BERT HOWE
  • Nationwide: (800) 482-1822    
    parking structure Wakefield Rhode Island office building Wakefield Rhode Island institutional building Wakefield Rhode Island housing Wakefield Rhode Island custom home Wakefield Rhode Island custom homes Wakefield Rhode Island hospital construction Wakefield Rhode Island mid-rise construction Wakefield Rhode Island production housing Wakefield Rhode Island townhome construction Wakefield Rhode Island concrete tilt-up Wakefield Rhode Island condominium Wakefield Rhode Island casino resort Wakefield Rhode Island Medical building Wakefield Rhode Island Subterranean parking Wakefield Rhode Island condominiums Wakefield Rhode Island tract home Wakefield Rhode Island high-rise construction Wakefield Rhode Island landscaping construction Wakefield Rhode Island retail construction Wakefield Rhode Island industrial building Wakefield Rhode Island structural steel construction Wakefield Rhode Island
    Arrange No Cost Consultation
    Construction Expert Witness Builders Information
    Wakefield, Rhode Island

    Rhode Island Builders Right To Repair Current Law Summary:

    Current Law Summary: (Title 5 Chapter 5-20.8 Real Estate Sales Disclosures Section 5-20.8-4 Buyer's Rights(b)(2) Existing law provides that seller must have the opportunity to cure deficient conditions and that buyer must provide seller with a report of inspection performed by a recognized and reputable inspector or inspection company within seven calendar days and seller has seven days to respond. The remedy for seller not agreeing to cure the deficiency is termination of the transfer agreement.


    Construction Expert Witness Contractors Licensing
    Guidelines Wakefield Rhode Island

    A contractor's license is required for work on one to four-family dwellings. Licenses are required for electrical, plumbing, and mechanical work.


    Construction Expert Witness Contractors Building Industry
    Association Directory
    Rhode Island Builders Association
    Local # 4105
    450 Veterans Memorial Pkwy Suite 301
    East Providence, RI 02914
    http://www.ribuilders.org


    Construction Expert Witness News and Information
    For Wakefield Rhode Island

    Court Rules on a Long List of Motions in Illinois National Insurance Co v Nordic PCL

    Know the Minnesota Statute of Limitations for Construction Defect Claims

    Exact Dates Not Needed for Construction Defect Insurance Claim

    Construction Suit Ends with Just an Apology

    Exclusion Bars Coverage for Mold, Fungus

    Contractor’s Coverage For Additional Insured Established by Unilateral Contract

    Florida County Suspends Impact Fees to Spur Development

    Tampa Condo Owners Allege Defects

    Architectural Firm Disputes Claim of Fault

    “Other Insurance” and Indemnity Provisions Determine Which Insurer Must Cover

    Water Is the Enemy

    Texas “your work” exclusion

    Homebuilding on the Rise in Nation’s Capitol

    Florida “get to” costs do not constitute damages because of “property damage”

    Appropriation Bill Cuts Military Construction Spending

    Mississippi exclusions j(5) and j(6) “that particular part”

    Insurer’s Motion for Summary Judgment Based on Earth Movement Exclusion Denied

    HOA Has No Claim to Extend Statute of Limitations in Construction Defect Case

    Tennessee Court: Window Openings Too Small, Judgment Too Large

    Supreme Court of New York Denies Motion in all but One Cause of Action in Kikirov v. 355 Realty Assoc., et al.

    Subcontractor Not Liable for Defending Contractor in Construction Defect Case

    Ghost Employees Steal Jobs from Legit Construction Firms

    Eleventh Circuit Asks Georgia Supreme Court if Construction Defects Are Caused by an "Occurrence"

    Hospital Construction Firm Settles Defect Claim for $1.1 Million

    Texas covered versus uncovered allocation and “legally obligated to pay.”

    LEED Certified Courthouse Square Negotiating With Insurers, Mulling Over Demolition

    Increased Expenditure on Injuries for New York City School Construction

    Environment Decision May Expand Construction Defect Claims

    Water Drainage Case Lacks Standing

    Timing of Insured’s SIR Payment Has No Effect on Non-Participating Insurer’s Equitable Contribution to Co-Insurer

    No Coverage for Negligent Misrepresentation without Allegations of “Bodily Injury” or “Property Damage”

    Insurance Firm Defends against $22 Million Claim

    The Colorado Court of Appeals Rules that a Statutory Notice of Claim Triggers an Insurer’s Duty to Defend.

    Texas “Loser Pays” Law May Benefit Construction Insurers

    Florida: No Implied Warranties for Neighborhood Improvements

    Discovery Ordered in Nevada Construction Defect Lawsuit

    Insurer’s Discovery Requests Ruled to be Overbroad in Construction Defect Suit

    Crane Dangles and So Do Insurance Questions

    Condo Board May Be Negligent for not Filing Construction Defect Suit in a Timely Fashion

    MGM Seeks to Demolish Harmon Towers

    Harmon Tower Construction Defects Update: Who’s To Blame?

    Seven Tips to Manage Construction Defect Risk

    Harmon Towers Duty to Defend Question Must Wait, Says Court

    Florida trigger

    Surveyors Statute Trumps Construction Defect Claim in Tennessee

    Construction Workers Unearth Bones

    Preparing For the Worst with Smart Books & Records

    Louisiana Politicians Struggle on Construction Bills, Hospital Redevelopment

    Construction Law Client Alert: California Is One Step Closer to Prohibiting Type I Indemnity Agreements In Private Commercial Projects

    Good Signs for Housing Market in 2013

    Ensuing Loss Found Ambiguous, Allowing Coverage

    One World Trade Center Due to Be America’s Tallest and World’s Priciest

    Former New York Governor to Head Construction Monitoring Firm

    Lien Claimant’s Right to Execute against Bond Upheld in Court of Appeals

    BUILD Act Inching Closer To Reality

    Driver’s Death May Be Due to Construction Defect

    Firm Sued For Construction Defects in Parking Garage

    Plaintiffs In Construction Defect Cases to Recover For Emotional Damages?

    State Audit Questions College Construction Spending in LA

    New Washington Law Nixes Unfair Indemnification in Construction Contracts

    Insurer Rejects Claim on Dolphin Towers

    Legislatures Shouldn’t Try to Do the Courts’ Job

    Building Boom Leads to Construction Defect Cases

    District Court Awards Summary Judgment to Insurance Firm in Framing Case

    Florida Construction Defect Case Settled for $3 Million

    OSHA Extends Delay of Residential Construction Fall Protection Requirements

    Construction Defect Claim Did Not Harm Homeowner, Court Rules

    Ninety-Day Extension Denied to KB Home in Construction Defect Insurance Claim

    Water District Denied New Trial in Construction Defect Claim

    Texas Law Bars Coverage under Homeowner’s Policy for Mold Damage

    School District Marks End of Construction Project by Hiring Lawyers

    Georgia Law: “An Occurrence Can Arise Where Faulty Workmanship Causes Unforeseen or Unexpected Damage to Other Property”

    Tacoma Construction Site Uncovers Gravestones

    Nevada Construction Defect Lawyers Dead in Possible Suicides

    Colorado Statutes of Limitations and Repose, A First Step in Construction Defect Litigation

    South Carolina “occurrence” and allocation

    Lockton Expands Construction and Design Team

    General Contractor/Developer May Not Rely on the Homeowner Protection Act to Avoid a Waiver of Consequential Damages in an AIA Contract

    Court Consolidates Cases and Fees in Soil Construction Defect Case

    Is Construction Heading Off the Fiscal Cliff?

    Federal Court Denies Summary Judgment in Leaky Condo Conversion

    Safer Schools Rendered Unsafe Due to Construction Defects

    Lien Law Unlikely To Change — Yet

    Contractor Sues License Board

    Parking Garage Collapse May Be Due to Construction Defect

    Homeowner Loses Suit against Architect and Contractor of Resold Home

    California Construction Bill Dies in Committee

    Arizona Contractor Designs Water-Repellant Cabinets

    Construction Defects Leave Animal Shelter Unusable

    Architect Not Responsible for Injuries to Guests
    Corporate Profile

    WAKEFIELD RHODE ISLAND CONSTRUCTION EXPERT WITNESS
    DIRECTORY AND CAPABILITIES

    The Wakefield, Rhode Island Construction Expert Witness Group at BHA, leverages from the experience gained through more than 5,500 construction related expert witness designations encompassing a wide spectrum of construction related disputes. Leveraging from this considerable body of experience, BHA provides construction related trial support and expert services to Wakefield's most recognized construction litigation practitioners, commercial general liability carriers, owners, construction practice groups, as well as a variety of state and local government agencies.









    Construction Expert Witness News & Info
    Wakefield, Rhode Island

    Construction Suit Ends with Just an Apology

    February 10, 2012 — CDJ Staff

    After suing a contractor for failing to complete the remodeling of their home, an Orange County couple has settled for an apology. Douglas J. Pettibone represented the contractor, who had lost his business after a broken neck, multiple surgeries, and an addiction to pain medicine. Mr. Pettibone represented his client pro bone. The case was settled in arbitration by JAMS.

    Mr. Pettibone noted that his client gave “a heartfelt and very moving apology.” The remodeling was completed by another contractor, two years after Thorp Construction stopped work on the project. After the apology, the case was dismissed.

    Read the full story…


    Appeals Court Reverses Summary Judgment over Defective Archway Construction

    February 10, 2012 — CDJ Staff

    A judge has ruled that a plaintiff can go forward with her suit that she was injured by a defective archway during a birthday party. A three-judge panel of the California Court of Appeals issued this ruling on January 23, 2012, in the case of Trujillo v. Cosio.

    Ms. Trujillo attended a birthday party at the home of Maria Cosio and Joel Verduzco. A piñata was hung between a tree and a brick archway. Ms. Trujillo went to get candy that had fallen from the piñata, during which the archway fell on her hand. Subsequent examination of the archway showed that it had not been “properly anchored to the supporting pillars to protect the arch from falling.”

    Ms. Cosio and Mr. Verduzco argued that they could not have been aware of the defective nature of the archway’s construction, as it had been built at the request of the prior property owner. The structure was constructed without building permits. Mark Burns, a civil engineer testifying for the plaintiff, said that “a reasonable property owner would have thoroughly tested the archway to ensure it was capable of withstanding such horizontal forces before allowing children to enter into the area.” Mr. Burns noted that twenty rope pulls would have been sufficient to demonstrate the structure’s instability.

    The trial court rejected Mr. Burn’s statements, finding that the respondents did not have any knowledge of the defect and that a visual inspection should have sufficed. The court noted that this a triable issue, whether visual inspection suffices, or whether the property owners should have done as Mr. Burns suggested and yank a rope twenty times. The court noted that “although a jury may ultimately disagree with Burn’s opinion, it was supported by sufficient foundation and was not speculative.”

    The opinion was written by Judge Flier, with Judges Rubin and Grimes concurring.

    Read the court’s decison…


    Drug Company Provides Cure for Development Woes

    November 18, 2011 — CDJ Staff

    Vertex Pharmaceuticals is poised to become the holder of Boston’s biggest commercial lease, paying $72.5 million for 1.1 million square feet on Boston’s waterfront. Vertex’s new buildings are still under construction, but the plans have spurred other development in the Fan Pier area, according to the New York Times. The Times quotes Mary A. Burke, a senior economist at the Federal Reserve Bank of Boston that the Vertex project gives “a big push” to the “momentum for economic growth.”

    The Fallon Company is building Vertex’s new laboratory and office space. They are separately planning to build a high-rise with 150 luxury condominium units. According to Joseph Fallon, the chief executive and president of the Fallon Company, there is already a waiting list of 50 buyers for the condominiums.

    Across the street from the Vertex site, a group including Morgan Stanley and Boston Global Investors is planning a 23-block mixed use project that would include 1.2 million square feet of retail space. Additionally, the New England Development and the Hanover Group is building a 356-unit apartment building at the adjacent Pier 4.

    Read the full story…


    Fire Reveals Defects, Appeals Court Affirms Judgment against Builder

    July 10, 2012 — CDJ Staff

    The Arizona Court of Appeals has ruled in the case of Simms v. Nance Construction. After a fire damaged his home, Jerry Simms discovered some construction defects in the work of the builder, Nance Construction. Nance Construction completed the home in 2000 and it was damaged by fire in 2001. In the course of Simms’ suit against his neighbor, “defense experts opined both that Dusty Creek had negligently repaired the damage to Simms’ residence and that many defects found in the houses were the result of defects in the original construction.” Nance offered to make roof repairs. Simms responded with a list of “numerous construction defects,” stating this was “not a comprehensive and final list of items.” Nance offered to repair some while disputing others. Simms entered a lawsuit against Nance and other parties.

    Nance first sought a summary judgment, “asserting that Simms had failed to adequately disclose the repairs for which he sought to hold Nance responsible.” The court denied this. It also would not allow Nance to introduce evidence that Simms had been denied a license by the Arizona Department of Gaming over “questionable business practices, illegal activities, and financial transactions with a person purportedly involved in organized crime.”

    During the suit, Simms contracted with Advanced Repair Technologies “for repairs that included a complete remodel of the roof and the exterior stucco system.” Nance later claimed that the cost of ART’s repair was unreasonable, claiming that it should have cost about $600,000 instead of the $1.5 million for which Simms contracted. The jury found against Nance, with a judgment of $870,200 of which half was due to the roofing subcontractor.

    After the verdict, Nash moved for a new trial, stating that the jury should have heard expert testimony on whether the contract price was reasonable. Nance also “argued that the trial court had erred in refusing to allow Nance to impeach Simms’ credibility with his purported prior acts of dishonesty.” These motions were denied and Nance appealed.

    The appeals court upheld the trial court on all counts. The court found that, despite the contention made by Nance, the jury had sufficient information to determine if the cost of the repairs were reasonable. The court also found that Simms had given Nance an opportunity to propose repairs. The law, however, “does not require the Plaintiff to accept an offer for repairs,” adding that “the record makes clear that the parties were far apart in their belief of the nature of repairs necessary.” Nor did the court find that Nance should have been allowed to introduce evidence to impeach Simms’ credibility.

    Although judgment of the lower court was affirmed, the court took the discretion to decline to award attorneys’ fees to Simms, although he was awarded costs.

    Read the court’s decision…


    New Jersey Court Rules on Statue of Repose Case

    May 26, 2011 — CDJ Staff

    A three-judge panel issued a per curium ruling on May 23 in Fairview Heights Condo. v. Investors (N.J. Super., 2011), a case which the members of a condominium board argued: “that the judge erred by: 1) dismissing plaintiff’s claims against RLI based upon the statute of repose; 2) dismissing the breach of fiduciary duty claims against the Luppinos based upon a lack of expert opinion; 3) barring the testimony of Gonzalez; and 4) barring the May 23, 1989 job site report.” The court rejected all claims from the condominium board.

    The court found that the building must be unsafe for the statute of repose to apply. They noted, “the judge made no findings on whether the water seepage, or the property damage caused by such seepage, in any way rendered the building, or any of the units, unsafe.” Further, “without a specific finding on the question of whether the defects had rendered the building ‘unsafe,’ defendants were not entitled to the benefit of the ten-year statute of repose.“

    On the second point, the court also upheld the lower court’s findings regarding the management company:

    “The report submitted by Berman establishes that the EIFS product was defective in its design and would therefore have failed from the outset. The defects in that product were, according to Berman, not prone to repair or other mitigation. Therefore, even if defendants did not appropriately inspect or repair the EIFS, their failure to do so would have had no impact on the long-term performance of the EIFS exterior cladding. As plaintiff failed to raise a genuine issue of material fact on these questions, the judge properly granted summary judgment to the Luppinos on plaintiff’s breach of fiduciary duty claim.”

    On the final two points, the judges noted “plaintiff maintains that the judge committed reversible error when he excluded the Gonzalez certification and the 1989 job site report prepared by Raymond Brzuchalski.” They saw “no abuse of discretion related to the exclusion of the Gonzalez certification, and reject plaintiff’s arguments to the contrary.” Of the job site report, they found, “no abuse of discretion in the judge's finding that the Brzuchalski 1989 job site report did not satisfy the requirements of N.J.R.E.803(c)(6).”

    Read the court’s decision


    A Call to Washington: Online Permitting Saves Money and the Environment

    October 28, 2011 — Douglas Reiser, Builders Counsel

    Here’s some good news for Oregon contractors:  Electronic Permitting is here. That’s right, no more standing in line with folders full of printed submittals and waiting all day for your permit. The click of a few buttons and you are in business. Great news, right? Unfortunately, Oregon isn’t sharing that celebration with Washington. So I say - why not?

    Last week, the State of Oregon released its new ePermitting online interface. The website allows contractors, owners and even local building departments to create an account, submit building plans and procure permits. With your account, you can track the progress of submissions, print documents and get posting information.

    The state ran a limited test version in the City of Florence since 2009, working out the kinks. Perhaps the most impressive result of the new system is that Oregon tackled the task of coagulating a local process into one central location.

    Read the full story...

    Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com


    Georgia Supreme Court Rules Construction Defects Can Constitute an Occurrence in CGL Policies

    April 5, 2011 — April 5, 2011 Beverley BevenFlorez - Construction Defect Journal

    Recently, the Supreme Court of Georgia reversed the decision in American Empire Surplus Lines Insurance Company v Hathaway Development Company, Inc. stating that because Whisnant’s faulty workmanship caused damage to the surrounding properties, the construction defects constituted “occurrences” under the Commercial General Liability (CGL) policy. Unlike the South Carolina Supreme court ruling in the case of Crossman Communities v Harleysville Mutual, the Georgia Supreme Court stated that an accident can happen intentionally if the effect is not the intended result.

    Interestingly, the only dissenting judge, J. Melton, disagreed with his colleagues on the basis that “although the term ‘accident’ is not specifically defined in the policy, it is axiomatic that an ‘accident’ cannot result from ‘intentional’ behavior.” It is clear that what constitutes an occurrence in CGL policies is still being hotly debated.

    Read the full story...


    Construction Defects in Home a Breach of Contract

    September 9, 2011 — CDJ Staff

    The Supreme Court of North Dakota has ruled in Leno v. K & L Homes, affirming the verdict of the lower court. K & L Homes argued that district court had erred in several ways, including by refusing to instruct the jury on comparative fault, denying a request for inspection, and not allowing a defendant to testify on his observations during jury viewing.

    The Lenos purchased a home constructed by K & L Homes, after which they alleged they found cracks, unevenness, and shifting, which they attributed to improper construction. They claimed negligence on the part of K & L Homes. K & L Homes responded that the Lenos were responsible for damage to the home. The Lenos dropped their negligence claim, arguing breach of contract and implied warranties.

    Before the trial, after the discovery period had passed, K & L Homes requested to inspect the home. This was rejected by the court. Kelly Moldenhauer, the owner of K & L Homes sought to testify about his observations during the jury’s viewing of the house. The court denied this too. The jury found that K & L was in breach of contract and awarded damages to the Lenos.

    The North Dakota Supreme Court noted that K & L Homes gave “warranties that the home had been built according to local building codes and laws, and that the house was fit for its particular purpose as a residence.” The court found that a defective home breached this warranty. Further, the home violated an implied warranty of fitness.

    The district court had denied K & L’s request to inspect the home, as the discovery period had ended and it would not give the Lenos time to do further discovery of their own. At the time of the request, there was only twenty-two days before the trial. The Supreme Court ruled that this was not an abuse of discretion of the part of the district court.

    The Lenos had requested that Moldenhauer’s testimony not be permitted, as it would “have the same effect as if the court had granted K & L Homes’ pretrial request for inspection.” K & L Homes agreed to this in court, replying, “okay.”

    The decision affirms the judgment of the district court and the damages awarded to the Lenos by the jury.

    Read the court’s decision…


    Ensuing Loss Provision Does Not Salvage Coverage

    December 9, 2011 — Tred R. Eyerly, Insurance Law Hawaii

    Water intrusion caused by a construction defect was not covered under the all risk policy’s ensuing loss provision. See Friedberg v. Chubb & Son, Inc., 2011 U.S. Dist. LEXIS 123582 (D. Minn. Oct. 25, 2011).

    Extensive water damage was discovered in the insureds’ home when a small hole in the exterior wall was being repaired. Chubb’s adjuster and an expert found water intrusion causing rot, mold, and damage to the home’s wood framing and insulation. Chubb denied coverage because water intruded through the roof and wall, resulting in gradual deterioration. The insureds filed suit.

    The policy excluded coverage for construction defects, but insured "ensuing covered loss unless another exclusion applies."

    The court agreed there was a prima facie case for coverage because the home suffered a physical loss.

    Read the full story…

    Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com


    One World Trade Center Due to Be America’s Tallest and World’s Priciest

    February 10, 2012 — CDJ Staff

    As One World Trade Center rises, so does the price tag. After construction delays and cost overruns, the cost of the building at the site of the September 11 attacks has risen to $3.8 billion. Part of the expense of the skyscraper is the heavily reinforced base of the building. The elevator shafts are also heavily reinforced, all part of guarding against future terrorist attacks.

    In comparison, the world’s tallest tower, the Burj Khalifa in Dubai, cost only $1.5 billion, less than half the cost of One World Trade Center. As a result, the Port Authority does not see the building as being profitable in near future. In order to fund it, the agency is raising tolls on bridge and tunnel traffic.

    Currently, about the half the unfinished building is leased. Construction is expected to conclude in 2013.

    Read the full story…


    Godfather Charged with Insurance Fraud

    July 1, 2011 — CDJ Staff

    Texas-based Godfather Construction is a recipient of a fraud suit from the Cook County state attorney’s office. The firm incorporated in Illinois in April 2010, moving there to do business after storms damaged homes in the Chicago suburbs, according to a report in the Chicago Tribune. The state attorney alleges that Godfather brought unlicensed out-of-state workers and the work they performed was “incomplete or shoddy.” Godfather is claimed to have received about $60,000 from Illinois homeowners. The prosecutors are seeking restitution for Godfather’s clients and seek to forbid the firm from doing business in Illinois.

    Read the full story…


    Construction Defects: 2010 in Review

    July 10, 2012 — CDJ Staff

    Candace Matson, Harold Hammersmith, and Helen Lauderdale, all of Sheppard Mullin, recently looked at design and construction defect litigation in 2010. They look at three California construction law cases. In one prominent case, the developer’s claims were barred under California law. However, the court did allow a claim for breach of the duty to defend.

    In a second case, the California Supreme Court ruled that a duty to defend is separate from a duty to indemnify. A developer sought to include its engineering subcontractor in a suit. The subcontractor unsuccessfully argued that it had no duty to defend as the homeowners had not sued it.

    The third case involved a lawyer who had represented a homeowner accused a libel against a construction firm and then later represented one of the subcontractors the firm had employed. The California Court of appeals concluded that there was no conflict of interest and so the contractor could not disqualify the subcontractor’s lawyer.

    Read the full story…


    Policing Those Subcontractors: It Might Take Extra Effort To Be An Additional Insured

    June 14, 2011 — Douglas Reiser, Builders Council Blog

    I just came across a case that I think truly paints the insurance dilemma for contractors. Thanks to this recent Illinois case, I don’t have to make up any factual scenarios—so kudos to Attorney Robert Boylan for posting it.

    In reading over my RSS feeds this weekend, I noticed a great writeup on long-time blogger Josh Glazov’s Construction Law Today. Attorney Robert Boylan’s post describes a recent Illinois case where a general contractor was denied its additional insured status on a second-tier subcontractor’s insurance. The reason for the denial: the general contractor failed to procure an agreement in writing with the second-tier subcontractor, requiring it to be listed as an additional insured.

    Read the full story…

    Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com


    Insurers Reacting to Massachusetts Tornadoes

    August 11, 2011 — CDJ Staff

    The Patriot-Ledger reports that insurers could pay out as much as $200 million to cover homes damaged or destroyed in the tornadoes that hit central and southern Massachusetts in June, 2011. Joseph Murphy, Commissioner of the State Division of Insurance didn?t foresee problems with insurers covering these claims. “At this point, there doesn’t seem to be any one company overexposed in that area,” he told the Patriot-Ledger.

    Insurance executives did not think the tornadoes would cause them to raise rates. Steve Chevalier, CEO of NLC Companies, said, “it’s a major event for those impacted by it, but it’s not close to a financial hit to us.”

    One insurer noted that the winter weather generated more claims; however the cumulative value of those claims was $15 million.

    Read the full story…


    Couple Sues Attorney over Construction Defect Case, Loses

    June 10, 2011 — CDJ Staff

    The California Court of Appeals has ruled against a couple who sued their lawyer, after they were unhappy with the results of a construction defect case. Craig and Jeanne Petrik sued Mahaffey and Associates for legal malpractice and breach of contract. Their lawyer, Douglas L. Mahaffey, had settled their case for $400,000. The Petricks claimed Mahaffey did not have the authority make an offer to compromise.

    In the original case, Mahaffey held back the $400,000 awarded in the settlement until he and the Petricks came to terms on how much of that was owed to Mahaffey. The lower court concluded that the Petricks were due $146,323,18. The jury did not agree with the Petrik’s claim that conditions had been met in which Mahaffey would not be charging them costs.

    Judges O’Leary and Ikola wrote the opinion, with the third judge on the panel, Judge Bedworth offering a dissent only on their view of the cost waiver clause.

    Read the court’s opinion


    Construction Defect Not a RICO Case, Says Court

    August 4, 2011 — CDJ Staff

    The US District Court of North Carolina has rejected an attempt by a homeowner to restart her construction defect claim by turning it into a RICO lawsuit. Linda Sharp, the plaintiff in the case of Sharp v. Town of Kitty Hawk, attempted to amend a claim under the Racketeer Influenced and Corrupt Organizations Act (RICO) and argued that her case belonged in the federal courts.

    Ms. Sharp sued in November, 2010 claiming construction defects. She sued in federal court, although the court noted that as she and most of the defendants are citizens of North Carolina, the state court would have been the appropriate jurisdiction. Further, the court noted that one federal claim Sharp made was dismissed with prejudice, leaving only the state law claims. These the court dismissed without prejudice, declining to exercise jurisdiction over North Carolina law.

    After the dismissal, Ms. Sharp attempted to amend her complaint after the deadline. To do so, according to the court, she would be required to obtain consent from defendants or leave of the court. She did neither.

    In his opinion, Judge W. Earl Britt rejected her motion for leave to amend. He also granted the defendants’ motion to dismiss. The clerk was directed to close the case.

    Read the court’s decision…


    Nevada Assembly Bill Proposes Changes to Construction Defect Litigation

    April 14, 2011 — April 14, 2011 Beverley BevenFlorez - Construction Defect Journal

    Assemblyman John Oceguera has written a bill that would redefine the term Construction Defect, set statutory limitations, and force the prevailing party to pay for attorney’s fees. Assembly Bill 401 has been referred to the Committee on Judiciary.

    Currently, the law in Nevada states that “a defect in the design, construction, manufacture, repair or landscaping of a new residence, of an alteration of or addition to an existing residence, or of an appurtenance, which is done in violation of law, including in violation of local codes or ordinances, is a constructional defect.” However, AB401 “provides that there is a rebuttable presumption that workmanship which exceeds the standards set forth in the applicable law, including any applicable local codes or ordinances, is not a constructional defect.”

    The Nevada courts may award attorney fees to the prevailing party today. However, AB401 mandates that attorney fees must be awarded, and the exact award is to be determined by the Court. “(1) The court shall award to the prevailing party reasonable attorney’s fees, which must be an element of costs and awarded as costs; and (2) the amount of any attorney’s fees awarded must be determined by and approved by the court.”

    AB401 also sets a three year statutory limit “for an action for damages for certain deficiencies, injury or wrongful death caused by a defect in construction if the defect is a result of willful misconduct or was fraudulently concealed.”

    This Nevada bill is in the early stages of development.

    Read the full story...

    Homeowners Not Compelled to Arbitration in Construction Defect Lawsuit

    January 6, 2012 — CDJ Staff

    A California appeals court has ruled that developers cannot enforce CC&Rs in a case where a developer cited an arbitration clause it had inserted into the CC&R. The homeowners are alleging construction defect and wished to sue the developer who claimed a right to this under the CC&Rs.

    The Marina del Rey Argonaut reports that particular appeal dealt only with whether the developer could compel arbitration. The underlying construction defect issues will subsequently have to be determined at trial.

    The attorney for the homeowners’ association, Dan Clifford, noted that “arbitration has to be agreed to by both parties.” The covenant was drafted by the developer and in addition to requiring arbitration, it had a clause that it could not be amended without the consent of the developers. The court ruled that CC&Rs “can be enforced only by the homeowners association, the owner of a condominium or both.”