The Deadline to File Suit on a Public Works Payment Payment Bond is Triggered by a Claimant’s Work on a Project Not by a Claimant’s Work Under a Contract
June 02, 2026 —
Garret D. Murai - California Construction Law BlogCalifornia law requires that prime contractors furnish a payment bond – providing for payment to lower-tiered subcontractors and suppliers – on state and local public works projects with a value in excess of $25,000. There are three conditions that must be satisfied when a claimant makes a claim against a payment bond on a public works project in California:
- First, generally, the claimant must have served a preliminary notice, unless the claimant is a first-tier subcontractor or supplier;
- The claimant must have “ceased to provide work” on the project; and
- The claimant must file suit against the payment bond no later than six (6) months after the period in which a stop payment notice must be given or, in other words, the earlier of 270 days after completion of the public works project or 210 days after a notice of completion or cessation was recorded on a public works project.
In
Tarlton & Sons, Inc. v. Great American Insurance Company, 111 Cal.App.5th 376 (2025), the 2nd District Court of Appeal examined whether a subcontractor timely filed a claim against a payment bond when a prime contractor was terminated and replaced by another prime contractor who the subcontractor continued to perform work for.
Read the full story...Reprinted courtesy of
Garret D. Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Managing Rising Costs and Shifting Legal Risk for Florida High-Rise and Condominium Projects
May 05, 2026 —
Stephen Hauptman - Ball Janik LLPFlorida's construction defect landscape is experiencing a major shift. The convergence of material and labor cost volatility, regulatory tightening, and increasingly complex litigation strategies is forcing associations, developers, and their counsel to rethink how they approach risk management and dispute resolution. For those managing large-scale condo and high-rise projects, the stakes have never been higher.
The Cost Volatility Trap
Construction material prices rose at a "staggering" 12.6% annualized rate during the first two months of 2026, according to
recent industry analysis. Tariff impacts are projected to lead to more increases of 5.4% to 6.8%, depending on property type. For associations facing construction defect claims, this volatility creates a cascading problem: repair scopes defined two years ago are now dramatically underpriced, and damage calculations that appeared reasonable at discovery are obsolete by the time of settlement.
Courts and mediators are increasingly scrutinizing how cost estimates were developed and whether they account for existing market circumstances. Associations must now commission updated repair assessments more frequently, a practice that increases investigation costs but strengthens the credibility of damage claims. Conversely, defendants are weaponizing cost inflation as a defense, arguing that claimed damages are speculative or inflated. The practical result: repair sequencing and phasing strategies have become critical litigation tools. Associations that can demonstrate a rational, cost-effective repair plan tied to current market data are more favorably placed in settlement negotiations.
Regulatory Pressure and Deliberate Timing
Florida's 2026 condo compliance regime has significantly changed the defect claims landscape. Elevated transparency requirements, stricter reserve funding mandates, and tightened building safety inspection protocols mean that associations now face dual pressures: Comply with new regulations while simultaneously handling construction defect exposure.
This regulatory environment is changing investigation and documentation strategy. Associations that delay defect investigation to avoid triggering reserve funding obligations or disclosure requirements are taking on considerable legal risk. Recent case law such as the Third District Court of Appeal's reaffirmation of Chapter 558's pre-suit mediation requirements, underscores Florida's intent to resolve disputes early. Associations that move deliberately and record carefully during the pre-suit phase gain leverage in mediation and reduce the risk of expensive litigation.
Timing also intersects with repair sequencing. Associations must now balance the urgency of compliance inspections against the strategic advantage of phased repairs. Some associations are using compliance deadlines as a forcing mechanism to accelerate settlement discussions, while others are sequencing repairs to demonstrate good-faith remediation efforts before litigation commences.
The Emerging Risk Transfer Challenge
As construction defect claims grow more complex and costly, the traditional risk transfer systems, such as design-build warranties, contractor bonds, and insurance, are proving inadequate. Developers and general contractors are increasingly shifting risk to subcontractors and material suppliers, fragmenting liability and complicating recovery efforts for associations. Permitting and approval friction is also creating new litigation pressure points. Delays in municipal approvals, changes to building code interpretations, and disputes over remedial work compliance continue to spawn collateral claims that go beyond the original defect. Associations must now anticipate not only defect liability but also regulatory compliance disputes with municipalities, creating a dual-front legal challenge.
For large communities, this means reconsidering the entire risk architecture. Insurance carriers are tightening coverage, and traditional indemnification chains are breaking down. Forward-thinking associations are engaging counsel earlier in the development process to negotiate clearer risk allocation provisions and more robust insurance requirements.
Taking a Data-Driven Approach
Managing rising costs and shifting legal risk in Florida's high-rise and condo market requires a more sophisticated, data-driven approach. Associations must commission frequent cost updates, move deliberately through pre-suit investigation and mediation, and challenge traditional assumptions about risk transfer. Developers and their counsel should view regulatory compliance not as a burden but as an opportunity to demonstrate good-faith risk management and strengthen settlement positioning.
The firms and associations that succeed in 2026 will be those that treat cost volatility, regulatory change, and litigation strategy not as separate challenges but as linked elements of a coherent risk management framework.
Stephen Hauptman is special counsel in Ball Janik LLP’s Fort Lauderdale office. He may be reached at shauptman@balljanik.com.
Connecticut Expands Construction Wage-Theft Liability and Prevailing Wage Recordkeeping Requirements
June 29, 2026 —
Anand Gupta & Guest Contributor - Construction Law ZoneThis post was co-authored by Labor + Employment group lawyer Christopher Costain, Hayden Eckblom (Summer Intern), and Pasqualina Fox-Mina (Summer Associate). Hayden and Pasqualina are not admitted to practice law.
On May 11, 2026, Connecticut Governor Ned Lamont signed into law Public Act 26-12, a wide-ranging bill centered around employee rights. Our colleagues in Robinson+Cole’s Labor, Employment, Benefits + Immigration group recently published a
legal update summarizing the key components of Public Act 26-12. Here, we focus on the Wage Theft and Prevailing Wage concepts in the bill that directly relate to the construction industry.
Wage Theft
With exceptions for public works and small residential projects, general contractors will be jointly and severally liable for any unpaid wages owed to an employee of a subcontractor of any tier on private construction projects, beginning with contracts entered into on or after January 1, 2027. As we know, there is a separate regime for public works projects involving payment bonds.
Read the full story...Reprinted courtesy of
Anand Gupta, Robinson & Cole LLPMr. Gupta may be contacted at
agupta@rc.com
Bridging the Gap at Alaska’s Juneau Creek
September 21, 2026 —
Tim Newcomb - Engineering News-RecordThe largest single-span steel plate girder bridge launch in the nation wasn’t about setting records. Alaska’s Juneau Creek Bridge design was a matter of necessity. The fully erected steel plate girder bridge, featuring a 440-ft main span hovering 285 ft above the Juneau Creek, was part of the larger Sterling Highway project. It offered a logistical challenge but was chosen among over a dozen bridge types due to the unique constraints brought by the mountainous site.
Read the full story...Reprinted courtesy of
Tim Newcomb, Engineering News-RecordENR may be contacted at
enr@enr.com
21 Snell & Wilmer Attorneys Named Lawyers of the Year by Best Lawyers® for 2027
October 12, 2026 —
Snell & WilmerPHOENIX – Snell & Wilmer is pleased to announce that 21 of the firm’s attorneys, located across eight offices, have been named 2027 Lawyers of the Year by Best Lawyers®.
In conjunction with selection to the 2027 edition of The Best Lawyers in America® guide, the “Lawyer of the Year” recognition is awarded to individual lawyers with the highest overall peer-feedback for a specific practice area and geographic region. Only one lawyer is recognized for each practice area and location.
Read the full story...Reprinted courtesy of
Snell & Wilmer
Louisiana Legislature Enacts Act 932 – Significant Changes to Insurer Bad-Faith Exposure for Failure to Settle
July 13, 2026 —
Tabitha R. Durbin & Jennifer E. Michel - Lewis BrisboisThe Louisiana Legislature has enacted Act 932 (formerly House Bill 1162), which became law this week without the Governor's signature pursuant to the Louisiana Constitution, after expiration of the applicable constitutional review period. Act 932 makes several important amendments to Louisiana's insurer bad-faith statute and appears intended, at least in part, to address issues arising from the Louisiana Supreme Court's decision in Kelly v. State Farm Fire & Casualty Co., 169 So.3d 328 (La. 2015). The Act also makes changes regarding claim payments involving licensed contractors. The Act takes effect on August 1, 2026.
Key Takeaways
Act 932:
- Limits certain bad-faith causes of action (bad faith failure to settle) involving personal injury and bodily injury claims where good-faith disputes exist or where an insurer has not been afforded sufficient opportunity to respond to a settlement demand.
- Requires insurers and adjusters to verify a contractor's Louisiana license status before issuing claim payments when a contractor is named as a payee on a check for repair or restoration of immovable property.
- Creates a statutory safe harbor protecting insurers from bad-faith penalties and attorney fees when payment delays result from an inability to verify a contractor's license, provided specified documentation and notice requirements are met.
Reprinted courtesy of
Tabitha R. Durbin, Lewis Brisbois and
Jennifer E. Michel, Lewis Brisbois
Ms. Durbin may be contacted at Tabitha.Durbin@lewisbrisbois.com
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Read the full story...
Achieving Sustainability Through Design Build Delivery: Part II – A Framework for Managing Sustainability Objectives on Private Commercial Construction
October 06, 2026 —
Jennifer Harris, Tiffany Harrod & Joshua Pruett - ConsensusDocsPart I of this series traced the history and development of sustainability in construction and explained why design-build (“DB”) contracting is particularly well suited to achieve sustainability objectives. But selecting DB contracting does not by itself ensure a sustainable outcome. The parties must define their sustainability objectives with precision, establish measurable performance criteria and identify who will measure compliance with the criteria, and also draft contract terms that clearly and fairly allocate the associated responsibilities and risks. Otherwise, the completed project may fall short of its sustainability objectives and expose the parties to claims, disputes, and litigation. Part II offers a non-exhaustive list of practical guidance for addressing these issues and reducing those risks.
This article references the ConsensusDocs 310 Green Building Addendum, in conjunction with an agreement between the Owner and the Design-Builder (e.g., ConsensusDocs 415)
[1],
[2] and AIA Document E204–2017 Sustainable Projects Exhibit,
[3] together with AIA A141,
[4] as its contractual baseline. The five-part framework that follows is a roadmap for allocating sustainability risk between private owners and design-builders: define the requirements, identify hidden performance guarantees, map out the sustainable objective, address third-party certification risk, and track performance against agreed benchmarks.
Reprinted courtesy of
Jennifer Harris, Peckar & Abramson, P.C.,
Tiffany Harrod, Peckar & Abramson, P.C. and
Joshua Pruett, Peckar & Abramson, P.C.
Ms. Harris may be contacted at jharris@pecklaw.com
Ms. Harrod may be contacted at tharrod@pecklaw.com
Mr. Pruett may be contacted at jpruett@pecklaw.com
Read the full story...
'Drywall Isn't Light': Peter Lupo on Safety Management at Standard Drywall
May 26, 2026 —
Elaine Silver - Engineering News-RecordPeter Lupo has been safety director since 2019 at San Diego-based Standard Drywall Inc., a major wall and ceiling contractor. He draws on over two decades of safety experience across a wide range of commercial construction work, having previously served as safety director for general contractor T.B. Penick & Sons. He has also previously operated Peter Lupo Consulting, where he reviewed legal cases and provided expert testimony, and blogged on safety for ENR.com. Lupo recently spoke to ENR Correspondent Elaine Silver about the weight of drywall, heat hazard control, bilingual crews and how he supports safety creativity and learning on the Standard Drywall staff. The conversation has been edited.
Read the full story...Reprinted courtesy of
Elaine Silver, Engineering News-RecordENR may be contacted at
enr@enr.com