Texas exclusions j(5) and j(6).
April 27, 2011 — April 27, 2011, by CDCoverage.com
In Evanston Ins. Co. v. D&L Masonry of Lubbock, Inc., No. 07-10-00358-CV (Tex. Ct. App. April 18, 2011), insured masonry subcontractor D&L sued its CGL insurer Evanston to recover costs incurred by D&L for the replacement of window frames damaged by D&L while performing masonry work adjacent to the window frames. The trial court granted summary judgment for D&L.
Read the full story…
Reprinted courtesy of CDCoverage.com
After Breaching its Duty to Defend, Insurer Must Indemnify
August 11, 2011 — Tred Eyerly, Insurance Law Hawaii
In a brief decision analyzing Oregon law, the Ninth Circuit determined that once an insurer breaches its duty to defend, it must indemnify. See Desrosiers v. Hudson Speciality Ins. Co., 2011 U.S. App. LEXIS 12591 (9th CIr. June 21, 2011).
The victim secured a judgment against the insured after he was beaten by another patron outside the insured's bar. Hudson Speciality Insurance refused to defend the insured, claiming the injury arose from an assault and battery, which excluded coverage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Judge Rejects Extrapolation, Harmon Tower to Remain Standing
November 7, 2012 — CDJ Staff
CityCenter has filed an emergency motion asking the Nevada Supreme Court to intervene in Judge Elizabeth Gonzalez’ order that the building’s defects cannot be extrapolated from those tested. CityCenter’s structural engineering expert “evaluated 397 of the Harmon’s critical structural elements and found all but one defective,” according to the article on Vegas.Inc. Judge Gonzalez would not permit this to be extrapolated to the untested 1,072, as the locations tested were not random.
Judge Gonzalez also ruled that if CityCenter does additional testing, they may not appeal her order that ruled the extrapolation inadmissible. CityCenter argued to the Nevada Supreme Court that “the notion that CityCenter should be forced to incur additional millions of dollars in testing costs and sanctions ?Äì on the condition that it waive its right to appeal this ruling ?Äì just to be permitted to present its own damages evidence, shocks the conscience.”
Gonzalez gave the okay to CityCenter to demolish the building, but its demolition would make any further testing impossible. Under Gonzalez’ ruling, the untested structural elements cannot b assumed to be defective.
Read the full story…
Federal Judge Dismisses Insurance Coverage Lawsuit In Construction Defect Case
December 9, 2011 — CDJ Staff
A federal judge dismissed a coverage lawsuit brought by Mid Continent Casualty Company against its insured, Greater Midwest Builders Ltd.
Plaintiff brought this declaratory judgment action in response to a suit filed in Johnson County District Court, seeking a judicial determination that it had no coverage obligation for claims asserted against its insured. This case was stayed until the state court action entered judgment against the insured. The prevailing parties then commenced a garnishment action against the plaintiff, and another insurance company, in state court in Missouri. The court was asked whether it should lift the stay and proceed with the case, or decline jurisdiction in favor of resolution in the Missouri state court.
The court granted the motion to dismiss holding that proceeding with the case would lead to protracted, piecemeal litigation, while deferring to the Missouri state court would decide all the claims involved in the dispute.
Read the court’s decision…
Contractors with Ties to Trustees Reaped Benefits from LA Community College Modernization Program
March 3, 2011 — Original reporting by Gale Holland, Michael Finnegan and Doug Smith, Los Angeles Times
In the latest installment of the “Billions To Spend” series of investigative reports focused on construction defects, management, and cost issues relevant to LACC’s Community College Modernization Projects, the LA Times examines the costs associated with the various layers of construction management and benefits that accrued to contractors with ties to LACC trustees.
The reporting by the Times is seemingly critical of the project’s utilization of “body shops” an industry term for companies that function as employers of record. The article segment published today cites a number of circumstances wherein their utilization appears to have escalated costs substantially.
“To gauge the cost of the staffing system, The Times reviewed thousands of pages of financial records from April 2007, when URS began managing the program, to July 2010. Reporters identified two dozen contractors serving as conduits for pay and benefits for employees they did not supervise.
At least 230 people were employed in this manner, at a total cost of about $40 million, the records show.
Approximately $18 million of the total was paid to the employees, according to the Times analysis. The remaining $22 million went to profit and overhead for contractors, the records indicate.
For employees on its own payroll, the district says that medical and other benefits increase compensation costs 40% above base salaries. So if the district had employed its construction staff directly, the total cost for the period studied would have been $25 million instead of $40 million, a savings of $15 million, The Times calculated.”
Read Full Story...
Contractor Underpaid Workers, Pocketed the Difference
February 10, 2012 — CDJ Staff
Property Casualty 360 reports that the owner of a construction company in California’s Bay Area has been arraigned in San Francisco Superior Court. The fifty-seven felony counts include charges of payroll theft and insurance fraud.
San Francisco District Attorney, George Gascon is quoted as saying that Doherty’s actions “hurts the honest businesses that were unable to successfully compete for these projects which the defendant was able to underbid and win as a result of this scheme.”
Frances Ann Doherty, owner of Doherty Painting & Construction has been charged with submitting false documentation as to what wages she paid her workers. It is alleged that over three years she pocketed $600,000. Additionally, she is charged with underpaying her insurer by more than $100,000 by submitting to them the fake payroll information.
Read the full story…
California Supreme Court Binds Homeowner Associations To Arbitration Provisions In CC&Rs
September 13, 2012 — Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP (http://www.gdandb.com).
The California Supreme Court ruled in Pinnacle Museum Tower Assn. v. Pinnacle Market Development (August 16, 2012, S186149) __ Cal.4th __ [2012 WL 3516134], that arbitration provisions within the covenants, conditions, and restrictions (“CC&Rs”) for condominium projects are enforceable against their homeowner associations. The ruling — two years in the making — was based on legislative history of laws governing common interest developments, and decades of decisional authority involving contracts and arbitration provisions.
In Pinnacle, a homeowners association sued a condominium builder for construction defects and resultant property damage to the common areas, and to the separate property interests held by the individual members. The builder moved to compel arbitration, based on a provision contained in the CC&Rs which required resolution of all construction disputes through binding arbitration. The association argued it could not be compelled to arbitrate these claims because it was not a party to the agreement to arbitrate, asserting “the Association did not bargain with [the builder] over the terms of the Project CC&R's or participate in their drafting.”
The Supreme Court rejected the association's argument on the grounds that the builder-authored CC&Rs complied with the Davis-Stirling Act (“the Act”) (Civil Code §1350, et seq.) ? the law that governs all common interest developments in California. Under the Act, builders and sellers of common interest residential units are required to provide a copy of the CC&Rs to all purchasers, as well as copies of the Department of Real Estate's public report, which informs purchasers of their rights and remedies as members of the association, and encourages each prospective purchaser to review the terms carefully before entering into any agreement. Further, the Act states all CC&Rs are enforceable, unless unreasonable, and inure to the benefit of and bind all owners in the development. (Civ. Code, §1354, subd. (a).) The Court found each owner who purchased a condominium in the project either expressly consented to the terms and provisions of the CC&Rs or was deemed to have consented to the terms at the time of purchase.
The Court also did not find the arbitration provision to be unconscionable. The Court indicated the provision was drafted and recorded in accordance with the Act, which allowed each prospective purchaser to make an informed decision prior buying a condominium unit. The provision also limited arbitration to construction defect disputes. The Court did not find any evidence the provision “shocked the conscience” or was “oppressive” in any way.
Pinnacle settles a decades-long conflict over whether arbitration provisions in CC&Rs for condominium projects are enforceable against homeowner associations and their members. It remains unclear, however, whether Pinnacle’s rationale will be applied to cases involving homeowner associations for single-family residences (as opposed to condominiums), assuming those CC&Rs have similar arbitration requirements. Regardless, the result of Pinnacle is clear, if arbitration provisions contained in condominium CC&Rs meet the fairness and unconscionability tests set out by the Court, more condominium construction defect cases brought by homeowner associations will be resolved through the arbitration process.
Read the court’s decision…
Printed courtesy of Stephen A. Sunseri and Aarti Kewalramani, Gatzke Dillon & Ballance LLP. Mr. Sunseri can be contacted at ssunseri@gdandb.com and Ms. Kewalramani can be contacted at akewalramani@gdandb.com.
District Court’s Ruling Affirmed in TCD v American Family Mutual Insurance Co.
May 10, 2012 — CDJ Staff
In the case, TCD, Inc. v American Family Mutual Insurance Company, the district court’s summary judgment was in favor of the defendant. In response, the Plaintiff, TCD, appealed “on the ground that the insurance company had no duty to defend TCD under a commercial general liability (CGL) insurance policy.” The appeals court affirmed the decision.
The appeals ruling provides a brief history of the case: “This case arises out of a construction project in Frisco, Colorado. The developer, Frisco Gateway Center, LLC (Gateway), entered into a contract with TCD, the general contractor, to construct a building. TCD entered into a subcontract with Petra Roofing and Remodeling Company (Petra) to install the roof on the building. The subcontract required Petra to "indemnify, hold harmless, and defend" TCD against claims arising out of or resulting from the performance of Petra’s work on the project. The subcontract also required Petra to name TCD as an additional insured on its CGL policy in connection with Petra’s work under the subcontract.”
Furthermore, “TCD initiated this case against Petra and the insurance company, asserting claims for declaratory judgment, breach of insurance contract, breach of contract, and negligence. The district court entered a default judgment against Petra, and both the remaining parties moved for summary judgment. The court granted summary judgment on the entirety of the action, in favor of the insurance company, concluding that the counterclaims asserted by Gateway against TCD did not give rise to an obligation to defend or indemnify under the CGL policy.”
The appeals court rejected each contention made by TCD in turn. First, “TCD contend[ed] that Gateway’s counterclaims constitute[d] an allegation of ‘property damage,’ which is covered under the CGL policy.” The appeals court disagreed. Next, “TCD argue[d] that [the court] should broaden or extend the complaint rule, also called the ‘four corners’ rule, and allow it to offer evidence outside of the counterclaims to determine the insurance company’s duty to defend in this case.” The appeals court was not persuaded by TCD’s argument.
The judgment was affirmed. Judge Roman and Judge Miller concur.
Read the court’s decision…
Fifth Circuit Asks Texas Supreme Court to Clarify Construction Defect Decision
November 7, 2012 — CDJ Staff
The Fifth Circuit Court has withdrawn its decision in Ewing Construction Company v. Amerisure Insurance Company, pending clarification from the Texas Supreme Court of its decision in Gilbert Texas Construction, L.P. v. Underwriters at Lloyd’s London. The Fifth Circuit had applied the Gilbert case in determining that a contractual liability exclusion barred coverage for faulty workmanship. The Insurance Journal reports that this decision was both applauded and criticized, with a concern noted that “an insurer would now have its pick of either the ‘your work’ exclusion or the contractual liability exclusion without the exception for subcontracted work.”
The Fifth Circuit is now asking the Texas Supreme Court two questions to clarify Gilbert, which Brian S. Martin and Suzanne M. Patrick see as a sign that the Court has realized that it overly expanded the scope of the earlier ruling. A response is expected from the Texas Supreme Court by spring 2013.
Read the full story…
Arbitration Clause Not Binding on Association in Construction Defect Claim
June 19, 2012 — CDJ Staff
Determining that a community’s CC&Rs do not form an agreement to arbitrate, the California Court of Appeals has reversed the decision of the Superior Court inVerano Condo. Homeowners the Ass’n v. La Cima Dev., LLC (Cal. App., 2012). La Cima purchased an apartment complex in December 2004, which they converted into condominiums. In the process, La Cima created the CC&Rs, under which the Verano Condominium Homeowners Association came into being. One section of the CC&Rs included arbitration clauses. Additionally, the purchase agreements for individual condominium units also contained arbitration clauses. Subsequently, the owners became aware of construction defect both in units and in the common areas. The Association sued La Cima both in its own interest and on behalf of its members. La Cima moved to compel arbitration, which was denied by the trial court. La Cima appealed.
The court concluded that “CC&Rs are insufficient to form an agreement to arbitrate between La Cima and the Association.” The court noted that “no evidence exists to show the Association consented to the terms of the CC&Rs, either explicitly or implicitly.”
The court agreed with La Cima that the arbitration agreement applied to those owners who had purchased their units directly from La Cima. Moreover, as the conversion to condominiums involved interstate commerce, in part because a Delaware company was selling condominiums located in California, the court held that the Federal Arbitration Act (FAA) applied, and as such “even a state constitutional standard, such as the the jury waiver provision requirements of the California Constitution, cannot be used to circumvent the FAA in the face of an otherwise valid arbitration agreement.”
However, the court also held that there was “no agreement in the CC&Rs between La Cima and owners who did not purchase units directly from La Cima,” adding that “no meeting of the minds between La Cima and these later purchasers and their successors occurred.” The court did not believe that “the Legislature intended that CC&Rs would be used to provide continuing and irrevocable contractual development or role as a representative of the owners of the development.”
The purpose of the CC&Rs, according to the court are to “protect owners from one another and permit enforcement of its terms by the Association.” The court stated that “La Cima relinquished its interests in the land by selling its property and may not assert any rights under the CC&Rs following the transfer of its ownership interest.
In its conclusion, the court determined that claims must be organized in three classes. The claims the association made against La Cima for defects in the common area “are not subject to any valid agreement to arbitrate.” The second category are those owners who did not purchase their units directly from La Cima. Here, also, the court found that the units “are similarly not subject to a valid arbitration agreement.”
The third category, however, was “owners who purchased units directly from La Cima.” The court held that these arbitration agreements were valid, and if the claims were to be taken up by the association, the association could only submit these claims to arbitration. The lower court was instructed to separate these claims, as here La Cima’s motion could be granted.
Read the court’s decision…
Another Guilty Plea In Nevada Construction Defect Fraud Case
April 25, 2012 — CDJ Staff
The eleventh defendant has entered a guilty plea in the ongoing federal investigation of construction defect fraud in the Las Vegas area. Mahin Quintero plead guilty to producing a false authentication feature, a misdemeanor. Ms. Quintero’s part in the scheme was to falsely authenticate signatures on loan documents for straw buyers. Ms. Quintero stated in court that she had been ordered to destroy her notary book three years ago. According to her plea bargain, the straw buyers did not appear in front of her when she notarized their signatures. As part of the scheme, the straw buyers would take control of homeowners associates, sending construction defect complaints and repairs to favored firms.
Read the full story…
Insurer Settles on Construction Defect Claim
July 10, 2012 — CDJ Staff
Law360 reports that Arch Specialty Insurance Company has settled over claims that it wrongly denied coverage in a construction defect claim. The court dismissed Arch with prejudice. Terms of the settlement were not disclosed and the attorneys made not comment to Law360.
Read the full story…
Ninety-Day Extension Denied to KB Home in Construction Defect Insurance Claim
July 10, 2012 — CDJ Staff
A magistrate judge has denied a request by KB Home Nevada to extend the time for service an additional ninety days. KB claims that St. Paul Fire & Marine Insurance Company has failed to defend them in a construction defect claim. However, the judge did grant KB an additional twenty days to effectuate service, noting that the request for additional time may be renewed.
Read the court’s decision…
Summary Judgment in Construction Defect Case Cannot Be Overturned While Facts Are Still in Contention in Related Cases
September 9, 2011 — CDJ Staff
The Alabama Court of Civil Appeals has dismissed an appeal of a summary judgment in the case Bella Investments, Inc. v. Multi Family Services, Inc. MFS was hired by Bella to be the general contractor for a hotel in Gardendale, Alabama. MFS hired various subcontractors, including the architect for the project. After completion of the hotel in April, 2006, Bella made requests for MFS to repair cracked floor tiles.
In August, 2008, Bella sued MFS, the architect, and various fictitiously named defendants. Subsequently, Bella amended its complaint, naming some of the fictitiously named defendants.
MFS in turn claimed that Bella’s claims were void under the statute of limitations and that Bella was in beach of contact by failing to pay MFS the full amount owed. MFS moved for summary judgment under the statute of limitations, which was granted by the court.
Bella requested that the court “alter, amend, or vacate its summary judgment order.” When this was denied, Bella appealed to the Alabama Supreme Court, which transferred the appeal to the Court of Civil Appeals. The Court of Appeals refused to vacate the summary judgment as claims that form part of the case against MFS are also part of Bella’s claims against the other defendants. For this reason, the court upheld the summary judgment.
Read the court’s decision…
Illinois Court Determines Insurer Must Defend Negligent Misrepresentation Claim
December 9, 2011 — Tred R. Eyerly, Insurance Law Hawaii
Although the insureds disclosed flooding problems in the basement, the buyers purchased their home. USAA Cas. Ins. Co. v. McInerney, 2011 Ill. App. LEXIS 1130 (Ill Ct. App. Oct. 31, 2011). In a supplemental disclosure, the insureds reported that during heavy rains light seepage occurred in the basement.
After moving in, the buyers experienced significant water infiltration and flooding in the basement. The buyers and their children also began to experience mold-related illnesses.
The buyers sued for rescission of the contract or, in the alternative, damages. They alleged breach of contract, fraudulent misrepresentation and negligent misrepresentation. In the claim for negligent misrepresentation, the buyers alleged that the insureds carelessly omitted the fact that there were material defects in the basement and foundation when they should have known of such defects.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
One Colorado Court Allows Negligence Claim by General Contractor Against Subcontractor
December 20, 2012 — Heather Anderson , Higgins, Hopkins, McLain & Roswell
Judge Paul King of the Douglas County District Court recently confirmed that subcontractors in residential construction owe an independent duty, separate and apart from any contractual duties, to act without negligence in the construction of a home in Colorado. See Order, dated September 7, 2010, Sunoo v. Hickory Homes, Inc. et al., Case No. 2007CV1866; see alsoCosmopolitan Homes, Inc. v. Weller, 663 P.2d 1041 (Colo. 1983); A.C. Excavating v. Yacht Club II Homeowners Ass’n, Inc., 114 P.3d 862 (Colo. 2005). He also verified that the holding in the B.R.W. Inc. v. Dufficy & Sons, Inc., 99 P.3d 66 (Colo. 2004)[1] case does not prohibit general contractors, such as Hickory Homes, from enforcing a subcontractor’s independent duty to act without negligence in the construction of a home.
Read the full story…
Reprinted courtesy of Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Anderson can be contacted at anderson@hhmrlaw.com
California Supreme Court to Examine Arbitration Provisions in Several Upcoming Cases
December 9, 2011 — CDJ Staff
Glen C. Hansen, writing on Abbott & Kinderman’s Land Use Law Blog looks at several cases pending before the California Supreme Court which ask if a developer can insist on arbitration of construction defect claims, based on provision in the CC&Rs. Currently, there is a split of opinions in the California appeals courts on the issue.
Four of the cases are in California’s Fourth Appellate District. In the earliest case, Villa Milano Homeowners Association v. Il Davorge, from 2000, the court concluded that the arbitration clause was sufficient to require that construction defect claims undergo arbitration. However, the Fourth Appellate District Court concluded in three later cases that the arbitration clauses did not allow the developer to compel arbitration. In two cases, argued in 2008 and 2010, the court concluded that to do otherwise would deprive the homeowners of their right to a jury trial. In the most recent case, Villa Vicenza Homeowners Association v. Nobel Court Development, the court decided that the CC&Rs did not create contractual rights for the developer.
The Second Appellate District Court came to a similar decision in Promenade at Playa Vista Homeowners Association v. Western Pacific Housing, Inc. In their decision, the court noted that CC&Rs could be enforced by homeowners and homeowners associations, but not developers.
Read the full story…
Harmon Towers Case to Last into 2014
December 20, 2012 — CDJ Staff
Don’t expect a fast resolution to the Harmon Tower case in Las Vegas. The latest schedule sets trial for the construction defect claims in January 2014. Previously, these claims were going to be heard during the trial set to start in June 2013. Now the June trial will be over payment issues only.
Don’t expect the building to come down soon either. While CityCenter claims the building could come down in an earthquake, Judge Elizabeth Gonzalez had determined that as the structural testing was not random; its results cannot be extrapolated through the entire structure. As a result, CityCenter has elected to do more testing, holding off on demolishing the building. They are appealing Gonzalez’s order to the Nevada Supreme Court.
Read the full story…