A Downside of Associational Standing - HOA's Claims Against Subcontractors Barred by Statute of Limitations
March 28, 2012 — Bret Cogdill, Colorado Construction Litigation
In multi-family construction defect litigation in Colorado, homeowners associations rely on associational standing to pursue claims affecting more than two units and to bring claims covering an entire development. This practice broadens an association’s case beyond what individual, aggrieved owners would otherwise bring on their own against a developer or builder-vendor. However, reliance on associational standing to combine homeowners’ defect claims into a single lawsuit has its drawbacks to homeowners.
A recent order in the case Villa Mirage Condominium Owners’ Association, Inc., v. Stetson 162, LLC, et al., in El Paso County District Court, presents an example. There, the HOA unsuccessfully sought a determination from the court that its claims against subcontractors were not barred by the statute of limitations. To do so, the HOAs attempted to apply the Colorado Common Interest Ownership Act (“CCIOA”), which governs the creation and operation of HOAs, and a statute intended to apply to persons under a legal disability.
Under CCIOA, during the period of “declarant control” the developer may appoint members to the association’s executive board until sufficient homeowners have moved into the development and taken seats on the board.
Read the full story…
Reprinted courtesy of Bret Cogdill of Higgins, Hopkins, McClain & Roswell, LLC. Mr. Cogdill can be contacted at cogdill@hhmrlaw.com.
Texas contractual liability exclusion
May 18, 2011 — May 18, 2011 - CDCoverage.com
In Ewing Construction Co., Inc. v. Amerisure Ins. Co., No. C-10-256 (S.D. Tex. April 28, 2011), insured Ewing was the general contractor for an athletic facility constructed for a school district. The school district sued Ewing alleging defective construction of the project. The underlying complaint included contract and negligence causes of action, and sought damages for the repair of the damages and loss of the use of the project. The complaint did not allege damage to any property other than the project itself. Ewing tendered its defense to its CGL insurer Amerisure. Amerisure denied a defense and Ewing filed suit against Amerisure. The federal district trial court entered summary judgment for Amerisure. Applying Texas law, the court held that all of the damages fell within the “contractual liability†exclusion precluding any duty to defend or indemnify.
Read the full story…
Reprinted courtesy of CDCoverage.com
Contractor Removed from Site for Lack of Insurance
October 28, 2011 — CDJ Staff
The MetroWest Daily News reports that a demolition firm was told to leave the construction site at Natick High School since their failure to have workers compensation insurance makes them unable to work on the project. The contractor, Atlantic Dismantling and Site Construction, Inc. may have been working illegally since September.
The equipment that Atlantic had rented for the job was repossessed in August. Brait Builders Corp, the general contractor for the site had rented equipment so Atlantic could continue their work.
Their lack of insurance was discovered when a worker had a minor job-related injury. The state had issued a stop-work order for the firm and they could not legally bid on public projects. The school system did not receive any notice of this, and the school’s facilities director said of the general contractor, “chances are Brait never heard of anything either.”
Read the full story...
Continuous Trigger of Coverage Adopted for Loss Under First Party Policy
August 2, 2012 — Tred Eyerly, Insurance Law Hawaii
The Seventh Circuit predicted that the Wisconsin Supreme Court would adopt the continuous injury trigger for first party property loss that extends over several policy periods. Miller v. Safeco Ins. Co. of Am., 2012 U.S. App. LEXIS 12940 (7th Cir. June 25, 2012).
A home inspection report performed before the Millers purchased their home showed a soft spot on the roof. The stucco's finish color was also uneven and stained. Further, some water damage was found in the study and skylights above the kitchen sink. But the report advised that the exterior walls, chimney, grass roof, flashings, floor joists/beams and columns, garage walls and floor appeared serviceable. A roof specialist determined the soft spot was not significant and could be repaired for $1,500.
The Millers purchased a homeowner's policy from Safeco on June 30, 2005. The policy went into effect the next day when the Millers closed on the property. But the Millers did not see the policy's terms until Safeco mailed them a copy of the policy at the end of July.
Before receiving the policy, the Millers discovered severe inner wall water leaks and significant water infiltration on three of the home's exterior walls.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Claims Under Colorado Defect Action Reform Act Count as Suits
July 10, 2012 — CDJ Staff
The Colorado Court of Appeals has affirmed the judgment of the lower court in Melssen v. Auto-Owners Insurance. The Melssens built a custom home for the Holleys, during which time the Melssens retained a comprehensive general liability policy from Auto-Owners, which “obligated Auto-Owerns to defend the Melssens with respect to any ‘suit’ seeking damages for ‘property damage’ during the policy period.” Soon after the house was constructed, cracks developed in the drywall, then outside stucco and basement slab. The Holleys contended that “approximately $300,000 of damages to the Holleys’ property was caused by the Melssens’ engineering and construction defects” and filed a claim under the Colorado Defect Action Reform Act (CDARA). The Melssens “demanded Auto-Owners defend and indemnify the Melssens and forwared Auto-Owners the notice of claim.”
Although the Melssens notified Auto-Owners in June 2008, it was not until October 2008 that Auto-Owners denied coverage stating that the claims were sustained outside the policy period. The Melssens filed an action against Auto-Owners. At trial, the jury ruled in favor of the Melssens awarding them damages, to which the trial court added costs and attorney fees.
On appeal, Auto-Owners contended that the trial court erred in allowing the Melssens to argue that the CDARA notice of claim “was the functional equivalent of a complaint commencing a suit.” The appeals court found that “the CDARA notice of claim process constituted an alternative dispute resolution proceeding under the policy.” The court agreed that jury should not have been asked to determine if a CDARA action is a “suit,” but as the jury found for the Melssens, the concluding it “constituted harmless error.” Further, the court found that an action under the CDARA satisfied the definition of a “suit.”
The court found for the Melssens, affirming the lower court’s decision and remanding the case to the lower court for the awarding of appeals costs to the Melssens.
Read the court’s decision…
Partial Settlement in DeKalb Construction Management Case
July 10, 2012 — CDJ Staff
The DeKalb County School District has made a partial settlement in a lawsuit over their claims of mismanagement of construction projects. The Atlanta Journal-Constitution reports that the school board settled with E. R. Mitchell & Co., the smaller of two firms that they have sued. As part of the settlement, Mitchell will be testifying against their former partner. Claims from the other side of the lawsuit are that the school board improperly fired the Heery/Mitchell partnership. The superintendant who fired the company, Crawford Lewis, and his chief operations office, Pat Reid, have since been charged with criminal conspiracy to defraud the construction program. A lawyer for Heery said that “we believe that when presented to a jury, Heery will be vindicated.”
Read the full story…
Local Government Waives Construction Fees to Spur Jobs
June 19, 2012 — CDJ Staff
Warren Township in New Jersey has waived building and electrical permit fees, up to $5,000, for businesses that create at least five new jobs. The fee reductions are available for construction in areas zones under various designations. Buildings that have received a zoning variance are not eligible. The Echoes-Sentinel notes that other towns in Somerset County, New Jersey have adopted similar ordinances.
Read the full story…
One Colorado Court Allows Negligence Claim by General Contractor Against Subcontractor
December 20, 2012 — Heather Anderson , Higgins, Hopkins, McLain & Roswell
Judge Paul King of the Douglas County District Court recently confirmed that subcontractors in residential construction owe an independent duty, separate and apart from any contractual duties, to act without negligence in the construction of a home in Colorado. See Order, dated September 7, 2010, Sunoo v. Hickory Homes, Inc. et al., Case No. 2007CV1866; see alsoCosmopolitan Homes, Inc. v. Weller, 663 P.2d 1041 (Colo. 1983); A.C. Excavating v. Yacht Club II Homeowners Ass’n, Inc., 114 P.3d 862 (Colo. 2005). He also verified that the holding in the B.R.W. Inc. v. Dufficy & Sons, Inc., 99 P.3d 66 (Colo. 2004)[1] case does not prohibit general contractors, such as Hickory Homes, from enforcing a subcontractor’s independent duty to act without negligence in the construction of a home.
Read the full story…
Reprinted courtesy of Heather Anderson, Higgins, Hopkins, McLain & Roswell, LLC. Ms. Anderson can be contacted at anderson@hhmrlaw.com
Micropiles for bad soil: a Tarheel victory
March 14, 2011 — Original article by by Melissa Brumback on March 14, 2011
Despite foundation challenges, construction is almost complete on the expansion at University of North Carolina’s Kenan stadium. The project started with a deep foundation system from design-build contractor GeoStructures. Known as the Carolina Student-Athlete Center for Excellence, the addition was built on a parcel with a knotty mix of fill soils, subsurface boulders and varying depths to rock. To achieve uniform foundation support, GeoStructures designed a Micropile system (also known as a Mini pile system) which could be drilled into the variable ground conditions.
Read the full story...
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl law.com.
Nevada Court Adopts Efficient Proximate Cause Doctrine
February 10, 2012 — Tred Eyerly, Insurance Law Hawaii
Although the Nevada Supreme Court adopted the efficient proximate cause doctrine, it determined it did not apply to salvage coverage under an all-risk policy for a rain-damaged building. Fourth Street Place, LLC v. The Travelers Indemn. Co., 2011 Nev LEXIS 114 (Nev. Dec. 29, 2011).
Fourth Street owned an office building which was insured by an all-risk policy issued by Travelers. Fourth Street hired Above It All Roofing to repair the roof of the office building. Above It All removed the waterproof membrane on the roof and prepared to replace the membrane the following week. Over the weekend, however, substantial rain hit. On Sunday, Above It All returned to cover the exposed portions of the roof with tarps, but wind later blew the tarps away. The building suffered significant interior damage as it continued to be exposed to the rain.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Lower Court “Eminently Reasonable” but Wrong in Construction Defect Case
July 10, 2012 — CDJ Staff
Noting that “circuit court’s orders are eminently reasonable, logical and just” the Supreme Court of Appeals of West Virginia has granted a writ to halt enforcement of these orders and to compel arbitration instead in the case of State v. Tucker. The initial case concerned claims that an HVAC system had been improperly designed, constructed, manufactured, or maintained, leading to serious problems. Glenmark Holding, the owner of the Suncrest Executive Plaza brought a lawsuit against seven defendants. Three of the defendants, Morgan Keller, Inc, York International Corporation, and Johnson Controls, Inc. argued that Glenmark was obligated to enter into arbitration.
Glenmark and the other defendants argued that the motions for arbitration should be denied “so all the claims and cross-claims of the parties could be litigated in one forum, in one proceeding.” The circuit court noted that arbitration is preferred over litigation because of its supposed “expeditious, economic resolution of issues,” but that in this case, “the petitioners would expend additional, not fewer resources responding to the parties’ claims and cross-claims.” As “compulsory arbitration would be insufficient and inequitable” the court denied the request, finding the arbitration clauses “unconscionable and, therefore, unenforceable.”
Morgan Keller, York, and Johson argued that “the interpretation of arbitration clauses is governed exclusively by the Federal Arbitration Act.” The appeals court found that “the circuit court was within its authority to consider Glenmark’s claim that the arbitration clauses were unenforceable.” However, the appeals court rejected the circuit court’s conclusion about the “piecemeal” resolution of the conflict, as it contradicts a Supreme Court ruling. The Supreme Court stated in 1983 that the FAA “requires piecemeal resolution when necessary to give effect to an arbitration agreement.” In a 1985 decision, the Court held that a court could “not substitute [its] own views of economy and efficiency.”
Nor could the court find the arbitration clause to be unconscionable or unenforceable. The court noted that the contract was a standard AIA form, and was amended by the parties involved, whom the court characterized as “commercially sophisticated.” The court found that the agreement limited the rights of all parties and was not one-sided.
As the arbitration clause was neither unconscionable nor unenforceable, and Supreme Court rulings preclude a court from substituting its own procedures, even when these are “eminently reasonable, logical and just,” the appeals court halted the order of the circuit court, sending the matter to arbitration.
Read the court’s decision…
Builder Cannot Receive Setoff in Construction Defect Case
July 10, 2012 — CDJ Staff
The California Court of Appeals has dismissed an appeal in a San Diego construction defect case. In Smith v. Walters Group, Christopher and Maud Smith sued The Walters Group, a real estate developer, and Galen C. Pavelko, Inc, the builder of their home. Walters had bought five lots and hired Pavelko to build houses on them, selling one of these homes to the Smiths. “After moving in, the Smiths noticed a strong and obnoxious odor permeating the house.” The Smiths sued but were ordered to arbitrate instead, pursuant to a clause in the purchase contract. The Smiths were awarded $1.5 million at arbitration.
Walters requested that the arbitration remain open to determine if Walters was entitled to a setoff for settlements from defendants not involved in the arbitration. During this time, Pavelko made a settlement with the Smiths, which the court found was in good faith. At the same time, the arbitrator “reached the opposite conclusion.” The arbitrator concluded that “only settlements made ‘in good faith before verdict or judgment’ qualified for setoff.”
Walters moved that the trial court “‘correct’ the award,” but the trial court declined to do so and confirmed the award. In the appeal, Walters raised the issue of “whether Pavelko’s settlement occurred ‘before verdict or judgment.’” The appeals court dismissed the appeal, noting that “Walters would not be entitled to a $500,000 setoff if we reversed the trial court’s order determining the Smith-Pavelko settlement was made in good faith because Pavelko’s $500,000 payment was expressly conditioned on such an order.” They add that “were we to reverse the trial court’s order, Pavelko would have no obligation to pay the Smiths the $500,000.” This would then “deprive Walters of the corresponding statutory right to a setoff.”
Read the court’s decision…
Eighth Circuit Remands to Determine Applicability of Collapse Exclusion
January 6, 2012 — Tred Eyerly, Insurance Law Hawaii
The Eighth Circuit determined a jury instruction regarding the applicability of the "all-risk" policy’s exclusion for "collapse" was inadequate. See KAAPA Ethanol, LLC v. Affiliated FM Ins. Co., 2011 U.S. App. LEXIS 22158 (8th Cir. Nov. 3, 2011).
KAAPA had nine large, cylindrical, stainless steel tanks fabricated at its location. Soon after operations began in 2003, some of the tanks experienced unusual movement and began to shift. A geotechnical engineer found "silty clay" had been used for infill instead of compacted granular fill called for in engineering drawings. A year long plan to repair all nine tanks was implemented.
Affiliated’s "all-risk" policy excluded damage caused by faulty workmanship. It also excluded damage caused by settling or cracking. The settling exclusion went on to provide, "This exclusion will not apply to loss or damage resulting from collapse of: a building or structure; or material part of a building or structure." Affiliated denied coverage because of the faulty workmanship and settling exclusions.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Nebraska Man Sentenced for Insurance Fraud in Construction Projects
July 10, 2012 — CDJ Staff
Thomas Herink has been ordered to repay more than $5 million to his victims and will be serving three years of probation after 18 months in jail for defrauding banks and insurance companies, according to a report in the Insurance Journal. Herink falsified financial statements to lenders and insurers so that his company, Golf Services Group Inc. could participate in construction projects.
Read the full story…
Senate Committee Approves Military Construction Funds
June 29, 2011 — CDJ Staff
With a decrease in funding, as compared to the House bill, the Military Construction and Veteran’s Affairs subcommittee of the Senate moved on a $72 billion construction bill. The House version had approved an additional half billion dollars in funding. Senator Tim Johnson, Democrat of South Carolina, said that he expected easy reconciliation with the House version. The Senate bill will move to the full Senate Appropriations Committee on June 30.
The bill, S 1255, includes funding for construction and remodeling of military housing, as well as construction and remodeling of base facilities.
Read the full story… Read S1255
Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.
April 28, 2011 — April 28, 2011 Beverley BevenFlorez - Construction Defect Journal
In the construction defect suit Kikirov v. 355 Realty Associates, LLC, et al., the Supreme Court of the State of New York granted a dismissal of the plaintiff’s fourth cause of action, but denied the defendants’ motion in all other respects. The plaintiff alleged breach of contract, among other claims. “355 Realty was the sponsor of 355 Kings Highway Condominium, a condominium project located at 355 Kings Highway, in Brooklyn, New York. The condominium units were allegedly marketed as ‘ultra luxury condos,’ and a ‘Manhattan style condominium building,’ which would be the ‘epitome of luxury and quality.’ The construction of the six-story 28 unit residential condominium building began in approximately November 2003. […] Plaintiff entered into a purchase agreement, dated December 21, 2005, with 355 Realty (which was executed on behalf of 355 Realty by Michael Marino, as its member) for the purchase of Unit 2G in the building.”
The plaintiff alleged that construction defects emerged soon after moving into the unit: “After taking occupancy of his condominium unit, plaintiff allegedly experienced serious leakage and moisture problems in his unit, which caused a dangerous mold condition to develop, in addition to causing actual damage to the structural elements of his unit. According to plaintiff, the walls, moldings, and wood floors of his unit are constantly wet and moist, and there is severe buckling of the wood floors. Plaintiff claims that these problems have caused his unit to be uninhabitable. Plaintiff alleges that he has been forced to remove all of his personal belongings from his unit and has been unable to occupy his unit.”
According to the plaintiff, Foremost attempted to repair the defects, but only made the situation worse: “Specifically, plaintiff asserts that Foremost’s contractors opened his walls to remove the stained drywall, but never corrected the cause of the leaks, destroyed the walls, and never properly taped and painted the sheet rock. Plaintiff alleges that Foremost repaired the openings in a defective manner. Plaintiff also claims that his floor was repaired at that time by a subcontractor hired by Foremost, but the basic structural problem was never resolved and the leaks continued, compromising the beams and causing the mold conditions, in addition to all of the physical damage present in the unit. On or about July 16, 2009, plaintiff allegedly sent a notice of the defects to 355 Realty and to the managing agent designated by the condominium board, by certified mail, return receipt requested. Plaintiff asserts that defendants have failed and refused to repair and remedy the defective condition, and that the damage is extensive and requires major structural repairs.”
The plaintiff filed suit on May 4, 2010, and the original complaint asserted eight causes of action. “By decision and order dated September 13, 2010, the court granted a motion by defendants to dismiss plaintiff’s second cause of action for breach of implied covenants of good faith and fair dealing, his third cause of action for breach of implied warranties, his fifth cause of action for negligence as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his seventh cause of action for negligence as against Vision, Foremost, and MMJ, and his eighth cause of action for violations of General Business Law § 349 and § 350, and granted plaintiff leave to replead his first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, his fourth cause of action for breach of statutory warranties, and his sixth cause of action for breach of contract as against Vision, Foremost, and MMJ.”
The plaintiff amended their complaint on October 18, 2010, and “has repleaded these three causes of action by asserting a first cause of action for breach of contract as against 355 Realty, Michael Marino, Anthony Piscione, Ahron Hersh, and Toby Hersh, a second cause of action for breach of statutory warranties, and a third cause of action for breach of contract as against Vision, Foremost, and MMJ. In addition, plaintiff, in his amended complaint, has added a fourth cause of action for fraud.”
The defendants, on the other hand, “argue that each of the four causes of action alleged by plaintiff in his amended complaint fail to state a claim upon which relief may be granted, and that plaintiff’s amended complaint must be dismissed pursuant to CPLR 3211 (a) (7). Defendants also cite to CPLR 3211 (a) (1), and (5), asserting that dismissal is also required based upon documentary evidence and the Statute of Limitations contained in the limited warranty.”The defendants’ motion to dismiss the first cause of action, breach of contract against 355 Realty, was denied: “While defendants dispute that the alleged defects are actually structural in nature, plaintiff’s allegations as to their structural nature are sufficient, at this juncture, to withstand defendants’ motion to dismiss. Thus, dismissal of plaintiff’s first cause of action must be denied.”
Next, the court reviewed the second cause of action, which was breach of statutory warranties: “Defendants’ motion also seeks dismissal of plaintiff’s second cause of action for breach of statutory warranties, which alleges that, under applicable law, including General Business Law § 777-a, et seq., the sponsor warranted to purchasers of units that the units would be constructed in a skillful, careful, and workmanlike manner, consistent with proper design, engineering, and construction standards and practices, and free of material latent, design, and structural defects. Defendants argue that General Business Law § 777-a, known as the housing merchant implied warranty, is inapplicable to this case because it is limited to the construction of a ‘new home,’ defined in General Business Law § 777 (5) as ‘any single family house or for-sale unit in a multi-unit residential structure of five stories or less.’ As noted above, the building in which plaintiff’s condominium unit is located is a six-story building.”
The motion to dismiss the second cause of action is denied. The court provided this reasoning: “the full text of the offering plan has not been provided, the court is unable to examine the entire written agreement so as to determine the purpose of the inclusion of the text of General Business Law § 777.”
In the third cause of action, the plaintiff alleges “a breach of contract claim as against Vision, Foremost, and MMJ based upon their contract with 355 Realty, pursuant to which they agreed to be the general contractors/construction managers for the condominium, to undertake oversight responsibility for the design and construction of the condominium, to prepare and/or review drawings, plans, and specifications for the condominium, and to otherwise manage and oversee the project. Plaintiff alleges that Vision, Foremost, and MMJ breached their contractual obligations in that the condominium units were improperly and inadequately designed and constructed, and completed in an incompetent and unworkmanlike manner, with material design and construction defects.”
The motion to dismiss the third cause of action was denied as well: “Plaintiff alleges, in his amended complaint, that Vision, Foremost, and MMJ have acknowledged notice of the defects and have not denied that they are responsible for providing a warranty to plaintiff. Plaintiff also refers to this warranty, in his amended complaint, by noting that paragraph 16 of the purchase agreement stated that the ‘[s]eller shall not be liable to . . . the [p]urchaser for any matter as to which an assignable warranty . . . has been assigned . . . to [p]urchaser and in such case the sole recourse of such . . . [p]urchaser . . . shall be against the warrantor . . . except that in the event a contractor or subcontractor is financially unable or refuses to perform its warranty . . . [s]eller shall not be excused from its obligations enumerated in the [offering p]lan under Rights and Obligations of Sponsor.’ Consequently, the court finds that dismissal of plaintiff’s third cause of action as against Foremost and MMJ must also be denied.”
In the fourth cause of action, the plaintiff alleges “that defendants made false statements and representations orally, in advertisements, and in the purchase agreement, that the condominium was properly and adequately designed and constructed and completed in a competent and workmanlike manner, in accordance with the condominium plans and specifications and proper design, engineering, and construction standards and practices consistent with applicable standards for a first class, luxury condominium in Brooklyn.”
The court dismissed the fourth cause of action stating, “it must be dismissed because it is duplicative of his first cause of action for breach of contract.” Therefore, “defendants’ motion to dismiss plaintiff’s amended complaint is granted to the extent that it seeks dismissal of plaintiff’s fourth cause of action, and it is denied in all other respects.”
Read the court’s decision…
CC&Rs Not the Place for Arbitration Agreement, Court Rules
May 24, 2011 — CDJ Staff
In January, the California Court of Appeals ruled that an arbitration clause inserted in a development’s CC&Rs by the developer could not be enforced. The case, Villa Vicenza Homeowners Association v. Noble Court Development, involved a case in which, according to the opinion, “following the first sale Nobel controlled the board of directors of the Association and because the initial condominium buyers noticed defects in common areas and common facilities and did not believe Nobel had provided a reserve fund sufficient to repair the defects, the condominium owners brought a derivative action on behalf of the Association against Nobel.”
The court concluded, “The use of CC&R's as a means of providing contractual rights to parties with no interest in or responsibility for a common interest development is also problematic from the standpoint of determining what if any consideration would support such third-party agreements. By their terms the CC&R's bind all successors, even those with whom a third party such as Nobel has never had any contractual relationship and to whom Nobel has not provided any consideration.” The court determined that “the trial court did not err in denying Nobel's motion to compel arbitration.”
Read the court’s decision