Construction Employment Rises in Half of the States
December 9, 2011 — CDJ Staff
The Labor Department has noted that half the states and the District of Columbia saw increases in construction employment during the month of October. During the same month, twenty-three states lost construction jobs.
The biggest gains were in North Dakota, Oklahoma, DC, Texas, and California. The biggest losses were in Georgia, New Mexico, Wisconsin, and Florida. There was no change for Alabama.
The chief executive officer of the Association of General Contractors of America, Stephen E. Sandherr, called for more infrastructure development. “Allowing water, transportation and energy networks to deteriorate will hurt construction employment and force taxpayers to spend more later, to fix broken infrastructure.”
Read the full story…
Residential Construction: Shrinking Now, Growing Later?
August 17, 2011 — CDJ Staff
Jim Haugey, the Chief Economist for Reed Construction Data noted that new residential construction spending fell 0.2% in June and a slightly larger drop of 0.5% in residential remodeling. While economic growth is still low, Haugey states that homebuilders have “record low inventories.” He forecasts a shrinkage of 1.5% in 2011, followed by about 20% growth in 2012.
Read the full story…
Exclusion Bars Coverage for Mold, Fungus
October 23, 2012 — Tred Eyerly, Insurance Law Hawaii
The court considered whether rain damage to a house was barred by the policy's mold exclusion. Stewart v. State Farm Fire & Cas. Co., 2012 U.S. Dist LEXIS 127804 (D. S.D. Sept. 7, 2012).
The insureds hired DJ Construction to build a new home. Before construction was completed, it was discovered that DJ Construction and some of its subcontractors had failed to protect the partially constructed house from the elements, which allowed melting snow and rain to intrude into the house. Soon after this discovery, DJ Construction abandoned the project. The house remained incomplete and uninhabitable.
The insureds sued DJ Construction.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Limiting Plaintiffs’ Claims to a Cause of Action for Violation of SB-800
November 18, 2011 — Samir R. Patel, Esq. and Todd E. Verbick, Esq., Lorber, Greenfield & Polito, LLP
There has been a fair share of publicity about the SB-800 amendments to the Civil Code (Civil Code section 896, et seq.) that codified construction defect litigation in 2002. Most of the publicity is geared toward the pre-litigation standards allowing a builder the right to repair before litigation is commenced by a homeowner. Less focus and attention has been given to the fact that violation of the SB-800 performance standards is being used by plaintiff’s counsel as an additional tool in the plaintiff’s pleading tool box against builders. Closer scrutiny to SB-800 reveals that those provisions should in fact act as a limitation to the pleading tools available to plaintiffs and an additional tool for builders in the defense of cases governed by SB-800.
The typical construction defect complaint contains the boiler plate versions of numerous causes of action. These causes of action include Strict Liability, Negligence, Negligence Per Se, Breach of Contract, Breach of Contract – Third-Party Beneficiary, Breach of Express Warranties, Breach of Implied Warranties, among others. The wide array of causes of action leave a defendant “pinned to the wall” because they require a complex defense on a multitude of contract and tort related causes of action. Furthermore, the statutes of limitations as to these claims widely differ depending upon if the particular defect is considered latent or patent. The truth of the matter remains, no matter what the circumstances, if a construction defect matter ultimately goes to trial, it is inevitable that plaintiffs will obtain a judgment on at least one of these causes of action.
On its own, the Strict Liability cause of action can be a thorn in a defendant’s side. A builder is obviously placing a product into the stream of commerce and strict liability is a tough standard to defend against, particularly when it concerns intricate homes comprised of multiple components that originally sold for hundreds of thousands of dollars. A Negligence cause of action can also be difficult to defend because the duty of care for a builder is what a “reasonable” builder would have done under the circumstances. An interpretation of this duty of care can easily sway a jury that will almost always consist of sympathetic homeowners. A Negligence Per Se cause of action can also leave a defendant vulnerable to accusations that a builder violated the Uniform Building Code or a multitude of other obscure municipal construction-related code provisions during the construction of the home. Lastly, the Breach of Contract cause of action leaves a builder relying on dense and intricate purchase and sale agreements with dozens of addenda which leave the skeptical jurors turned off by what they view as one-side, boilerplate provisions. Ultimately, when a matter is about to go to trial, the complexity of these complaints can benefit a plaintiff and increase a plaintiff’s bargaining power against a defendant who is attempting to avoid a potentially large judgment.
Enter the SB-800 statutes. The SB-800 statutes apply to all homes sold after January 1, 2003. Civil Code section 938 specifically states that “[t]his title applies only to new residential units where the purchase agreements with the buyer was signed by the seller on or after January 1, 2003.” (Civil Code §, 938.) As time progresses, more residential construction defect cases will exclusively fall under the purview of SB-800. Slowly but surely more SB-800 governed litigation is being filed, and its exclusive application is looming on the horizon.
On its surface, this “right to repair” regime has left builders with a lot to be desired despite the fact that it is supposed to allow the builder the opportunity to cure any deficiencies in their product before litigation can be filed by potential plaintiffs. However, the application of the time line for repair has shown to be impractical for anything but the most minor problems involving only small numbers of residential units. Moreover, the fact that the fruits of the builder’s investigation into the claimed defects in the pre-litigation context can freely be used as evidence against it in litigation makes builders proceed with trepidation in responding with a repair. For these reasons, more SB-800 litigation can be expected to result due to the shortcomings of the pre-litigation procedures, and savvy defense counsel should anticipate the issues to be dealt with in presenting the defense of such cases at trial.
This fact should not necessarily be met with fear or disdain. Within the SB-800 statutes, the legislature made it clear that they were creating a new cause of action for construction defect claims, but it further made it clear that this cause of action is a plaintiff’s exclusive remedy. The legislature giveth, but at the same time, the legislature taketh away. Throughout numerous provisions within the SB-800 statutes, the Civil Code states that claims for construction defects as to residential construction are exclusively governed by the Civil Code, and that the Civil Code governs any and all litigation arising under breaches of these provisions. Civil Code section 896 specifically states:
In any action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction … the claimant’s claims or causes of action shall be limited to violation of, the following standards, except as specifically set forth in this title. (Civil Code §, 896.)
Civil Code section 896 then provides approximately fifty-plus standards by which a construction defect claim is assessed under that provision. Civil Code section 896 covers everything from plumbing to windows, and from foundations to decks, and in several instances expressly dictates statutes of limitations as to specific areas of construction that severely truncate the 10-year latent damage limitations period. As for any construction deficiencies that are not enumerated within Civil Code section 896, Civil Code section 897 explicitly defines the intent of the standards and provides a method to assess deficiencies that are not addressed in Civil Code section 896. Civil Code section 897 states:
Intent of Standards
The standards set forth in this chapter are intended to address every function or component of a structure. To the extent that a function or component of a structure is not addressed by these standards, it shall be actionable if it causes damage. (Civil Code §, 897.)
Therefore, Civil Code section 897 acts as a catch-all by which defects that are not covered within Civil Code section 896 can be evaluated on a damage standard mirroring the Aas case (damages must be present and actual). The result of sections 896 and 897 being read in combination is a comprehensive, all-inclusive set of performance standards by which any defect raised by Plaintiffs can be evaluated and resolved under a single SB-800 based cause of action.
Civil Code section 943 makes clear that a cause of action for violation of SB-800 performance standards is a plaintiff’s sole remedy for a residential construction defect action. Specifically, Civil Code section 943 states:
Except as provided in this title, no other cause of action for a claim covered by this title or for damages recoverable under 944 is allowed. In addition to the rights under this title, this title does not apply to any action by a claimant to enforce a contract or express contractual provision, or any action for fraud, personal injury, or violation of a statute. (Civil Code §, 943.)
Civil Code section 944 provides the method for computing damages within a construction defect action, as follows:
If a claim for damages is made under this title, the homeowner is only entitled to damages for the reasonable value of repairing any violation of the standards set forth in this title, [and] the reasonable cost of repairing any damages caused by the repair efforts… . (Civil Code §, 944.)
A cursory review of these statutes yields the conclusion that the legislature was attempting to create an exclusive cause of action that trumps all other causes of action where SB-800 applies. The remedy available to plaintiffs is limited to that allowed by the Civil Code. As noted above, “[n]o other cause of action for a claim covered by this title…is allowed.” (Civil Code §, 943.) Therefore, Civil Code sections 896, 897, 943, and 944 specifically prohibit the contract-based and tort-based causes of action typically pled by plaintiffs.
Plaintiff’s counsel has seized upon the language of section 943 to advance the argument that SB-800 still allows a plaintiff to advance typical contract and tort based causes of action. On the surface, this argument may seem compelling, but a minimum of scrutiny of the express language of section 943 dispels this notion. Section 943 says that it provides rights “[i]n addition” to those under the SB-800 Civil Code provisions. Clearly, the language in section 943 is intended to expressly underscore the fact that a plaintiff is not precluded from seeking relief in addition to that allowed under SB-800 for damages not arising from a breach of the SB-800 standards or for damages in addition to those recoverable under Section 944. This language does not provide an unfettered license to bring a Strict Liability, Negligence or other cause of action against a builder where SB-800 applies.
In fact, this language only keeps the door open for plaintiffs to pursue such causes of action not arising from a breach of the SB-800 standards should there be such supporting allegations. For example, if a plaintiff alleges that a builder breached an “express contractual provision” related to the timing of the completion of the home and close of escrow, and the contract specifies damages in this regard, a plaintiff may have a viable separate cause of action for Breach of Contract for recovery of those damages precisely because that is not an issue expressly dealt with in SB-800 in the performance standards under sections 896 and 897, or in the damage recovery terms under 944. As it stands, the vast majority of complaints are seeking redress for violation of the same primary right; that is, defects specifically outlined in Section 896 and 897 or which result in damages as stated in Section 944.
So, how does a builder defend against a complaint that contains multiple causes of action regarding construction defects for a home sold after January 1, 2003? There are numerous ways to approach this. First and foremost, these superfluous and improper causes of action can be attacked by demurrer seeking dismissal of all causes of action other than the cause of action alleging violation of SB-800. If the the time period within which to file a demurrer has passed already, a motion for judgment on the pleadings can be utilized to attack the improper causes of action in the same way as a demurrer can be used for this purpose.
The limitation to a demurrer or motion for judgment on the pleadings is that the judge is restricted to viewing only the four corners of the pleading when making a ruling. It is typical for plaintiffs’ counsel to cleverly (or one might even say, disingenuously) leave the complaint purposely vague to avoid a successful defense attack on the pleadings by not including the original date the residence was sold. In that instance, a motion for summary adjudication can be used to attack a plaintiff’s complaint. By simply providing evidence that the homes were originally sold after January 1, 2003, the improper causes of action should be subject to dismissal by summary adjudication. If the plaintiff is a subsequent purchaser, the builder still has recourse to enforce the pleading limitations under SB-800. Civil Code section 945 states that “[t]he provisions, standards, rights, and obligations set forth in this title are binding upon all original purchasers and their successors-in-interest.” (Civil Code §, 945.)
Attacking a plaintiff’s complaint to eliminate multiple causes of action can have numerous benefits. The practical result is that a plaintiff will only have one viable cause of action. The advantage is that the SB-800 performance standards include the defined performance standards and shortened statutes of limitations periods with regard to specific issues. Furthermore, as to defects which are not specifically provided for in Civil Code section 896, Civil Code section 897 requires a proof of actual damages. Therefore, a plaintiff must provide evidence of current damages and not simply conditions that may potentially cause damage in the future.
The Appellate Courts have yet to directly address and interpret these SB-800 provisions. The time for that is undoubtedly drawing near. For now, however, plaintiffs will have to find ways to accurately plead construction defect claims within the confines of one cause of action for breach of the performance standards enumerated within the Civil Code.
Printed courtesy of Lorber, Greenfield & Polito, LLP. Mr. Patel can be contacted at spatel@lorberlaw.com and Mr. Verbick at tverbick@lorberlaw.com.
Brown Paint Doesn’t Cover Up Construction Defects
April 25, 2012 — CDJ Staff
In a decision that describes the case as illustrating “the perils that real estate brokers and their agents assume when acting as a dual listing agent to both the buyers and sellers of the same house,” the California Court of Appeals has issued a decision in William L. Lyon & Associates v. The Superior Court of Placer County. Lyon & Associates sought summary judgment to dismiss the claims of the Henleys who bought a home in a transaction where a Lyon agent represented both sides.
The prior owners of the home, the Costas, had used a Lyon agent in purchasing their home. When they later sought to sell it, that agent “became aware of some of the house’s defects and problems.” In response, the Costas sought the help of another agent, Connie Gidal, also of Lyons & Associates. Photos taken in the presence of Ms. Gidal show defects of the paint and stucco. The Costas also took the step of painting the house dark brown. During the sale process, “rain caused many of the painted-over defects to reappear.” The Costas “purchased more dark brown paint and covered up the newly visible damage prior to inspection by the Henleys.”
With the damage concealed, the Henleys bought the home in May 2006. The agreement with Lyons & Associates noted that “a dual agent is obligated to disclose known facts materially affecting the value or desirability of the property to both parties.” Escrow closed on May 9, 2006. The contract with the broker included a two-year limit on the time to bring legal action.
The Henleys moved in during June 2006, and “began to discover construction defects that had been concealed by the Costas.” In addition to the painted-over stucco problems, the Henleys found that the Costas had “installed quartzite stone overlays on the backyard steps in a manner that caused water intrusion on the house’s stucco walls.”
In May 2009, the Henleys sued the Costas, Ron McKim Construction, Lyons & Associates, and Ms. Gidal. Their complaint alleged that Lyons & Associates had committed breach of contact, negligence, fraud, breach of fiduciary duty, and negligent nondisclosure in connection with the construction defects. The Costas named Lyons in a cross complaint. Lyons moved for summary judgments on the grounds that the two-year statute of limitations had expired before the complaint and cross-complaint were filed. Both the Henleys and the Costas opposed this claim. The court denied the motion and Lyons appealed.
The appeals court upheld the denial, noting that the both California Supreme Court decision and later action by the legislature compels real estate brokers and salespersons “to conduct a reasonably competent and diligent visual inspection of the property offered for sale.” The court noted that under California law, brokers have responsibilities to both sellers and buyers. The section of law cited by Lyons applies to seller’s agents. The court rejected the contention by Lyons that they were “cooperating brokers.” The Henleys were “not constrained by the two-year statute of limitations.”
Lyons contended that even if California’s statute did not apply, there was a contractual limit of two years. The court also rejected this, agreeing with the Henleys that “the two-year limitation period must be extended by the discovery rule.”
The court noted that “Lyon & Associates may not reap the benefit of a shortened contractual limitation period when its own alleged malfeasance contributed to the delay in the discovery of the buyer’s injury.” The court found that the Henleys could proceed with their breach of contract claim, because, “when a breach of contract is committed in secret, such as the intentional nondisclosure of a real estate broker regarding a previously visible construction defect, the contractual limitations period is properly held subject to the discovery rule.” The court felt that the interpretation favored by the California Association of Realtors would “halve the applicable statute of limitations period.”
In addition to rejecting Lyon request for summary judgment on the claims made by the Henleys, the court also rejected the request of summary judgment on the claims made by the Costas, concluding that neither claim is time-barred. Costs were awarded to both the Henleys and Costas.
Read the court’s decision…
Insurer’s Motion for Summary Judgment Based on Earth Movement Exclusion Denied
October 28, 2011 — Tred Eyerley, Insurance Law Hawaii
After carefully dissecting the earth movement exclusion, the court denied the insurer’s motion for summary judgment. High Street Lofts Condominium Assoc., Inc. v. Am. Family Mut. Ins. Co., 2011 U.S. Dist. LEXIS 109043 (D. Colo. Sept. 26, 2011).
The City of Boulder performed road repair work near High Street’s property, some of which involved the use of a vibrating compactor to compact and set the roadbed. High Street noticed damage to its building, such as cracks in walls, sloping of floors and separations of porches from the building itself. High Street contacted the City of Boulder, who forwarded the complaint to its contractor, Concrete Express, Inc.
High Street also filed a claim with its business insurer, American Family, who denied the claim. American Family relied on an opinion letter by High Street’s engineer. The letter indicated that the damage was the result of "soil consolidation/settlement," in response to the construction activities. Based on this letter American Family concluded the claim was excluded under the policy’s earth movement exclusion.
High Street sued American Family, who moved for summary judgment.
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Gut Feeling Does Not Disqualify Expert Opinion
July 6, 2011 — CDJ Staff
The New Jersey Supreme Court issued a ruling in June on the case of Nevins v. Toll in which they reversed an earlier decision and remanded the case to a lower court for retrial. At issue in the case was the testimony of the plaintiff’s expert, J. Anthony Dowling. In depositions, Mr. Dowling said that his estimates for repair were based on a “gut feeling.” Dowling said he had “very little” experience in cost estimates for single-family homes. The defendants sought to bar Dowling’s testimony which was granted by the judge. Without an expert, Ms. Nevin’s case was dismissed.
Describing Dowling’s report as “far from a model of how an expert’s opinion in a construction case should be presented,” the court noted that Dowling is not a professional expert witness. However, the court did note that Dowling is a professional cost estimator. Despite Mr. Dowling using his “gut feeling” to construct his estimate, the New Jersey Supreme Court felt that whether his estimate is convincing is “a question for the jury.”
Read the court’s opinion…
Don MacGregor To Speak at 2011 West Coast Casualty Construction Defect Seminar
January 1, 2011 — February 08, 2011 CDJ Staff
“Challenges for Experts in Construction Defect Claims and Litigation” will be held Thursday May 13, 2011 between 1:30 and 3:00 PM at this year’s West Coast Casualty Construction Defect Seminar. Among the various topics covered will be of Right to Repair/Opportunity to Repair statutes, improper testing methodologies, new challenges where a case involves a Wrap Policy, OCIPS, CCIPS, and other owner controlled insurance programs, as well as the need for realistic testing protocols for the party the expert is retained to represent.
During the presentation Mr. MacGregor will be working in connection with a group of construction and design experts each of which have extensive experience with construction defect and claims related litigation. This particular session is expected to attract a standing-room only crowd, drawing in excess of 1700 attendees.
The West Coast Casualty Construction Defect Seminar is the largest seminar of its type. This year’s event is scheduled for will take place on May 12 and 13, 2011, at The Disneyland Hotel and Resort. For more information regarding the years event please visit http://www.westcoastcasualty.com/dyncat.cfm?catid=3322
http://www.westcoastcasualty.com/dyncat.cfm?catid=3322
Excess Carrier Successfully Appeals Primary Insurer’s Summary Judgment Award
December 9, 2011 — Tred R. Eyerly, Insurance Law Hawaii
Although the excess carrier was given inadequate notice of the underlying arbitration, the trial court determined it shared responsibility with the primary carrier for the arbitration award. Finding disputed issues of fact, the Washington Court of Appeals reversed in Am. States Ins. Co. v. Century Surety Co., 2011 Wash. App. LEXIS 2488 (Wash. Ct. App. Oct. 31, 2011).
The primary insurer, American States, issued two liability policies to Professional Home Builders (PHB), a siding contractor. The policies were for successive years, 1998-1999 and 1999-2000. Each policy had annual limits of $1 million per occurrence. PHB also had a commercial excess liability policy for 1999-2000 with Century Surety Company.
PHB was sued by Residential Investment Partners (RIP) for construction defects after moisture entered the building envelope, causing decay and damage. Century’s expert determined the decay started before the 1999-2000 policy period.
RIP and PHB went to arbitration.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Construction Defect Not an Occurrence in Ohio
November 7, 2012 — CDJ Staff
The Ohio Supreme Court has concluded that claims of defective construction or workmanship are not an occurrence under a general liability policy. The court looked at appellate decisions and concluded that CGL policies are not intended to insure against risks under the control and management of the insured. These risks should instead be mitigated with performance bonds.
The question was raised in the case Westfield Ins. Co. v. Custom Agri Systems, Inc. The Sixth District Court of Ohio concluded it was an “open question under Ohio law whether a CGL policy covers defective construction claims.” Westfield filed a motion, granted by the Sixth Circuit, to certify the question to the state Supreme Court. The Sixth Court additionally found that the contractual liability exclusion barred coverage in the case, issues a summary judgment to Westfield.
Read the full story…
Official Tried to Influence Judge against Shortchanged Subcontractor
February 10, 2012 — CDJ Staff
A contractor testified in the trial of former Cuyahoga County Commissioner Jimmy Dimora. According to Fox 8 in Cleveland, Ohio, Sean Newman, the president of Letter Perfect testified that his company was a subcontractor on the reconstruction of the locker rooms at the Cleveland Browns Stadium. Newman said his company was paid only $400,000 of their $650,000 bid. When Letter Perfect sued the contractor, D.A.S. Construction, Dimora called the judge to influence her to rule in favor of D.A.S.
The judge in the earlier case, Bridgett McCafferty, has been found guilty of lying to the FBI during their investigation and is serving a 14-month prison sentence.
Read the full story…
Architect Not Liable for Balcony’s Collapse
September 13, 2012 — CDJ Staff
The Texas Supreme Court declined to hear an appeal from a woman who was partially paralyzed due to the collapse of a balcony. She had sued the architect of her friends’ home, but the Texas Third Circuit Court of Appeals had reversed a jury ruling against the architect, Sinclair Black. Black’s firm, Black + Vernooy, had designed the home and had supervised “administration of the construction contract.” Despite a contractual obligation to “endeavor to guard the owner against defects and deficiencies,” the balcony builder had not followed the architect’s specifications, including in the construction of the balcony.
While the jury found Black liable for ten percent of the blame, Black argued that he could not be held liable for the contractor’s negligence, nor did he have any duty to third parties.
Read the full story…
The Flood Insurance Reform Act May be Extended to 2016
April 7, 2011 — April 7, 2011 Beverley BevenFlorez - Construction Defect Journal
The Flood Insurance Reform Act of 2011 (H. R. 1309) has been referred to the House Committee on Financial Services—the first step in the legislative process. The bill, if passed, would extend the program to September 30, 2016. It is currently slated to be terminated September 30 of this year. The bill also contains changes to premium rates, mapping protocols, and privatization initiatives.
H. R. 1309 has garnered the support of several Insurance organizations. Leigh Ann Pusey, president and CEO of the American Insurance Association (AIA), sent a letter of support to the Chair and Ranking member of the House Financial Services Subcommittee. “AIA has advocated for a long term reauthorization of the NFIP to protect consumers and help increase stability for real estate transactions and policyholders,” Pusey said. “AIA believes the five-year extension contained in HR 1309, will provide certainty in the flood program thereby increasing consumer and business confidence in the NFIP.”
Jimi Grande, senior vice president of federal and political affairs for the National Association of Mutual Insurance Companies (NAMIC) spoke out in support of the bill. “For the NFIP to survive, the prices for flood insurance must reflect the actual costs of flood risk for a property,” Grande said. “HR 1309 will provide that transparency. In addition, the Technical Mapping Advisory Council will give communities a voice in the flood mapping process, fostering a better understanding of what flood maps represent and how they are made.”
Read H. R. 1309...
Read the American Insurance Association statement...
Read the NAMIC Press Release...
Anti-Assignment Provision Unenforceable in Kentucky
December 20, 2012 — Tred Eyerly, Insurance Law Hawaii
On a certified question from the Federal District Court, the Supreme Court of Kentucky decided that an anti-assignment provision in a policy is unenforceable.Wehr Constructors v. Paducah Div. Assur. Co. of Am., 2012 Ky. LEXIS 183 (Ky. Oct. 25, 2012).
Before building an addition to its hospital, Murray Calloway County Hospital purchased a builder's risk policy from Assurance Company of America.The policy provided, "Your rights and duties under this policy may not be transferred without Assurance's written consent . . . ." The Hospital contracted with Wehr Constructors to install concrete subsurfaces and vinyl floors in order to expand the hospital. After installation, a portion of the floors and subsurface work was damaged. The Hospital submitted a claim to Assurance for $75,000, but the claim was denied.
Wehr sued the Hospital to recover money for its work on the construction project. In settling the case, the Hospital assigned to Wehr any claim or rights the Hospital had against Assurance.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
General Contractors Must Plan to Limit Liability for Subcontractor Injury
May 18, 2011 — May 18, 2011 - Douglas Reiser in the Builders Counsel Blog
It takes more than a hard hat, but safety checks, a good policy and a smart contract might save you some problems.If you are a general contractor, you will want to pay close attention to this article. A new Washington appellate decision showcases a general contractor’s liability to subcontractors who are injured on the job, when security barriers fail. But can a general limit this liability? Will its contract help?
In Wrought Corporation, Inc., Appellant V. Mario Interiano (quick note: this opinion is unpublished, but we are here to talk about an issue that was not determined on appeal – WISHA compliance), a subcontractor was injured when a security barrier failed and he fell into an elevator shaft.
A jury awarded a $1.56 million verdict against the general contractor, and the court of appeals affirmed on the basis that the general contractor has a non-delegable duty to ensure compliance with the Washington Industrial Safety and Health Act of 1973, codified under RCW 49.17 (WISHA).
Read the full story… Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Ohio Adopts Energy-Efficient Building Code
June 19, 2012 — CDJ Staff
In a compromise between environmental groups, who were looking for stricter standards, and homebuilders, who were trying to contain building costs, the state of Ohio has adopted buildings codes that will increase the energy efficiency of new homes. The estimated costs are about $1,100 with estimated annual savings of $230. According to Corey Roblee of the International Code Council, “It’s something needed in the state of Ohio.”
The Ohio Home Builders Association opposed a proposal to adopt the guidelines of the International Code Council. Builders will be able to either follow the ICC guidelines or they can use the Ohio guidelines to meet the same energy efficiency. Vincent Squillace, the executive vice president of the OHBA, said, “We came up with an equivalent code that’s more strict but is about $2,000 cheaper per home to implement than the original code.”
The new code will require that at least 75% of lighting must be high efficiency, increases the degree of insulation, and specifies more efficient windows, among other changes.
Read the full story…
Washington Court of Appeals Upholds Standard of Repose in Fruit Warehouse Case
August 4, 2011 — CDJ Staff
On July 28, the Washington Court of Appeals ruled in Clasen Fruit & Cold Storage v. Frederick & Michael Construction Co., Inc. that more than six years had passed since a contractor had concluded work and so granted a summary dismissal of the suit.
Frederick & Michael Construction Co., Inc. (F&M) was contracted to construct several buildings for Clasen Fruit and Cold Storage. These were completed in March, 1999. The buildings suffered wind damage to the roofs in 2001, 2003, 2005, and 2006. In the first two incidents, F&M repaired the roofs with Clasen paying for repairs.
In 2005, Clasen hired Continuous Gutter to make repairs. The final incident was the collapse of the roof of one building. This was attributed to “excessive moisture in the roof’s vapor barriers.” At this point, Clasen demanded that F&M pay for repair and replacement costs. In 2008, Clasen sued F&M for damages for breach of contract and negligent design and construction of the roof.
The decision then covered the meanings, in Washington law, of “termination of services” and “substantial completion.” The panel concluded that construction was “substantially completed in 1997” and “relevant services” by 2001. “But Clasen did not sue until 2008, some seven years after termination of any roof related services.”
Read the court’s decision…
Appeals Court Reverses Summary Judgment over Defective Archway Construction
February 10, 2012 — CDJ Staff
A judge has ruled that a plaintiff can go forward with her suit that she was injured by a defective archway during a birthday party. A three-judge panel of the California Court of Appeals issued this ruling on January 23, 2012, in the case of Trujillo v. Cosio.
Ms. Trujillo attended a birthday party at the home of Maria Cosio and Joel Verduzco. A piñata was hung between a tree and a brick archway. Ms. Trujillo went to get candy that had fallen from the piñata, during which the archway fell on her hand. Subsequent examination of the archway showed that it had not been “properly anchored to the supporting pillars to protect the arch from falling.”
Ms. Cosio and Mr. Verduzco argued that they could not have been aware of the defective nature of the archway’s construction, as it had been built at the request of the prior property owner. The structure was constructed without building permits. Mark Burns, a civil engineer testifying for the plaintiff, said that “a reasonable property owner would have thoroughly tested the archway to ensure it was capable of withstanding such horizontal forces before allowing children to enter into the area.” Mr. Burns noted that twenty rope pulls would have been sufficient to demonstrate the structure’s instability.
The trial court rejected Mr. Burn’s statements, finding that the respondents did not have any knowledge of the defect and that a visual inspection should have sufficed. The court noted that this a triable issue, whether visual inspection suffices, or whether the property owners should have done as Mr. Burns suggested and yank a rope twenty times. The court noted that “although a jury may ultimately disagree with Burn’s opinion, it was supported by sufficient foundation and was not speculative.”
The opinion was written by Judge Flier, with Judges Rubin and Grimes concurring.
Read the court’s decison…