC&R's bind all successors, even those with whom a third party such as Nobel has never had any contractual relationship and to whom Nobel has not provided any consideration.” The court determined that “the trial court did not err in denying Nobel's motion to compel arbitration.”