New Construction Laws, New Forms in California
July 10, 2012 — CDJ Staff
New construction laws came into effect in California on July 1. Writing for the Martindale-Hubble Legal Library, Glenn Mau, J. Michael McGuire, and John Tonsing, all of Archer Norris, discuss these changes. They note that the most important part of the changes to California construction law is that “all mechanics liens, stop notices and bond claims recorded after July 1, 2012 must use the new standardized forms and follow the new definitions, notice prerequisites and statutory release form language.”
Read the full story…
Harsh New Time Limits on Construction Defect Claims
April 26, 2011 — April 26, 2011 by Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq. of
Sullan2, Sandgrund, Smith & Perczak, P.C. in the
HindemanSanchez blogA recent Colorado Supreme Court decision, Smith v. Executive Custom Homes, Inc., 230 P.3d 1186 (Colo. 2010), considerably shortens the time limit for bringing many construction defect lawsuits. Homeowners and homeowner associations risk losing the right to seek reimbursement from builders, developers and other construction professionals unless they carefully and quickly act upon discovery of evidence of any potential construction defect.
The Statute of Limitations for Construction Defect Claims
Colorado’s construction defect statute of limitations limits the time for homeowners and homeowners associations to bring lawsuits for construction defects against “construction professionals,” including developers, general contractors, builders, engineers, architects, other design professionals, inspectors and subcontractors. The statute requires homeowners and associations to file suit within two years “after the claim for relief arises.” A claim for relief “arises” when a homeowner or association discovers or reasonably should have discovered the physical manifestation of a construction defect.
The two-year time limitation applies to each construction defect separately, and will begin to run upon the appearance of a “manifestation” of a construction defect (which may include, for example, a condition as simple as a roof leak or drywall cracks), even if the homeowner or association does not know the cause of the apparent problem.
The Smith Opinion and its Effect on the Statute of Limitations
In Smith v. Executive Custom Homes, Inc., the plaintiff homeowner, Mrs. Smith, slipped on ice that had accumulated on her sidewalk because of a leaking gutter and suffered injury. When she first noticed the leak, she reported it to her property manager, who reported it to the builder. The builder attempted to repair the gutter, unbeknownst to Mrs. Smith, and she did not notice further problems until approximately one year after she first observed the leak, when she fell and suffered serious injury. She sued the builder within two years of her injury, but nearly three years after she first learned of the leak.
The Colorado Supreme Court dismissed Mrs. Smith’s claims as untimely and held that under the construction defect statute of limitations, the two-year period for suing for injuries due to construction defects begins when the homeowner first observes the physical manifestation of the defect, even if the resulting injury has not yet occurred. The court acknowledged that this ruling could result in “unfair results,” especially if a serious and unforeseeable injury occurs more than two years after the first time the homeowner noticed the problem, and as a result the victim is unable to seek redress from those responsible for the defect.
Read the full story…
Reprinted courtesy of Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq. of Sullan2, Sandgrund, Smith & Perczak, P.C., and they can be contacted through their web site.
Rihanna Finds Construction Defects Hit a Sour Note
August 2, 2012 — CDJ Staff
The pop singer Rihanna is suing the former owners of her Beverley Hills home among others in a construction defect lawsuit. She contends that Adriana and Heather Rudomin concealed defects in the home that lead to water leaks and flooding during a 2010 storm. The Beverly Hills Patch noted that the dollar amount of the singer’s suit was not specified.
The most recent court ruling denied a motion from the owners to be dismissed from the lawsuit. They remain part of it, along Landmark Design Group, LLC, which renovated the home before the sale, and Prudential California Realty which sold the home.
Read the full story…
Architect Not Responsible for Injuries to Guests
September 1, 2011 — CDJ Staff
The Texas Court of Appeals has ruled, with one dissent, that the architectural firm that designed a home was not responsible to the injuries caused to guests when a balcony collapsed. Judge David Puryear wrote the majority opinion in Black + Vernooy Architects v. Smith.
Black + Vernooy designed a vacation home for Robert and Kathy Maxfield in 2000. The Maxfields hired a general contractor to build the home. The general contractor hired a subcontractor to build a balcony; however, the subcontractor did not follow the architect’s design in building the balcony.
A year after the house was completed; the Maxfields were visited by Lou Ann Smith and Karen Gravely. The balcony collapsed under the two women. Ms. Gravely suffered a broken finger, a crushed toe, and bruises. Ms. Smith was rendered a paraplegic as a result of the fall. They sued the Maxfields, the general contractor, and the architects for negligence. The Maxfields and the general contractor settled. A jury found that the architects held 10% of the responsibility. The architects appealed the judgment of the district court.
The Appeals Court reversed this judgment, noting that “there has been no allegation that the Architects negligently designed the balcony or that the Architects actually created the defects at issue.” Further, “the Smiths allege that the defect was caused by the construction practices of the contractor and subcontractor when the balcony was not built in accordance with the design plans of the Architects.”
The court found that even though the architects had a duty “to endeavor to guard against defects and deficiencies in the construction of the home and to generally ascertain whether the home was being built in compliance with the construction plans,” this duty did not extend to third parties.
Read the court’s decision…
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 — Douglas Reiser, Builders Cousel
Ever had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Yellow Brass Fittings Play a Crucial Role in Baker v Castle & Cooke Homes
May 10, 2012 — CDJ Staff
Baker v Castle & Cooke Homes Hawaii, et al. is a “class action filed by homeowners who allege that their homes have a construction defect. They allege that their plumbing systems include brass fittings susceptible to corrosion and likely to cause leaks. They bring this action against the developer of their homes and the manufacturers of the brass fittings.”
Zurn, the manufacturer of the allegedly defective brass fittings, sought a dismissal, or if that could not be achieved, then “a more definite statement, of five of the six claims.” Zurn moved for summary judgment on the sixth claim, or alternately sought “summary judgment on one of the five claims it” sought to dismiss.” The court granted in part the motion, and denied the motion for summary judgment.
The developer, Castle & Cooke, sought dismissal of the First Amended Complaint stating “that Plaintiffs have not complied with Hawaii’s Contractor Repair Act, chapter 672E of Hawaii Revised Statutes, which requires, among other things, a plaintiff to give a contractor the results of any testing done before filing an action against that contractor.” The court couldn’t determine “certain facts essential to ruling” on Castle & Cooke’s motion, and therefore denied the motion, but ordered Plaintiffs to submit requested material by the stated deadline.
The Baker v Castle & Cooke case began with the Plaintiffs claim that the use of yellow brass fittings can lead to construction defects. They allege that “yellow brass is particularly susceptible to dezincification, a corrosion process in which zinc leaches into potable water that comes into contact with the brass. According to Plaintiffs, as the brass corrodes, it becomes porous and mechanically weak. Plaintiffs further allege that the PEX systems in the putative class members’ homes have begun to, or are about to, leak water into the walls, ceilings, and floors of their homes. Plaintiffs allege that the leakage will cause water damage and mold growth, exposing the occupants to toxins.”
In response to the plaintiffs’ claims, Zurn argued “because their yellow brass fittings have not failed to date, Plaintiffs fail to allege, and have no evidence showing, that they have suffered any actual injury.” Plaintiffs replied, “even if the fittings have not failed as of today, failure in the future is inevitable.”
However, the court stated, “whether Plaintiffs have suffered any injury, or whether Plaintiffs are attempting to proceed based solely on future injury, implicates Plaintiffs’ standing to bring this action, as well as whether this case is ripe for adjudication.” The court has requested the parties to submit “supplemental briefing on whether this case should be dismissed pursuant to Rule 12(b)(1). In supplemental briefs, Zurn argues that dismissal is appropriate because Plaintiffs lack standing, and Castle & Cooke argues that dismissal is appropriate because Plaintiffs’ claims are not ripe.”
The court continues to discuss the problem of standing: “To establish standing, a plaintiff must demonstrate three things. First, the plaintiff must suffer an "injury-in-fact," which means that there must be a concrete and particularized "invasion of a legally protected interest" and the invasion is actual or imminent. Lujan v. Defenders of Wildlife, 504 U.S. 555, 560 (1992). Second, the injury must be fairly traceable to the challenged action. Third, a favorable decision must be likely to redress the injury. Id. It is the first element (injury-in-fact) that is in issue here.”
The court found that the plaintiffs do have standing: “Even if the court could not rely on the allegations that the pipes will soon leak, the court would conclude that, for standing purposes, Plaintiffs have a sufficient injury-in-fact in the form of their alleged economic loss.” In a hearing, Plaintiffs argued that their homes had decreased in value.
The court also denied Castle & Cooke’s motion to dismiss based on a lack of ripeness, stating “the same reasons Plaintiffs satisfy the injury-in-fact requirement for standing purposes, they satisfy the constitutional ripeness requirement.”
Plaintiffs asserted six counts against Zurn. Zurn, in response, made a motion to dismiss counts VIII, IX, X, XII, and XIII. The court granted Zurn’s motion for Counts VIII, IX, and X only: “Counts VIII (product liability), IX (negligence), and X (strict liability) sound in tort. Zurn argues that, because Plaintiffs allege no injury other than to the PEX systems and the yellow brass fittings themselves, the economic loss rule bars their tort claims. The court agrees.”
The court disagreed with Zurn’s motion regarding Count XII: “Count XII asserts that Zurn has breached the implied warranty of merchantability. Zurn argues that Count XII is barred by the applicable statute of limitations and that Plaintiffs do not sufficiently allege an injury. The court disagrees.”
Zurn’s motion regarding Count XIII was also denied: “Count XIII asserts that Zurn violated section 480-2 of Hawaii Revised Statutes.” Furthermore, “Plaintiffs allege that Zurn ‘engaged in unfair and deceptive acts or practices when [it] designed, manufactured and sold Yellow Brass Fittings.’ Zurn argues that Plaintiffs fail to state a claim under section 480-2(a) because their claims are barred by the statute of limitations and they do not adequately allege reliance or a cognizable injury. The court disagrees.”
The court denied the motion for summary judgment with respect to Counts XI and XII.
Castle & Cooke sought to dismiss “Plaintiffs’ claims against it under section 672E-2 of Hawaii Revised Statutes, which provides for dismissal when claimants fail to comply with chapter 672E.” There was some discussion regarding the test results. Apparently, the plaintiffs had failed to provide a written notice of claim at least 90 days before filing the action. However, it is unclear if the Plaintiffs have since complied with the requirements of the chapter. “The court has received no supplemental information from either party about whether any test results from another case have been turned over or whether those materials are subject to a confidentiality agreement. The record at this point does not establish noncompliance with the requirement in chapter 672E to provide such information. The court therefore denies the motion to dismiss.”
In summary, “Zurn’s motion to dismiss is granted as to Count VIII, Count IX, and Count X. Zurn’s motion to dismiss is denied with respect to Plaintiffs’ other claims. Zurn’s request for a more definite statement and its summary judgment motion are denied. Plaintiffs are given leave to file an amended Complaint no later than May 21, 2012.” Furthermore, “the court denies Castle & Cooke’s motion, but directs Plaintiffs to file, within two weeks, either a certificate of compliance with section 672E-3(c), or an explanation as to why they have not complied. Castle & Cooke may submit a response within two weeks of Plaintiffs’ submission. Each party’s submission is limited to 1000 words.”
Read the court’s decision…
Good Signs for Housing Market in 2013
December 20, 2012 — CDJ Staff
Dan Green, a loan officer at Waterstone Mortgage, is optimistic about the construction market in 2013. He notes that the rise in building permit, housing starts, and housing completions are all good signs. Mortgage rates are still low, making these new homes attractive to buyers.
Read the full story…
The Ever-Growing Thicket Of California Civil Code Section 2782
January 6, 2012 — Michael D. Worthing, Borton Petrini
California Civil Code section 2782 imposes limits on indemnity and defense provisions in construction contracts. Since the initial adoption of S.B. 8001 in 2002 (eff. January 1, 2003) section 27822 has been revised several times, and legislative history suggests that interest groups representing builders, developers and sub-contractors, as well as the insurance industry, have seen legislative action on these indemnity and defense issues as part of the overall response to the same economic pressures resulting from construction defect litigation that gave rise to S.B. 800. Amendments in 2005, 2007, 2008 and 2011 (each effective January 1 of the following year) have increasingly entangled the provisions of Section 2782 with various provisions of S.B. 800. The application of section 2782 to construction contracts, and in particular contracts between developer-builders and subcontractors, executed after January 1, 2006, will require a concurrent reading and understanding of S.B. 800, the application of which is itself still in flux.
The time a construction contract was executed will likely determine which version of section 2782, read in connection with provisions of S.B.800, is applicable. Because of the nature of construction defect litigation, the determination of relative rights and liabilities of developer-builders vis-à-vis subcontractors under construction contracts does not become the subject of litigation, and legal and judicial interpretation, until years after the contracts were entered and work performed. As of the date this article is submitted, there has been no case law interpreting or applying any of the post S.B. 800 amendments, in part, and perhaps primarily, because litigation arising from construction contracts executed after January 1, 2006, has not yet reached the appellate courts.
SECTION 2782 AT THE TIME S.B. 800 WAS ENACTED
Section 2782 was originally enacted in 1967 and amended several times to the version in effect when S.B. 800 became law, at which time the section was relatively simple and straightforward. It then consisted of two subdivisions, which have essentially remained unchanged until the most recent amendment during the 2011 legislative session.
Section 2782 (a) prohibited, and still prohibits, provisions in construction contracts that “purport to indemnify the promisee against liability for damages for death or bodily injury to persons, injury to property, or any other loss, damage or expense arising from the sole negligence or willful misconduct of the promise.” This provision essentially prohibits what had been referred to as so-called Type I or “specific” indemnity provisions. In such agreements, the indemnitor [the promisor, that is, the person or entity indemnifying] will indemnify the indemnitee [the promisee, that is, the person or entity being protected by the indemnity] for the indemnitee’s own negligence, whether active or passive, whether the indemnitee is solely negligent or concurrently negligent with the indemnitor. (See, MacDonald & Kruse, Inc. v. San Jose Steel Co. (1972) 29 Cal.App.3d 413, 419.)3 Section 2782 (a) has remained essentially intact since the enactment of S.B. 800. It still must be considered and applied to interpret a construction contract. Generally, it will apply to contracts not involving a public agency; the next part of section 2782 specifically governs such contracts.
The second subdivision prohibits provisions in any construction contract with a public agency which purport to impose on the contractor, or relieve the public agency from, liability for the active negligence of the public agency. Subdivision (b) has been revised by the 2011 amendment, discussed below. If a construction contract with the public agency is for residential construction, the standards of S.B. 800 likely apply.4
This was the extent of section 2782 on January 1, 2003, when S.B. 800 went into effect, and remained so until January 1, 2006. This version will govern interpretation and application of indemnity and defense provisions in construction contracts executed before January 1, 2006.5
2005 AMENDMENT
The first “post S.B. 800” change to Section 2782 was in enacted in 2005, effective January 1, 2006, and added two new sections. Subdivision (c) stated (in somewhat greater detail than paraphrased here) that for residential construction contracts, or amendments thereto, entered into after January 1, 2006, a subcontractor cannot be required to indemnify (including the cost to defend) a builder for construction defects that arise out of negligence or design defects of the builder or other independent contractors, or that do not arise out of the scope of the subcontractor=s scope of work. The term “residential construction” was defined by reference to S.B.800 generally, and the term “builder” was defined by reference to section 911 (a part of S.B. 800), for the first time expressly connecting provisions of section 2782 to S.B. 800. Contractual provisions not expressly prohibited were reserved to the agreement of the parties.
What subdivision (c) took away was partially given back by subdivision (d). It stated that “subdivision (c) does not prohibit a subcontractor and builder from mutually agreeing to the timing or immediacy of the defense and provisions for reimbursement of defense fees and costs, so long as that agreement, upon final resolution of the claims, does not waive or modify the provisions of subdivision (c).”6 In addition, it stated that this subdivision (c) did not affect the obligations of an insurance carrier under Presley Homes, Inc. v. American States Insurance Company (2001) 90 Cal.App.4th 571, which holds that where an insurer has a duty to defend a developer pursuant to an additional insured endorsement obtained under a subcontractor’s policy, that duty generally applies to the entire action, even if the suit involves both covered and uncovered claims, or a single claim only partially covered by the policy. Finally, subdivision (d) stated that the amendment did not affect the builder’s or subcontractor’s obligations under S.B. 800. Both of these latter provisions, relating to the Presley Homes case, and obligations under S.B. 800, have been carried forward essentially intact in subsequent amendments of section 2782.
This version of section 2782 will be applicable to any contract between a builder as defined by section 911 (see fn. 4, above) and a subcontractor executed between January 1, 2006, and December 31, 2008. Thus, a general contractor, etc., who is not a builder is not subject to the provisions added by the 2005 amendment; this changed with the next amendment.
It is not clear whether this version would apply to a contract entered before January 1, 2006, but amended after that date. Subdivision (c) applies to “all construction contracts, and amendments thereto, entered into after January 1, 2006, for residential construction.” It would seem that the clearest and most logical construction would apply it only to contracts originally made after January 1, 2006, and thereafter amended, but there has been no judicial determination of this issue.
In addition, logically it would seem that this version of section 2782 should be applicable to construction contracts for residential construction between a builder and a subcontractor, entered between January 1, 2006, and December 31, 2008; however, legislative history relating to the 2008 amendment discussed below suggests a different result might occur.
2007 AMENDMENT
The second “post S.B. 800” amendment in 2007 (effective January 1, 2008), added subdivisions (e)(1) and (e)(2).
Subdivision (e)(1) added general contractors and subcontractors not affiliated with the builder and imposed essentially the same restrictions on provisions to indemnify, including the cost to defend, them as had been imposed on the “builder” by the 2005 amendment. The amendment refers to section 911 (b), again part of S.B. 800, to define general contractors, etc., not affiliated with the builder.
Subdivision (e)(1) essentially repeated the provisions of subdivision (d) permitting agreement to the timing and immediacy of the defense, the reference to the Presley Homes case, and the general contractor’s or subcontractor’s obligations under S.B. 800.
It appears this amendment was an attempt to harmonize the new restrictions on indemnity and defense provisions with S.B. 800. The 2005 amendment, whether by oversight or intent, covered only builders and not general contractors, although both classes are subject to the provisions of S.B. 800; the 2007 amendment added non-builder-affiliated general contractors.
Again, logically, it would seem that this version of section 2782 should be applicable to construction contracts for residential construction between a general contractor or contractor not affiliated with a builder and a subcontractor, entered between January 1 and December 31, 2008; however, legislative history relating to the 2008 amendment discussed below suggests a different result might occur. The same potential uncertainty regarding applicability to a contract entered before January 1, 2008, but amended after that date, exists for this provision as for the prior amendment, discussed above.
2008 AMENDMENT
The third “post S.B. 800” amendment in 2008 (effective January 1, 2009), reorganized the language relating to prohibited indemnity provisions, added a reference to insurance in that same prohibition, extensively rewrote the provisions governing agreements relating to the timing or immediacy of defense, added language preserving equitable indemnity claims, and added language defining “construction defect” by reference to the standards set forth in S.B. 800.
Subdivisions (a) and (b) remained unchanged.
Subdivision (c) now made a combined reference to builders (again by reference to section 911), as well as general contractors or contractors not affiliated with the builder (again by reference to section 911 (b)), rather than dealing with the two groups in separate but nearly identical subdivisions as previously. It otherwise restated the same limitations that were previously set forth separately in subdivisions (c) and (e), as well as the reference to the Presley Homes case, and the general contractor’s or subcontractor’s obligations under S.B. 800, but with one important addition. The word “insure” was added to the description of prohibited provisions, to-wit: “provisions? that purport to insure or indemnify, including the cost to defend, the builder, [etc.]? are unenforceable” to the extent they arise out of claims of the type previously described.
It is unclear what impact the addition of this single word “insure” will have; and, it will have to be read in light of the preservation of the language that it shall not affect the obligations of an insurance carrier under the holding of the Presley Homes case. Suppose a carrier had issued an additional insured endorsement under which it would otherwise be required to defend a builder or general contractor consistent with the Presley Homes rule: would this newly added single word (restricting the construction contract, to which the carrier is not a party) give the carrier a basis for denying coverage under the insurance contract? Or would the continued inclusion of the express language that it does not affect the obligations of an insurance carrier under Presley Homes control? That is surely an issue that will have to be worked out by the courts.
The new subdivision (d) addressed defense obligations. Again it permitted parties to agree to the timing and immediacy of the defense and provision for reimbursement of defense fees and costs, but imposed a very detailed scheme that appears to limit the extent of such agreement. A subcontractor owes no defense or indemnity obligation until the builder or general contractor provides a written tender of the claim, which has the same force and effect as notice of commencement of a legal proceeding. Upon that tender the subcontractor shall elect to follow one of two ways of performing: subdivision (d) (1) permits the subcontractor to defend with counsel of its choice and to control the defense, if the subcontractor gives written notice of this election within a reasonable time after receipt of the written tender and in no event later than 90 days following that receipt; subdivision (d) (2) provides an alternative by which the subcontractor pays a reasonable allocated share of the builder’s or general contractor’s defense fees and costs within 30 days of receipt of an invoice, subject to reallocation upon final resolution of the claim by settlement or judgment. Subdivision (e) sets forth remedies available to the builder or general contractor if a subcontractor fails to timely and adequately perform its obligations under either of the two alternatives in subdivision (d), including compensatory and consequential damages, reasonable attorneys’ fees in connection with the first alternative, and interest on defense and indemnity costs in connection with the second alternative. Subdivision (e) ends with provisions relating to reallocation of defense costs, and damages for failure to reallocate.
Application of these requirements in actual litigation is likely to be cumbersome and potentially fraught with conflicts. If retained pursuant to subdivision (d) (1) does the attorney represent the builder, the subcontractor, or both? To whom does the attorney owe his or her fiduciary duty? Can an appropriate informed written consent be formulated, for example, under Rule 3-310 of the California Rules of Professional Conduct, or Rule 1.7, ABA Model Rules of Professional Conduct? Could an attorney retained by a subcontractor blame the subcontractor if that is in the developer’s best interests? If multiple subcontractors elect to defend directly, how would the defense be coordinated among the potentially multiple attorneys so retained? Would an attorney retained by one subcontractor be able, or inclined, to blame another subcontractor who also chose to defend directly, in other words, what would prevent inconsistent defense positions amongst the various counsel retained by subcontractors for the developer? There may be solutions to such practical and professional considerations but it seems an ethical thicket awaits any attorney involved in such circumstances.
Subdivision (e) and (f) preserve equitable indemnity claims for the builder, general contractor or subcontractor, the first in general, the second as against any supplier, design profession, or product manufacturer. Finally, the 2008 amendment added for the first time, in subdivision (h), language defining "construction defect" as used in section 2782 as a violation of standards set forth in S.B. 800.
The inclusion of these last three subsections would seem to work against simplification of litigation. A builder or general contractor is likely to allege a claim for equitable indemnity against any and all subcontractors in addition to claims for contractual indemnity and defense (however limited by the other provisions of section 2782). Nothing in the section suggests the subcontractor should, or even can, somehow take on the representation of the builder, etc., in connection with a claim of equitable indemnity back against the subcontractor.
And the limited definition of “construction defect” in subdivision (h) appears to raise an issue of the applicability of the limitations set forth in subdivision (c). Although there is a school of thought that section 941 limits residential construction defect claims only to breach of the performance standards under S.B. 800, it is still common for CD complaints to plead other legal theories, e.g., breach of contract, breach of warranty, negligence, etc., in addition to violation of S.B. 800 standards. With the addition of subdivision (h) it is arguable that the restrictions on indemnity and defense provisions spelled out in subdivisions (c) and (d), both of which relate to claims for residential construction defects, are applicable only to claims for violation of S.B. 800 standards, and not other residential construction defect claims. In other words, a developer might conceivably still be entitled to a broader scope of indemnity and concomitant defense for other types of claims, such as breach of contract, breach of warranty, negligence, etc., so long as the indemnity does not violate the limitation of subdivision (a) against Type I indemnity, which as noted above, has remained intact through these revisions.
Finally, it would seem that this version of section 2782 should be applicable to contracts executed between builders, general contractors, etc., on the one hand and subcontractors on the other hand on and after January 1, 2009. And, as noted above in connection with the 2005 and 2007 amendments, logic would suggest that those versions would ordinarily apply to contracts executed during the time periods mentioned above. But, the Legislative Counsel’s Digest for the 2008 amendment as it finally was enacted into law includes the following statements:
This bill would delete the provisions applicable to construction contracts entered into on or after January 1, 2008, that purport to indemnify the general contractor or contractor not affiliated with the builder. The bill would revise the provisions applicable to contracts entered into after January 1, 2006, to instead apply to contracts entered into after January 1, 2009, and to apply to agreements that purport to insure or indemnify the builder or the general contractor or contractor not affiliated with the builder, as described.
Although it seems a startling result, this legislative history suggests an argument can be made that the 2008 amendment retroactively nullified the effect of the 2005 and 2007 amendments, so that contracts executed from January 1, 2006, as to builders or January 1, 2008, for general contractors, etc., through December 31, 2008, are still governed by the provisions of section 2782 as it was on the books prior to the first post-S.B. 800 amendment in 2005.
2011 AMENDMENT
Section 2782 has been amended yet again in the 2011 session of the California Legislature, effective January 1, 2012; however, the substantive changes affect certain contracts entered on or after January 1, 2013. All of the provisions contained in the 2008 amendment have been carried forward in the most recent amendment, although re-numbered: (c) became (d), etc., through (h) becoming (i). So, the law governing construction contracts entered into after January 1, 2009, for residential construction, as between a builder, or a general contractor, etc., not affiliated with a builder, and regarding insurance, indemnity or defense relating to claims for construction defects, remains the same as in the 2008 amendment.
As noted above the substantive changes to section 2782 all affect contracts entered into on or after January 1, 2013. Subdivision (b) has been amended such that any provision in a contract with a public agency that purports to impose on any contractor, etc., or relieve the public agency from, liability for the active negligence of the public agency will be void and unenforceable. A new subdivision (c) has been added that imposes a similar restriction on construction contracts with the owner of privately owned real property to be improved and as to which the owner is not acting as a contractor or supplier of materials or equipment to the work. This new restriction in subdivision (c) does not apply to a homeowner performing a home improvement project on his or her own single family dwelling.
The 2011 bill amending section 2782 also added a new section 2782.05, which will make void and unenforceable any provision in any construction contract (again, entered on or after January 1, 2013) that purports to insure or indemnify, including the cost to defend, a general contractor, construction manager, or other subcontractor, by a subcontractor for claims that arise out of the active negligence or willful misconduct of the general contractor, etc., or other independent contractors, etc., or to the extent the claims do not arise out of the scope of work of the subcontractor. However, the section also includes a long list of situations to which it does not apply, including all of those covered by section 2782 (residential construction subject to S.B. 800, public agency contracts subject to section 2782 (b), and direct contracts with private property owners subject to the new section 2782 (c)) as well as eight other categories. This apparently is intended to serve as a “catch-all” to extend a limitation on indemnity agreements to all construction contracts not previously swept into this widening legislative scheme, although the exact phrasing is slightly different.7
The new section 2782.05 then permits a mutual agreement to the timing or immediacy of a defense under a scheme essentially identical to that imposed in the 2008 amendment to section 2782: defend with counsel of choice, and maintain control of the defense; or, pay a reasonable allocated share of defense fees and costs. The same logistical and ethical difficulties presented by the 2008 scheme discussed above would likely be present in cases that fall under the new section 2782.05.
CONCLUSION
The California Legislature has been revising section 2782 since shortly after the adoption of S.B. 800. Each revision has been more complicated than the last, and each has tied certain provisions of section 2782 more closely to S.B. 800. In particular, with regard to construction defect claims relating to residential dwellings which are subject to S.B. 800, the Legislature has apparently attempted to exercise more and more control over the scope of allowable indemnity and dictated a very narrow scheme to govern how the defense obligation arising from a contractual indemnity is to be implemented. It seems likely that any attempt to manage the defense of a construction defect case under the options that allow a subcontractor to defend directly and control the defense will create a logistical problem and an ethical difficulty for any attorney attempting to defend a developer at the behest and direction of a subcontractor. Finally, as set forth in the current version of section 2782 relating to contractual indemnity and defense of S.B. 800 type cases (subdivisions (c) through (h) in the 2008 version, now subdivisions (d) through (i) in the 2011 amendment), the Legislature has apparently narrowed the application to only claims of violation of S.B. 800 standards. This may have, in essence, removed the restrictions on indemnity and defense provisions as they relate to other theories pleaded against developers in construction defense cases, e.g., breach of contract, breach of warranty, negligence, and the like. It is not at all clear that the Legislature has accomplished what it set out do accomplish. Rather, the law may have come full circle back to where it began, except for one legal theory, i.e. violation of S.B. 800 standards, currently being used in residential construction defect cases. For any other legal theory the limitation of section 2782 (a) may be solely controlling.
- California Civil Code section 43.99, and sections 895 to 945.5.
- All statutory references in this article are to the California Civil Code unless otherwise specified.
- Type I or specific indemnity does not exactly match the scope of proscribed indemnity as described in section 2782 (a) but it is the closest. More recent case law in California has eschewed a mechanical application of the MacDonald & Kruse typology in favor of examining the precise text of the actual contract (See, e.g., St. Paul Mercury Ins. Co. v. Frontier Pacific Ins. Co. (2003) 111 Cal.App.4th 1234, 1246, n. 6) but some recent cases still use the Type I, II and II classifications. And, an understanding of that “historical” typology is useful as an aid to evaluating and understanding express indemnity in general.
- The provisions of S.B. 800 other than the prelitigation procedures of sections 910 through 938 apply to general contractors, subcontractors, etc., pursuant to section 936. The prelitigation procedures generally involve a “builder,” which is specifically defined in section 911 (a) by reference to entities or individuals in the business of selling residential units to the public or of building, developing, or constructing residential units for public purchase. Pursuant to section 911 (b) the term builder does not include general contractors, etc., not affiliated with the builder. Thus, a general contractor who constructs residential housing pursuant to a contract with a public agency is still subject to claims for violation of the standards set forth in sections 896 and 897, resulting from its negligent act or omission or breach of contract, pursuant to section 936.
- As noted above, there has been no case law yet interpreting any of the “post S.B. 800” changes to Section 2782. One of the most important legal decisions relating to express indemnity and defense obligations and rights between developer-builders and sub-contractors was published after two of the amendments but based upon contracts executed and the language of section 2782 prior to January 1, 2006. (See, Crawford v. Weather Shield Mfg., Inc. (2008) 44 Cal.4th 541, 547, 566-67, fn. 14).
- Subcontractor dissatisfaction with the perceived inadequacy of protection afforded by this provision apparently became the impetus for a 2008 amendment to section 2782, discussed below, at least based upon the numerous (form) letters submitted to legislators in connection therewith.
- Section 2782 (a), where we started, and which has continued without change, prohibits indemnity for claims arising out of the sole negligence or willful misconduct of the promisee; sole negligence can be either active or passive. The various versions relating to residential construction prohibit indemnity for the negligence of the builder, etc., suggesting there is no express contractual indemnity for the negligence of the subcontractor if the builder, etc., is at all negligent. This is tempered a bit by the preservation of the right to equitable indemnity, which will now be found in section 2782 (g) and (h).
Courtesy of Michael D. Worthing of Borton Petrini, LLP. Mr. Worthing can be contacted at mworthing@bortonpetrini.com.
Florida Law: Defects in Infrastructure Improvements Not Covered in Home Construction Warranties
July 10, 2012 — CDJ Staff
In April 2012, Governor Rick Scott signed into law House Bill 1013, despite lobbying from homeowner and condominium associations among others. The law was in response to a case in which the court had found that implied warranties covered external subdivision improvements. Prior to the court decision, these were not thought to be covered.
According to an article in the Martindale-Hubble Legal Library, under the new law, road and drainage improvements will not be included implied warranty of a new home. The law took effect on July 1.
Read the full story…
Another Las Vegas Tower at the Center of Construction Defect Claims
November 7, 2012 — CDJ Staff
Accusations are coming from both sides over construction defects at a Las Vegas tower, only this time, it’s not the Harmon Towers, it’s Hilton Grand Vacations, which is part of the Planet Hollywood Resort. The project was originally dubbed PH Towers Westgate, and it was developed by Westgate Resorts, which is suing the contractor, Tutor-Saliba for $10 million over late completion and construction defects.
Among the defects Westgate is claiming are cracked floor tiles in the valet lobby and cracks and delamination of the pool deck. Tutor-Saliba argues that the failure of the valet lobby floor is due to Westgate specifying only 1/16th inch-wide grouting, instead of the specified ¬º inch, and Westgate’s refusal to allow expansion joints on the pool deck has lead to problems there. Westgate’s attorney, Robert Schumacher, attributes the problems to “shoddy construction practices.”
According to the article in the Las Vegas Review Journal, plans were only 60 percent complete when construction began, leading to “thousands of change orders.” Despite not meeting an August completion deadline, Tutor-Saliba is claiming it is owed a $1.5 million bonus nevertheless.
Read the full story…
Although Property Damage Arises From An Occurrence, Coverage Barred By Business Risk Exclusions
July 8, 2011 — Tred R. Eyerly, Insurance Law Hawaii
The homeowners hired the insured to raise the structure of their home twenty-four inches above the flood zone. Lafayette Ins. Co. v. Peerboom, 2011 U.S. Dist. LEXIS 58985 (S.D. Miss. June 2, 2011). When the insured’s crew returned from lunch one day, they found the house had fallen from hydraulic jacks being used to raise the structure a few inches at a time. There was substantial damage to the entire structure.
The homeowners sued, asserting several claims, including negligence and breach of contract. The complaint alleged the homeowners entered a contract with the insured to raise their structure while maintaining its integrity. However, the insured failed to use proper equipment, which caused the house to fall and be completely destroyed.
The insured tendered the claim to its insurer, Lafayette Insurance Company. Lafayette defended under a reservation of rights and filed suit for a declaratory judgment. Lafayette’s subsequent motion for summary judgment contended there was no “occurrence” alleged in the underlying complaint and, even if there was, the business risk exclusions barred coverage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Crane Dangles and So Do Insurance Questions
November 7, 2012 — CDJ Staff
Hurricane Sandy sent a construction crane dangling from the top of One57, a condo construction project in New York City. In response to the risk, the nearby Parker Meridian and other nearby buildings were evacuated until the crane could be stabilized. Businessweek reports that One57 involves “a tangle of companies,” including the developer, Extell Development and the contractor, Lend Lease Construction. Pinnacle Industries was responsible for providing and operating the crane.
The insurance claims are yet to be made, but they will likely include the costs of evacuating nearby buildings and to cover any damage to the building itself. David DeLaRue, a vice president in construction practice at Willis Group Holdings said there would be two questions: “Did our insured do anything to cause that loss? Does this policy cover it?”
Read the full story…
Texas Court of Appeals Conditionally Grant Petition for Writ of Mandamus to Anderson
April 25, 2011 — April 25, 2011 Beverley BevenFlorez - Construction Defect Journal
The Texas Court of Appeals conditionally grant mandamus relief to Anderson Construction Company and Ronnie Anderson (collectively “Anderson”)… from the trial court in a construction defect lawsuit filed by Brent L. Mainwaring and Tatayana Mainwaring. See Tex. Prop. Code Ann. 27.001-.007 (West 2000 & Supp. 2010). Relators contend the trial court abused its discretion by compelling discovery while the case was abated by operation of law.
The Court of Appeals opinion describes what led up to the proceedings: “The Mainwarings’ original petition identified certain defects in their Anderson-constructed home. Those defects concerned the roof trusses and framing, air conditioning, mortar and masonry, exterior doors and windows, and weep holes. With respect to the five areas of defects identified in their original petition, the Mainwarings gave Anderson the statutorily required notice on January 13, 2010. After implementing agreed extensions, Anderson made an offer of settlement for the defects the Mainwarings identified in their notice. Almost eight months later, the Mainwarings filed an amended petition adding defects they had not included in their original petition and notice. The additional defects the Mainwarings included in their amended petition had not been addressed by Anderson’s offer of settlement.”
Following these events, Anderson claimed the Mainwarings did not respond in writing to their settlement offer. “Anderson filed a verified plea in abatement on December 2, 2010. In the trial court, Anderson claimed that the Mainwarings failed to respond in writing to Anderson’s settlement offer, as required by Section 27.004(b) of the RCLA. See Tex. Prop. Code Ann. 27.004(b)(1). The Mainwarings moved to compel discovery responses from Anderson. The Mainwarings alleged that they rejected Anderson’s settlement offer, and that if their response was insufficient, they contend that Anderson’s offer was rejected by operation of law on the twenty-fifth day after the Mainwarings received it. See Tex. Prop. Code Ann. 27.004(i). The Mainwarings’ motion to compel was not supported by affidavit. See Tex. Prop. Code Ann. 27.004(d)(2). On January 13, 2011, Anderson filed a verified supplemental plea in abatement. Anderson alleged that the Mainwarings failed to provide written notice concerning the newly alleged defects and complained the Mainwarings were attempting to circumvent the inspection and resolution procedure of the RCLA. Over Anderson’s objection that the lawsuit had been abated, the trial court granted the Mainwarings’ motion to compel discovery.”
After listening to both sides, the Court of Appeals offered this reasoning for their opinion: “The parties do not dispute that Anderson inspected the property before the Mainwarings alleged the existence of additional defects in their amended pleading, nor do the Mainwarings claim that Anderson has been given an opportunity to inspect the additional defects the Mainwarings identified in their amended pleadings. We conclude the trial court did not have the discretion to deny or lift the abatement until the Mainwarings established their compliance with the statute. In other words, the Mainwarings are required to provide Anderson a reasonable opportunity to inspect the additional defects identified by their amended pleading, which will allow Anderson the opportunity to cure or settle with respect to the newly identified defects.”
The Court of Appeals spoke directly on the issue of mandamus relief: “The Mainwarings contend that mandamus relief is not available because the trial court’s ruling does not prevent Anderson from making settlement offers during the discovery process. ‘An appellate remedy is “adequate” when any benefits to mandamus review are outweighed by the detriments.’ In re Prudential Ins. Co. of Am., 148 S.W.3d 124, 136 (Tex. 2004). The failure to abate a case is typically not subject to mandamus. See In re Allstate Cnty. Mut. Ins. Co., 85 S.W.3d 193, 196 (Tex. 2002) (citing Abor v. Black, 695 S.W.2d 564, 567 (Tex. 1985)). In this case, however, the case was abated by operation of law. By ignoring the statutory abatement, the trial court interfered with the statutory procedure for developing and resolving construction defect claims. See In re Kimball Hill Homes Tex., Inc., 969 S.W.2d 522, 525 (Tex. App. Houston [14th Dist.] 1998, orig. proceeding) (An appeal provides an inadequate remedy for the trial court’s failure to observe automatic abatement pursuant to the RCLA.). The benefits of mandamus review are not outweighed by the detriments of mandamus review in this case.“
In conclusion, “The trial court had no discretion to compel discovery while the case was abated, and Anderson, who has been compelled to respond to discovery during a period the case was under an automatic abatement, has no adequate remedy on appeal. Accordingly, we conditionally grant the petition for writ of mandamus. The writ will issue only if the trial court fails to vacate its order of February 3, 2011, and fails to refrain from proceeding with the case until a motion to reinstate is filed that establishes compliance with the notice and inspection requirements of the Residential Construction Liability Act.”
Read the trial court’s decision…
Insurer’s Discovery Requests Ruled to be Overbroad in Construction Defect Suit
October 28, 2011 — CDJ Staff
The US District Court has ruled in the case of D.R. Horton Los Angeles Holding Co. Inc. v. American Safety Indemnity, Co. D.R. Horton was involved in a real estate development project. Its subcontractor, Ebensteiner Co., was insured by ASIC and named D.R. Horton as an additional insured and third-party beneficiary. D.R. Horton, in response to legal complaints and cross-complaints, filed for coverage from ASIC under the Ebensteiner policy. This was refused by ASIC. ASIC claimed that “there is no potential coverage for Ebensteiner as a Named Insurer and/or D.R. Horton as an Additional Insured.” They stated that “the requirements for coverage are not satisfied.”
The case same to trial with the deadline for discovery set at March 1, 2011. ASIC stated they were seeking the developer’s “job file” for the Canyon Gate project. D.R. Horton claimed that ASIC’s discovery request was overbroad and that it would be “unduly burdensome for it to produce all documents responsive to the overbroad requests.”
D.R. Horton did agree to produce several categories of documents, which included:
“(1) final building inspection sign-offs for the homes that are the subject of the underlying litigation;(2) an updated homeowner matrix for the underlying actions; (3) the concrete subcontractor files; (4) the daily field logs for D.R. Horton’s on-site employee during Ebensteiner’s work; (5) documents relating to concrete work, including documents for concrete suppliers; (6) documents relating to compacting testing; (7) documents relating to grading; and (8) D.R. Horton’s request for proposal for grading”
The court found that the requests from ASIC were overbroad, noting that the language of the ASIC Request for Production of Documents (RFP) 3-5 would include “subcontractor files for plumbing, electric, flooring, etc. - none of these being at issue in the case.” The court denied the ASIC’s motion to compel further documents.
The court also found fault with ASIC’s RFPs 6 and 7. Here, D.R. Horton claimed the language was written so broadly it would require the production of sales information and, again, subcontractors not relevant to the case.
Further, the court found that RFPs 8, 10, 11, and 13 were also overbroad. RFP 8 covered all subcontractors. D.R. Horton replied that they had earlier complied with the documents covered in RFPs 10 and 11. The court concurred. RFP 13 was denied as it went beyond the scope of admissible evidence, even including attorney-client communication.
The court denied all of ASIC’s attempts to compel further discovery.
Read the court’s decision…
2011 Worst Year Ever for Home Sales
September 9, 2011 — CDJ Staff
So few new single-family homes have sold in 2011 that expectations are that this will be the worst year for new homes sales since the Commerce Department started tracking this in 1963. The Harford Courant notes that previously builders created a new supply to which was added homes under foreclosure.
Ed Leamer, economist and director of UCLA’s Anderson Forecast, says that recovery would be driven by two sectors, manufacturing and construction. “It doesn’t look like there is going to be a big recovery in manufacturing,” he says. “It is going to have to come in housing.”
The soft housing market, however, is leading to a loss of construction jobs, as reported by the Associated General Contractors of America. As a result, stock prices for the twelve largest publicly-traded home builders have declined 22.7 percent in a market that has declined 4.2 percent overall.
Read the full story…
US Courts in Nevada Busy with Yellow Brass
August 2, 2012 — CDJ Staff
Judge Robert C. Jones, the chief judge of the United States District Court of Nevada, and Judge Peggy A. Leen, a magistrate judge with the same court, have issued orders in cases involving allegations of high-zinc yellow brass plumbing components. Judge Jones issued orders on Waterfall Homeowners Association v. Viega, Inc. and Greystone Nevada, LLC v. Anthem Highlands Community Association on July 9, 2012. Judge Leen issued orders on Southern Terrace Homeowners Association v. Viega, Inc. on July 10, and The Seasons Homeowners Association, Inc. v. Richmond American Homes of Nevada, Inc. on July 19.
Chief Judge Jones held an omnibus hearing on Waterfall v. Viega on June 12. During that hearing “Chief Judge Jones had already agreed that the claims against the product manufacturers should be be severed from the majority of the other claims and that discovery should proceed on different tracks.” Judge Leen ordered that the Southern Terrace claims be referred to Chief Judge Jones to determine if it should be consolidated with other yellow brass cases.
Chief Judge Jones’s decision in Greystone Nevada rests on issues of whether the affected homeowners had signed arbitration agreements. The judge found that the “Defendant’s claims that the seven homeowners they have identified are subsequent purchasers who need not arbitrate with Greystone is definitively refuted by the evidence.”
Judge Leen cites the Greystone decision in her ruling on Seasons Homeowners Association v. Richmond American Homes of Nevada. Richmond seeks to compel individual arbitration, stating that “the arbitration clause used singular rather than plural terms, and therefore, class arbitration was foreclosed.” Judge Leen determined that “under Nevada law, a homeowners association has statutory authority to represent homeowners associations in these types of actions. She did, however, accept Richmond’s argument that they could compel arbitration.
The Waterfall order involves an attempt by two homeowners associations to seek a class action against seventeen defendants, the first twelve of whom are described as “the Viega Defendants” and “the Uponor Defendants.” Chief Judge Jones notes that “many of these Defendants have been sued in identical class actions by the same law firms, but with different named defendants.” The homeowner association seek to “represent their own 998 members directly but also wish to represent up to 10,000 homeowner associations representing up to 250,000 similarly situated homeowner members throughout the Las Vega area via this class action.”
The judge has denied the Viega Defendants’ attempt to deny class certification, noting that the plaintiffs “argue that they intend to argue for class certification under Rule 23(b)(3). He also denied the motions by the two groups of the Viega Defendants. The U.S. Viega Defendants sought to be dismissed from the case for a variety of reasons. The judge noted of the claim that the plaintiffs had no injury of fact and are not alleging actual damage is contradicted by the allegations of actual damage made by the plaintiffs. ”They have alleged that the parts are defective and have already begun to corrode in at least a few sample circumstances, even if they have not yet failed.” To the argument that there re not particular claims made against defendants, the judge notes, “it is clear from the Complaint which Defendants are alleged to have manufactured and sold which brands of allegedly defective products, and which Defendants are alleged to have installed them.”
The German Viega firms also sought to be dismissed from the suit, noting that “they have no property, employees, accounts, advertisements, etc. in Nevada and have not sold any products in Nevada.” However, the judge notes that “at least Waterfall, and perhaps Red Bluff, was still under construction when Viega, Inc. became the sole shareholder of Vanguard Industries, Inc.”
Finally, both of Chief Judge Jones’s rulings cite a related case in the U.S. District Court for the District of Minnesota involving a class action settlement for those with F1807 systems. He notes in both these cases that “Plaintiffs disclaimed any claims based upon F1807 components.”
Read the courts' decisions…
Waterfall Homeowners Association v. Viega, Inc.
Greystone Nevada, LLC v. Anthem Highlands Community Association
Southern Terrace Homeowners Association v. Viega, Inc.
The Seasons Homeowners Association, Inc. v. Richmond American Homes of Nevada, Inc.
AFL-CIO Joins in $10 Billion Infrastructure Plan
June 30, 2011 — CDJ Staff
The AFL-CIO has announced plans to generate up to $10 billion in funding for infrastructure development, training construction workers, and making buildings more energy efficient, pledging $20 million to retrofit buildings. Bloomberg News reports that union officials made the announcement in Chicago at the Clinton Global Initiative, releasing a statement from Richard Trumka, president of the union, “we, at the AFL-CIO, believe that together, with our partners in business and government, we can profitably invest significant resources to make America more competitive and energy efficient.” A foot injury prevented Mr. Trumka from attending the event.
The statement also quoted Mark Ayers, president of the Building and Construction Trades Department of the AFL-CIO, “the time is now to become intensely focused on the creation of jobs.”
Read the full story…
Background Owner of Property Cannot Be Compelled to Arbitrate Construction Defects
November 7, 2012 — CDJ Staff
In Truppi v. Pasco Engineering, John Quattro sued Property Management Contractors, Inc. over construction defects in William Truppi’s home. All parties are named in the suit. The California Court of Appeals ruled that Property Management Contractors, Inc. (PMCI) could not compel Mr. Quattro to arbitration.
The background of the case involves two houses built in Encinitas, California by PCMI: one for Mr. Truppi at 560 Neptune, and one for Mr. Quattro at 566 Neptune. Both contracts contained an arbitration provision. Mr. Quattro signed the contract for his residence and Mr. Truppi signed the other. Mr. Quattro then sued PCMI and its principal, William Gregory. Mr. Quattro claimed to be the true contracting party for the 560 Neptune residence and a third party beneficiary of the contract Mr. Truppi signed, and stated that PCMI was aware of this.
PCMI in a demurrer stated that Quattro “had only a ‘prospective beneficial interest in the property upon its eventual sale or lease.’” Mr. Quattro amended his complaint to account for the issues raised by PCMI. The court rejected PCMI’s demurrer to the amended complaint.
Finally, PCMI and Gregory asserted that Quattro was “not the real party in interest” and could not sue. PCMI continues to assert that Quattro lacks standing, but their attorney sent Quattro an e-mail stating, “While my client disputes that you are a party, and that you lack standing to assert the claim, to the extent you do so I believe you are obligated to proceed by way of arbitration.”
The court did not cover the issue of Quattro’s standing in the case, only if he could be compelled to arbitration. The court affirmed the lower court’s finding that Quattro could not be compelled to arbitrate the construction defect claim as neither he nor Gregory signed the contract in an individual capacity. Further, the court noted that PCMI and Gregory “denied the existence of an agreement between themselves and Quattro on the 560 contract,” and cannot compel arbitration on a non-existent agreement. And while non-signatories can, in some situations be compelled to arbitrate, the court found that “these cases are inapplicable because here they seek to have the alleged third party beneficiary (Quattro) compelled by a nonsignatory (Gregory).” The arbitration clause in question “expressly limited its application to persons or entities that signed the 560 contract.”
As Mr. Quattro was not a signatory to that agreement, the court found that he could not be held to its arbitration provision.
Read the court’s decision…