    concrete tilt-up Sunbright Tennessee tract home Sunbright Tennessee production housing Sunbright Tennessee retail construction Sunbright Tennessee hospital construction Sunbright Tennessee industrial building Sunbright Tennessee condominiums Sunbright Tennessee Subterranean parking Sunbright Tennessee custom home Sunbright Tennessee office building Sunbright Tennessee structural steel construction Sunbright Tennessee multi family housing Sunbright Tennessee institutional building Sunbright Tennessee condominium Sunbright Tennessee Medical building Sunbright Tennessee landscaping construction Sunbright Tennessee custom homes Sunbright Tennessee parking structure Sunbright Tennessee townhome construction Sunbright Tennessee high-rise construction Sunbright Tennessee housing Sunbright Tennessee low-income housing Sunbright Tennessee
    Arrange No Cost Consultation
    Construction Expert Witness Builders Information
    Sunbright, Tennessee

    Tennessee Builders Right To Repair Current Law Summary:

    Current Law Summary: (HB 2787/SB2931 & HB 2771/SB 2201; Title 66, Chptr 36) Homeowners must serve written notice of a defect 15 days after its discovery; Contractors, upon receipt of the notice, have 10 business days to inspect the residence and inform any subcontractors it believes are reasonably responsible on the defect. Within 10 business days after notice of the claim, the subcontractor must serve a written response to contractor. Within 30 days after receipt of notice of a defect, the contractor must provide written notice of intention (repair, replace, monetarily compensate or reject) to the homeowner.


    Construction Expert Witness Contractors Licensing
    Guidelines Sunbright Tennessee

    Commercial and Residential Contractors License Required.


    Construction Expert Witness Contractors Building Industry
    Association Directory
    Greene County Chapter of National Associated Home Builders
    Local # 4464
    70 Afton Road
    Afton, TN 37616


    Johnson City Area Home Builders Association
    Local # 4494
    1001 N Roan St
    Johnson City, TN 37601
    http://www.jcahba.org

    Home Builders Association of Tennessee
    Local # 4400
    213 5th Ave N Ste 200
    Nashville, TN 37219
    http://www.hbat.org

    Home Builders Association of Upper Cumberland
    Local # 4491
    PO Box 243
    Cookeville, TN 38503
    http://www.uchba.com

    Home Builders Association of Dyer Co
    Local # 4425
    1075 Cooper Dr
    Dyersburg, TN 38024


    Home Builders Association of Gr Kingsport
    Local # 4445
    1200 E Sevier Ave
    Kingsport, TN 37664
    http://www.kingsporthomebuilders.com

    Clarksville-Montgomery Co Home Builders Association
    Local # 4406
    PO Box 1167
    Clarksville, TN 37041
    http://www.clarksvillehba.org


    Construction Expert Witness News and Information
    For Sunbright Tennessee

    Defense for Additional Insured Not Barred By Sole Negligence Provision

    Delays in Filing Lead to Dismissal in Moisture Intrusion Lawsuit

    Insurer Must Cover Construction Defects Claims under Actual Injury Rule

    Construction Delayed by Discovery of Bones

    Safe Harbors- not just for Sailors anymore (or, why advance planning can prevent claims of defective plans & specs) (law note)

    Construction Defects Are Occurrences, Says Georgia Supreme Court

    Ensuing Losses From Faulty Workmanship Must be Covered

    San Diego Construction Defect Claim Settled for $2.3 Million

    Contractor Sues License Board

    Federal Judge Dismisses Insurance Coverage Lawsuit In Construction Defect Case

    Anti-Assignment Provision Unenforceable in Kentucky

    Orange County Home Builder Dead at 93

    Congress Addresses Homebuilding Credit Crunch

    Equipment Costs? It’s a Steal!

    Nevada Budget Remains at Impasse over Construction Defect Law

    Unlicensed Contractors Nabbed in Sting Operation

    Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)

    Hospital Construction Firm Settles Defect Claim for $1.1 Million

    Florida trigger

    Arizona Contractor Designs Water-Repellant Cabinets

    Repair of Part May Necessitate Replacement of Whole

    One to Watch: Case Takes on Economic Loss Rule and Professional Duties

    DA’s Office Checking Workers Comp Compliance

    Florida Construction Defect Case Settled for $3 Million

    Bound by Group Builders, Federal District Court Finds No Occurrence

    There is No Non-Delegable Duty on the Part of Residential Builders in Colorado

    Homeowners Must Comply with Arbitration over Construction Defects

    Connecticut Gets Medieval All Over Construction Defects

    School Sues over Botched Pool

    Claims Under Colorado Defect Action Reform Act Count as Suits

    Florida Contractor on Trial for Bribing School Official

    Consumer Protection Act Whacks Seattle Roofing Contractor

    Nevada Supreme Court Reverses Decision against Grader in Drainage Case

    Florida Property Bill Passes Economic Affairs Committee with Amendments

    $5 Million Construction Defect Lawsuit over Oregon Townhomes

    Can Negligent Contractors Shift Blame in South Carolina?

    Gut Feeling Does Not Disqualify Expert Opinion

    Virginia Homebuilding Slumps After Last Year’s Gain

    Exclusion Bars Coverage for Mold, Fungus

    Bill Seeks to Protect Legitimate Contractors

    Arizona Court of Appeals Rules Issues Were Not Covered in Construction Defect Suit

    Minnesota Starts Wide-Ranging Registration of Contractors

    One World Trade Center Due to Be America’s Tallest and World’s Priciest

    Workers Hurt in Casino Floor Collapse

    Save A Legal Fee? Sometimes You Better Talk With Your Construction Attorney

    A Downside of Associational Standing - HOA's Claims Against Subcontractors Barred by Statute of Limitations

    Arizona Supreme Court Confirms Eight-Year Limit on Construction Defect Lawsuits

    US Courts in Nevada Busy with Yellow Brass

    Insurers Reacting to Massachusetts Tornadoes

    Continuous Trigger of Coverage Adopted for Loss Under First Party Policy

    Background Owner of Property Cannot Be Compelled to Arbitrate Construction Defects

    Homeowner’s Policy Excludes Coverage for Loss Caused by Chinese Drywall

    Colorado Statutes of Limitations and Repose, A First Step in Construction Defect Litigation

    Failure to Meet Code Case Remanded to Lower Court for Attorney Fees

    Colorado statutory “property damage” caused by an “occurrence”

    Former New York Governor to Head Construction Monitoring Firm

    In Colorado, Repair Vendors Can Bring First-Party Bad Faith Actions For Amounts Owed From an Insurer

    Firm Sued For Construction Defects in Parking Garage

    Arbitration Clause Found Ambiguous in Construction Defect Case

    Ensuing Loss Found Ambiguous, Allowing Coverage

    No Coverage for Construction Defects Under Alabama Law

    Contractual Liability Exclusion Bars Coverage

    Increased Expenditure on Injuries for New York City School Construction

    Homeowners Not Compelled to Arbitration in Construction Defect Lawsuit

    No Coverage Under Ensuing Loss Provision

    Unfinished Building Projects Litter Miami

    In Oregon Construction Defect Claims, “Contract Is (Still) King”

    Construction Defects Not Occurrences under Ohio Law

    Contractor Burns Down Home, Insurer Refuses Coverage

    Town Files Construction Lawsuit over Dust

    The Colorado Court of Appeals Rules that a Statutory Notice of Claim Triggers an Insurer’s Duty to Defend.

    New Construction Laws, New Forms in California

    Badly Constructed Masonry Walls Not an Occurrence in Arkansas Law

    Texas covered versus uncovered allocation and “legally obligated to pay.”

    A Call to Washington: Online Permitting Saves Money and the Environment

    Homebuilders Go Green in Response to Homebuyer Demand

    Does the New Jersey Right-To-Repair Law Omit Too Many Construction Defects?

    District Court’s Ruling Affirmed in TCD v American Family Mutual Insurance Co.

    West Coast Casualty Promises Exciting Line Up at the Nineteenth Annual Conference

    Public Relations Battle over Harmon Tower

    Georgia Supreme Court Rules Construction Defects Can Constitute an Occurrence in CGL Policies

    Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case

    When Does a Claim Against an Insurance Carrier for Failing to Defend Accrue?

    Construction Firm Charged for Creating “Hail” Damage

    Arizona Court of Appeals Decision in $8.475 Million Construction Defect Class Action Suit

    Construction Defect Journal Seeks Article Submissions Regarding SB800 and Other Builders Right to Repair Laws

    Faulty Workmanship Exclusion Does Not Bar Coverage

    Utah Construction Defect Claims Dependant on Contracts

    Construction on the Rise in Washington Town

    Flooded Courtroom May be Due to Construction Defect
    Corporate Profile

    SUNBRIGHT TENNESSEE CONSTRUCTION EXPERT WITNESS
    DIRECTORY AND CAPABILITIES

    Leveraging from more than 5500 construction defect and claims related expert witness designations, the Sunbright, Tennessee Construction Expert Witness Group provides a wide range of trial support and consulting services to Sunbright's most acknowledged construction practice groups, CGL carriers, builders, owners, and public agencies. Drawing from a diverse pool of construction and design professionals, BHA is able to simultaneously analyze complex claims from the perspective of design, engineering, cost, or standard of care.









    Construction Expert Witness News & Info
    Sunbright, Tennessee

    Construction Delayed by Discovery of Bones

    June 28, 2011 — CDJ Staff

    Work stopped on a $7 million construction project in Oak Harbor, Washington, after three sets of Native American remains were found. The Washington State Department of Archaeology and Historic Preservation had suggested that the project employ an archaeologist. City, state, and tribal officials are determining what will happen next. The Seattle Times reports that Jim Slowik, Oak Harbor’s mayor, has asked for a review of why no archaeologist was part of the project.

    Read the full story…


    Drug Company Provides Cure for Development Woes

    November 18, 2011 — CDJ Staff

    Vertex Pharmaceuticals is poised to become the holder of Boston’s biggest commercial lease, paying $72.5 million for 1.1 million square feet on Boston’s waterfront. Vertex’s new buildings are still under construction, but the plans have spurred other development in the Fan Pier area, according to the New York Times. The Times quotes Mary A. Burke, a senior economist at the Federal Reserve Bank of Boston that the Vertex project gives “a big push” to the “momentum for economic growth.”

    The Fallon Company is building Vertex’s new laboratory and office space. They are separately planning to build a high-rise with 150 luxury condominium units. According to Joseph Fallon, the chief executive and president of the Fallon Company, there is already a waiting list of 50 buyers for the condominiums.

    Across the street from the Vertex site, a group including Morgan Stanley and Boston Global Investors is planning a 23-block mixed use project that would include 1.2 million square feet of retail space. Additionally, the New England Development and the Hanover Group is building a 356-unit apartment building at the adjacent Pier 4.

    Read the full story…


    A Loud Boom, But No Serious Injuries in World Trade Center Accident

    March 1, 2012 — CDJ Staff

    The Wall Street Journal reports that nearly twenty tons of steel fell forty stories at the World Trade Center site on February 16. One person was checked by medical personnel. One person who works in the Financial District said it was “almost like thunder.” Frank Pensabene, one of the ironworkers on the site said that after “loud boom,” “all hell broke loose.” The steel beams and cables fell onto a flatbed truck, which was not occupied at the time.

    Read the full story…


    Who Is To Blame For Defective — And Still LEED Certified — Courthouse Square?

    September 1, 2011 — Douglas Reiser, Builders Counsel

    Remember Courthouse Square? I sure do. We have talked about the closed and evacuated LEED certified building a couple of times here on Builders Counsel. Well, it’s back in the news. This time building professionals are pointing fingers — but there is some talk about a fix. Still, its LEED certification remains.

    If you read my past articles about Courthouse Square, you can get caught up on this mess. The short of it is that Salem, Oregon had the five-story government building and bus mall completed in 2000 for $34 Million. It was awarded LEED certification during the USGBC’s infancy. Last year, it became public that the building had significantly defective concrete and design. The Salem-Keizer Transit District worked with the City of Salem to shut the building down, and it has not been occupied since.

    Last fall, Courthouse Square failed thorough forensic testing leading to a lengthy bout with a number of insurers.  The contractors and designers had been hauled into court, but the Transit District was able to settle with the architect and contractors. The only remaining party involved in the lawsuit appears to be the engineering firm, Century West Engineering. Most expert reports have pinned the responsibility for the poor design and materials on Century West’s shoulders.

    Read the full story…

    Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com


    Surveyors Statute Trumps Construction Defect Claim in Tennessee

    June 19, 2012 — CDJ Staff

    The Tennessee Court of Appeals has issued an opinion in the case of Dale v. B&J Enters. (Tenn. App., 2012), affirming the ruling of the Chancery Court for Knox County. The homeowners purchased properties in Knoxville, Tennessee in 2007 and 2008. Subsequently, according to the complaint, they found “significant sink holes and depressions throughout the subdivision.” The plaintiffs determined that a previous developer in 2004 had been aware of the sink holes. The Knox County Metropolitan Planning Commission, upon giving approval, made requirements that included that sink holes, even if they were filled, had to be designated on the site plans. The developer did not indicate these locations on the final plans. The plaintiffs made claims of “failure to disclose, misrepresentation, misrepresentation by concealment, and violation of the Tennessee Consumer Protection Act.” They filed their suit in June 2009.

    The defendants in the initial case, argued that they did not create the final plat, the site plan indicating the features and lot lines. This had been the work of the previous developer. In September, 2009, the plaintiffs amended their complaint to include the previous developer and its engineering firm. The engineering firm disavowed any responsibility. The developer noted that the surveyor, Benchmark Associates, had “failed to properly include the sink holes and/or depressions on the final plat.” In June, 2010, the plaintiffs added Benchmark.

    Benchmark argued that the plaintiffs’ claims should be dismissed, as Tennessee has a four-year statute of limitations on claims against surveyors. The final plat was recorded on May 19, 2006, and the plaintiff filed their claims against Benchmark on June 16, 2010, slightly less than a month over four years. The plaintiffs argued that “the real issue [was] the tortious misrepresentation by Benchmark.” The Chancery Court found for Benchmark.

    On appeal, the plaintiffs raised three issues. They argued that the trial court applied the wrong section of the law, and should have applied the section applying to construction and not surveyors. They also argued that the timeliness of the claim should be based on when the defects were discovered. The also raised the question of whether the laws concerning surveyors bar claims for misrepresentation. The appeals court upheld the decision of the Chancery Court.

    For the plaintiff’s first claim, although the statute addressing deficiencies in construction mentions surveying, an earlier court ruling found that the legislature had removed a reference to surveyors in one part of the statute, but failed to do so in the second part. The earlier court had concluded that the “obvious intent of the legislature was to place all limits on actions against surveyors into the new statute.” As the applicable statute states that “any such action not instituted within this four (4) year period shall be forever barred,” the court held that the plaintiffs’ claims must be time barred. Further, as the intent of the legislature was determined to “place all limits on actions against surveyors into one statute,” the court felt that it could not apply the Consumer Protection Act.

    Read the court’s decision…


    Insurer Able to Refuse Coverage for Failed Retaining Wall

    October 28, 2011 — CDJ Staff

    The Eleventh District of the US Court of Appeals has ruled in the case of Nix v. State Farm Fire & Casualty Company. In this case, the Nixes filed a claim after a portion of the retaining wall in their home collapsed and their basement flooded. State Farm denied the claim “on the ground that the policy excluded coverage for collapses caused by defects in construction and for damage caused by groundwater.”

    The court reviewed the Nixes’ policy and found that State Farm’s statement did specifically exclude both of these items. In reviewing the lower court’s ruling, the appeals court noted that State Farm’s expert witness, Mark Voll, determined that the retaining wall “lacked reinforcing steel, as required by a local building code, and could not withstand the pressure created by groundwater that had accumulated during a heavy rainfall.” Additionally, a french drain had been covered with clay soil and so had failed to disperse the groundwater.

    The Nixes argued that the flooding was due to a main line water pipe, but their opinions were those of Terry Nix and the contractor who made temporary repairs to the wall. “Those opinions were not admissible as lay testimony. Neither Nix nor the contractor witnessed the wall collapse or had personal knowledge about the construction of the Nixes’ home.”

    The lower court granted a summary judgment to State Farm which has been upheld by the appeals court.

    Read the court’s decision…


    Contract Not So Clear in South Carolina Construction Defect Case

    November 7, 2012 — CDJ Staff

    The South Carolina Court of Appeals has reversed a partial summary judgment issued by one of the lower courts in the case of The Retreat at Edisto Co-Owners Association v. The Retreat at Edisto. The underlying issues of the case deal with a construction defect complaint.

    The lower court had concluded “Developer’s ‘First Amendment’ to the Master Deed required the Developer to satisfy the provision in the paragraph labeled ‘Master Deed Amendment or Phase II’ as a condition precedent to its election to proceed with the development of Phase II.”

    The appeals court found that “the language of the First Amendment to the Master Deed is susceptible to more than one interpretation.” The court additionally concluded that the “Developer presented the requisite scintilla of evidence on the question of its intent in order to establish a genuine issue of material fact. As the material facts were in dispute, the appeals court reversed the summary judgment and remanded the case to the circuit court for further proceedings.

    Read the court’s decision…


    Harsh New Time Limits on Construction Defect Claims

    April 26, 2011 — April 26, 2011 by Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq. of Sullan2, Sandgrund, Smith & Perczak, P.C. in the HindemanSanchez blog

    A recent Colorado Supreme Court decision, Smith v. Executive Custom Homes, Inc., 230 P.3d 1186 (Colo. 2010), considerably shortens the time limit for bringing many construction defect lawsuits. Homeowners and homeowner associations risk losing the right to seek reimbursement from builders, developers and other construction professionals unless they carefully and quickly act upon discovery of evidence of any potential construction defect.

    The Statute of Limitations for Construction Defect Claims
    Colorado’s construction defect statute of limitations limits the time for homeowners and homeowners associations to bring lawsuits for construction defects against “construction professionals,” including developers, general contractors, builders, engineers, architects, other design professionals, inspectors and subcontractors. The statute requires homeowners and associations to file suit within two years “after the claim for relief arises.” A claim for relief “arises” when a homeowner or association discovers or reasonably should have discovered the physical manifestation of a construction defect.

    The two-year time limitation applies to each construction defect separately, and will begin to run upon the appearance of a “manifestation” of a construction defect (which may include, for example, a condition as simple as a roof leak or drywall cracks), even if the homeowner or association does not know the cause of the apparent problem.

    The Smith Opinion and its Effect on the Statute of Limitations
    In Smith v. Executive Custom Homes, Inc., the plaintiff homeowner, Mrs. Smith, slipped on ice that had accumulated on her sidewalk because of a leaking gutter and suffered injury. When she first noticed the leak, she reported it to her property manager, who reported it to the builder. The builder attempted to repair the gutter, unbeknownst to Mrs. Smith, and she did not notice further problems until approximately one year after she first observed the leak, when she fell and suffered serious injury. She sued the builder within two years of her injury, but nearly three years after she first learned of the leak.

    The Colorado Supreme Court dismissed Mrs. Smith’s claims as untimely and held that under the construction defect statute of limitations, the two-year period for suing for injuries due to construction defects begins when the homeowner first observes the physical manifestation of the defect, even if the resulting injury has not yet occurred. The court acknowledged that this ruling could result in “unfair results,” especially if a serious and unforeseeable injury occurs more than two years after the first time the homeowner noticed the problem, and as a result the victim is unable to seek redress from those responsible for the defect.

    Read the full story…

    Reprinted courtesy of Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq. of Sullan2, Sandgrund, Smith & Perczak, P.C., and they can be contacted through their web site.


    Repair of Part May Necessitate Replacement of Whole

    February 10, 2012 — CDJ Staff

    Judge Gleuda E. Edmonds, a magistrate judge in the United States District Court of Arizona issued a ruling in Guadiana v. State Farm on January 25, 2012. Judge Edmonds recommended a partial summary judgment in favor of the plaintiff.

    Ms. Guandiana’s home had water damage due to pluming leaks in September 2004. She was informed that polybutylene pluming in her house could not be repaired in parts “it must be completely replaced.” She had had the plumbing replaced. State Farm denied her claim, arguing that “the tear-out provision did not cover the cost of accessing and replacing those pipes that were not leaking.”

    In September 2007, State Farm filed a motion to dismiss. The court rejected this motion, stating that “If Guadiana can establish as a matter of fact that the system that caused the covered loss included all the pipes in her house and it was necessary to replace all the pipes to repair that system, State Farm is obligated to pay the tear-out costs necessary to replace all the pipes, even those not leaking.”

    In March 2009, State Farm filed for summary judgment, which the court granted. State Farm argued that “the tear-out provision only applied to ‘repair’ and not ‘replace’ the system that caused the covered leak.” As for the rest of the piping, State Farm argued that “the policy does not cover defective materials.”

    In December 2011, Ms. Guadiana filed for summary judgment, asking the court to determine that “the policy ‘covers tear-out costs necessary to adequately repair the plumbing system, even if an adequate repair requires replacing all or part of the system.”

    In her ruling, Judge Edmonds noted that Ms. Guadiana’s claim is that “the water damage is a covered loss and she is entitled to tear-out costs necessary to repair the pluming system that caused that covered loss.” She rejected State Farm’s claim that it was not obligated to replace presumably defective pipes. Further, she rejected State Farm’s argument that they were only responsible for the leaking portion, noting “Guadiana intends to prove at trial that this is an unusual case where repair of her plumbing system requires replacement of all the PB plumbing.”

    Judge Edmonds concluded by directing the District Court to interpret the tear out issue as “the tear-out provision in State Farm’s policy requires State Farm to pay all tear-out costs necessary to repair the plumbing system (that caused the covered loss) even if repair of the system requires accessing more than the leaking portion of the system.”

    Read the court’s decision…


    Las Vegas Home Builder Still in Bankruptcy

    October 23, 2012 — CDJ Staff

    American West Development attempted to exit Chapter 11 bankruptcy on September 27, but their plan was turned down by U.S. Bankruptcy Court Judge Mike Nakagawa. According to the Las Vegas Review-Journal, Judge Nakagawa rejected the plan over a trust fund for construction defects. America West’s attorney said they were hoping to complete the process by the end of the year.

    Under approved portions of the plan, America West’s owner, Lawrence Canarelli, will retain control of the corporation, although he must contribute $10 million into the firm and an additional $1.5 million into the fund for construction defects. America West faces charges for construction defects reported in the broad range of “less than $20 million” to “as much as $80 million.”

    Read the full story…


    Was Jury Right in Negligent Construction Case?

    September 30, 2011 — CDJ Staff

    Yes, said the South Carolina Court of Appeals in Pope v. Heritage Communities, Inc. Heritage Communities developed Riverwalk, a community in South Carolina. During the earlier trial, HCI “conceded that construction defects existed at Riverwalk, and repairs needed to be made.” The trial court found that the construction was negligent, awarding the property owners association $4.25 million in actual damages and $250,000 in punitive damages, with the class of owners awarded $250,000 in actual damages and $750,000 in punitive damages. HCI appealed on nine issues. All were rejected by the appeals court.

    The court rejected HCI’s claim that the judge’s instruction to the jury suggested to the jury that “the court had already determined that Appellants were willful, wanton, and reckless.” But here, the appeals court found “no reversible error.”

    The general contractor for Riverwalk was BuildStar. Off-site management and sale were managed by Heritage Riverwalk, Inc., which also owned title to the property. Both these companies were owned by Heritage Communities, Inc. During the trial, an HCI employee testified that “the three corporations shared the same officers, directors, office, and telephone number.” The trial court found that the three entities were amalgamated. This was upheld by the appeals court.

    Nor did the appeals agree with the HCI that the trial court had improperly certified a class. The owners were seen as properly constituting a class. Further, the court held that the property owners’ losses were properly included by the trial court. HCI objected at trial to the inclusion of evidence of subsequent remedial measures, however, as they did not object that it was inadmissible, the issue could not be addressed at appeal.

    HCI argued on appeal that the trial court should not have allowed evidence of defects at other HCI developments. The appeals court noted that “the construction defects at the other HCI developments were substantially similar to those experienced by Riverwalk.”

    The court additionally found that the negligence claims, the estimated damages (since full damage could not be determined until all defective wood was removed), and the award of punitive damages were all properly applied.

    Read the court’s decision…


    Federal District Court Continues to Find Construction Defects do Not Arise From An Occurrence

    May 10, 2012 — CDJ Staff

    Coverage for construction defects continues to be hotly contested in Hawaii state and federal courts. In a recent decision, Judge Mollway felt bound to follow the Ninth Circuit’s decision in Burlington Ins. Co. v. Oceanic Design & Constr., Inc., 383 F.3d 940, 944 (9th Cir. 2004), where the court found construction defect claims arise from breach of contract, not from an occurrence. Judge Mollway’s most recent decision on the issue is Illinois Nat. Ins. Co. v. Nordic PCL Constr., Inc., 2012 U.S. Dist. LEXIS 58464 (D. Haw. April 26, 2012).

    Nordic constructed a grocery store for Safeway. In addition to the grocery store, Nordic built a 165-space rooftop parking deck, retail shops and related improvements. After opening for business in 2007, Safeway experienced significant leaks. Safeway demanded that Nordic repair the parking deck. Nordic sent the demand letter to the insurer, who agreed to appoint counsel subject to a reservation of rights.

    Safeway filed suit against Nordic in state court alleging, among other things, breach of contract and negligence. The insurer provided Nordic with a defense, but Nordic hired independent counsel.

    The insurer filed for declaratory relief in federal district court.

    Read the full story…


    New Construction Laws, New Forms in California

    July 10, 2012 — CDJ Staff

    New construction laws came into effect in California on July 1. Writing for the Martindale-Hubble Legal Library, Glenn Mau, J. Michael McGuire, and John Tonsing, all of Archer Norris, discuss these changes. They note that the most important part of the changes to California construction law is that “all mechanics liens, stop notices and bond claims recorded after July 1, 2012 must use the new standardized forms and follow the new definitions, notice prerequisites and statutory release form language.”

    Read the full story…


    Certificate of Merit to Sue Architects or Engineers Bill Proposed

    May 3, 2011 — May 3, 2011 Beverley BevenFlorez - Construction Defect Journal

    North Carolina may become the twelfth state to require a Certificate of Merit to sue an architect or engineer. If North Carolina Senate Bill 435 (SB435) passes, then plaintiffs when filing a complaint will need to also attach an affidavit of a third-party licensed professional engineer or architect stating that the case has merit.

    SB435 is a short two pages in its current form. The bill states that the “third-party licensed professional engineer or licensed architect shall (i) be competent to testify and hold the same professional license and practice in the same area of practice as the defendant design professional and (ii) offer testimony based upon knowledge, skill, experience, education, training, and practice. The affidavit shall specifically state for each theory of recovery for which damages are sought, the negligence, if any, or other action, error, or omission of the design professional in providing the professional service, including any error or omission in providing advice, judgment, opinion, or a similar professional skill claimed to exist and the factual basis for each such claim. The third-party licensed professional engineer or licensed architect shall be licensed in this State and actively engaged in the practice of engineering or architecture respectively.”

    A few of the amendments allude to disciplining design professionals who certify civil actions that are without merit. The bill has been referred to the Committee on Judiciary I.

    While North Carolina is considering enacting a Certificate of Merit law, eleven other states already require one, including Arizona, California, Colorado, Georgia, Maryland, Minnesota, New Jersey, Oregon, Pennsylvania, South Carolina, and Texas. Christopher D. Montez, a partner with Thomas, Feldman & Wilshusen, LLP, has written a useful summary for each state’s certificate of merit scheme.

    Read the text of SB435

    Track the progress of SB435

    Read more from Christopher D. Montez’s article on Thomas, Feldman & Wilshusen, LLP site


    Construction Defects and Contractor-Owners

    July 10, 2012 — CDJ Staff

    On the expert advice site Avvo.com, a user asks if he can be sued for construction defects by the new owner of a building for which he served as general contractor and then owned for four years. He had construction insurance, but does not think he had construction defect insurance.

    A lawyer responding to his question says that “you could be sued.” In the event of a suit, “you would have to bring claims against all of your subcontractors.”

    Read the full story…


    The Year 2010 In Review: Design And Construction Defects Litigation

    February 25, 2011 — Candace Matson, Harold Hamersmith, and Helen Lauderdale - Construction & Infrastructure Law Blog - February 25, 2011

    This article is the first in a series summarizing construction law developments for 2010

    1. Centex Homes v. Financial Pacific Life Insurance Co., 2010 U.S. Dist. LEXIS 1995 (E.D. Cal. 2010)

    After settling numerous homeowners’ construction defect claims — and more than ten years after the homes were substantially completed — a home developer brought suit against one of the concrete fabrication subcontractors for the development seeking indemnity for amounts paid to the homeowners, as well as for damages for breach of the subcontractor’s duties to procure specific insurance and to defend the developer against the homeowners’ claims. The subcontractor brought a motion for summary adjudication on the ground the developer’s claims were barred by the ten year statute of repose contained in Code of Civil Procedure Section 337.15.

    The District Court agreed the developer’s claim for indemnity was barred by Section 337.15. And it held that because the damages recoverable for breach of the subcontractor’s duty to purchase insurance are identical to the damages recoverable through the developer’s indemnity claim, the breach of duty to procure insurance claim also was time-barred. The District Court, however, allowed the claim for breach of the duty to defend to proceed. The categories of losses associated with such a claim (attorneys’ fees and other defense costs) are distinct from the damages recoverable through claims governed by Section 337.15 (latent deficiency in the design and construction of the homes and injury to property arising out of the latent deficiencies).

    2. UDC — Universal Development v. CH2M Hill, 181 Cal. App. 4th 10 (6th Dist. Jan. 2010)

    Indemnification clauses in construction agreements often state that one party to the agreement — the “indemnitor” — will defend and indemnify the other party from particular types of claims. Of course, having a contract right to a defense is not the same as actually receiving a defense. Any indemnitor attempting to avoid paying for defense costs can simply deny the tender of defense with the hope that when the underlying claim is resolved the defense obligations will be forgotten. In the past, when parties entitled to a defense — the “indemnitees” — had long memories and pressed to recover defense costs, indemnitors attempted to justify denying the tender by claiming their defense obligations coincided with their indemnity obligations and neither arose until a final determination was made that the underlying claim was one for which indemnity was owed.

    Read the full story...

    Reprinted courtesy of Candace Matson, Harold Hamersmith, and Helen Lauderdale, Sheppard Mullin Richter & Hampton LLP. Ms. Matson can be contacted at cmatson@sheppardmullin.com, Mr. Hamersmith can be contacted at hhamersmith@sheppardmullin.com, and Ms. Lauderdale can be contacted at hlauderdale@sheppardmullin.com.


    CC&Rs Not the Place for Arbitration Agreement, Court Rules

    May 24, 2011 — CDJ Staff

    In January, the California Court of Appeals ruled that an arbitration clause inserted in a development’s CC&Rs by the developer could not be enforced. The case, Villa Vicenza Homeowners Association v. Noble Court Development, involved a case in which, according to the opinion, “following the first sale Nobel controlled the board of directors of the Association and because the initial condominium buyers noticed defects in common areas and common facilities and did not believe Nobel had provided a reserve fund sufficient to repair the defects, the condominium owners brought a derivative action on behalf of the Association against Nobel.”

    The court concluded, “The use of CC&R's as a means of providing contractual rights to parties with no interest in or responsibility for a common interest development is also problematic from the standpoint of determining what if any consideration would support such third-party agreements. By their terms the CC&R's bind all successors, even those with whom a third party such as Nobel has never had any contractual relationship and to whom Nobel has not provided any consideration.” The court determined that “the trial court did not err in denying Nobel's motion to compel arbitration.”

    Read the court’s decision


    Important Information Regarding Colorado Mechanic’s Lien Rights.

    November 7, 2012 — David McLain, Colorado Construction Litigation

    With payment problems in the construction economy having accelerated over the past few years, there has been a substantial increase in mechanic’s lien activity and associated litigation. The typical mechanic’s lien claimant is a material supplier, a trade subcontractor, or even a general contractor that has not been paid by the developer/owner of the construction project. The reason for filing a mechanic’s lien claim is that it offers the prospect in many cases to make the unpaid construction professional a priority creditor, with a lien on the real estate that is superior to the construction lender.

    One of the primary rules governing a mechanic’s lien claim is that the creditor’s formal written “Notice of Intent to File a Mechanic’s Lien” (hereafter “Lien Notice”) must be (1) served on the owner of the property for which the work was done or the materials used, and (2) served at the same time on the general contractor who has handled the construction project. After the creditor has made service of the lien claim by USPS certified mail (using the green return receipt card for proof of service) or separate personal delivery of the notice to the property owner and general contractor, ten full days must pass (not including the date of mailing of the notices) before the lien notice is filed in the public records.

    After ten days have expired following the date of mailing using certified mail, or personal delivery of the notice to the property owner and the general contractor, the lien notice can be filed to make the lien valid.

    Reprinted courtesy of David M. McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com